Queens Lane water main


2017 public improvement project

​Contact information

Project Manager: James Tigue                                    Capital Project Senior Manager: Robert Steele

(847) 904-4334                                                                      (847) 904-4423

jtigue@glenview.il.us                                                           rsteele@glenview.il.us

 

Civil Engineer: Adriana Webb

(847) 904-4414

awebb@glenview.il.us

Project description

Installation of water main, drainage enhancements within the right of way, and road reconstruction.

Project information and updates

Contractor: H. Linden and Sons Sewer and Water Inc.

Budget:  $380K

Project number: E2015-56

Project Blog: http://queenswatermain.blogspot.com/

Project map: Click here

Resident Preconstruction Open House Presentation May 3, 2017

Tentative schedule

  • May 8, 2017 – Contractor utility locates, tree protection, storm sewer televising
  • May 15, 2017 – Anticipated start of construction
    • Stage 1 – Underground work: water main installation and storm sewer improvements
    • Stage 2 – Pavement removal
    • Stage 3 – Full pavement reconstruction
    • Stage 4 – Driveway and parkway restoration
  • July 28, 2017 – Anticipated substantial project completion (weather permitting)

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.