The Village of Glenview

Becker Road resurfacing


2017 public improvement project

​​Contact information

Project Manager: James Tigue                                            Capital Project Senior Manager: Robert Steele

(847) 904-4334                                                                              (847) 904-4423

jtigue@glenview.il.us                                                                   rsteele@glenview.il.us

 

Civil Engineer: Adriana Webb

(847) 904-4414

awebb@glenview.il.us

Project description

Replacement and rehabilitation of storm sewer along with roadway resurfacing.

Project information and updates

Contractor: H. Linden and Sons Sewer and Water Inc.

Budget:  $548K

Project number: E2015-26

Project Blog:  https://beckerroadimprovements.blogspot.com/ 

Project map: Click here

Resident Preconstruction Presentation May 3, 2017

Tentative schedule

  • May 8, 2017 – Contractor utility locates, tree protection, storm sewer televising
  • June 5, 2017 – Anticipated start of construction
    • Stage 1 – Storm sewer improvements
    • Stage 2 – Pavement resurfacing
    • Stage 3 – Driveway and parkway restoration
  • July 28, 2017 – Anticipated substantial project completion (weather permitting)

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.