2017 Road Resurfacing


2017 public improvement project

​Contact Information

Project Manager: Adriana Webb                                           Capital Project Senior Manager: Robert Steele

(847) 904-4325                                                                                 (847) 904-4423

awebb@glenview.il.us                                                                    rsteele@glenview.il.us

Project description

The proposed improvements consist of the repair of existing underground utility (sanitary and storm sewer) sections, repair of existing utility structures, partial or full removal of existing pavement, placement of new hot-mix asphalt,  and replacement of deteriorated sections of sidewalk and curb and gutters.  The project scope also includes partial resurfacing of damaged pavement sections in various locations, as per the Minor Area Repair Strategy (MARS) program. Please see the table below for the areas that will be included as part of this project.

Street Name                                                                                                 Limits

Rolling PassGlenview RoadNorth cul-de-sac
Keenan LanePfingsten RoadEast end
Halina DriveKeenan LaneNorth end
Pfingsten RoadEast Lake AvenueKnight/south end
Sheryl  LaneHarrison StreetCovert Road
Somerset DriveEast Lake AvenueSouthwest cul-de-sac
Oxford LaneSomerset DriveNorth cul-de-sac
Rugen RoadBette LanePfingsten Road
​Springdale Avenue/Bette Lane​Gloria Court

​East of Rugen Road

​Concord Lane​Sanders Road​cul-de-sac
Avalon CourtConcord Lanecul-de-sac
Cambria Court​​Concord Lane​cul-de-sac
​Beech Drive (MARS)​Heatherfield​West end
Astor Court (MARS)​​Pfingsten Road​cul-de-sac
​Myrtle Parkway (MARS)​Landwehr Road​East end
​Central Parkway (MARS)​Waukegan Road​East end

Project information and updates

Contractor:

Budget:

Permit number:

Weekly updates can be found on the project blog when started.


Tentative schedule:

  • Start of construction:
  • Asphalt surface course completion:
  • Final restoration: 

 

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.