Shermer Road Viaduct Updates

A Union Pacific freight train hauling coal from Wyoming to Wisconsin derailed Wednesday afternoon, July 4, 2012, on a viaduct over Shermer Road, between Willow Road and Holste Road in Glenview. The viaduct subsequently collapsed. Cleanup crews on Thursday morning, July 5, 2012, discovered a car buried beneath the rubble. The driver, Burt Lindner, and the passenger, his wife, Zorine, both of Glenview, were killed.
On this page will be posted updates, information and schedules regarding construction of the replacement viaduct.
May 17, 2013 -- A new railroad bridge to replace the viaduct could be in place by the end of the this year, under an expedited schedule released recently by Union Pacific Railroad.
While businesses have remained open along Shermer Road between West Lake Avenue and Willow Road, through traffic remains blocked at the site of the collapse. Union Pacific intends to select a contractor at the end of May, with foundation and other construction taking place at the site between July and November. At the same time, work off site will continue on constructing the 149-foot-long steel span. The span could be installed by early December.
Still to be determined is the condition of Shermer Road underneath the crushed rocks that have served as a temporary rail bed embankment for freight train traffic.
The Villages of Glenview and Northbrook were originally notified that the permanent replacement viaduct would likely take until late 2014 to complete. By fast-tracking the state permitting process and material procurement, Union Pacific has been able to shorten the schedule.
--------------------------------------------------------------------------------------------------------------------------
October 12, 2012 -- Now that a Memo of Understanding between the Villages of Glenview and Northbrook, Union Pacific Railroad and the Illinois Department of Transportation has been finalized, work has begun on a few temporary measures aimed at alleviating the impact of the extended through-closure of Shermer Road while the railroad bridge is being replaced with a wider, safer viaduct.
The temporary bridge put in place after the July 4 train derailment and bridge collapse blocks Shermer Road south of Willow Road. Businesses north and south of the bridge site are open.
A temporary traffic signal is being installed at West Lake Avenue and Shermer Road. This signal will help traffic flow until a temporary connection from Shermer Road to Patriot Boulevard via Old Willow Road is constructed, which is estimated to be completed by the end of November. The temporary connection will be removed once a new bridge is constructed, which is currently estimated to take 18 to 24 months.
View these projects on this map. Read about these projects.
------------------------------------------------------------------------------------------------------------------------
August 24, 2012 -- The Glenview and Northbrook Village Boards of Trustees have scheduled a
joint meeting at 7:30 p.m. Tuesday, August 28, to review a Memorandum of Understanding with Union Pacific Railroad and the Illinois Department of Transportation for a permanent bridge over Shermer Road to replace the viaduct that collapsed July 4.
(UPDATE: August 28, 2012 -- Both boards passed resolutions approving the Memorandum of Understanding subject to final Village Attorney review and approval. The meeting can be viewed here.)
The meeting is scheduled to take place at Glenview Village Hall, 1225 Waukegan Road, in the Board Room. It can be viewed live on GVTV (cable channel 6 or 17), AT&T U-verse channel 99 PEG and streamed live on our website.
Key terms of the agreement up for discussion:
- Union Pacific will fund and build an approximately 149-foot-long bridge with a 57-foot clear span to provide for three 12-feet-wide traffic lanes, a 10-foot-wide bike path, a 7-foot-wide bike path and four feet of curbing, estimated to cost $10 million.
- Union Pacific will fund construction of a temporary connection to Patriot Bouelvard via Old Willow Road to facilitate traffic from businesses south of the closed bridge to detour to Willow Road, at a cost of up to $275,000.
- Union Pacific will fund construction of a temporary traffic control signal at West Lake Avenue and Shermer Road to improve traffic flow, at a cost of up to $57,000.
- Glenview, Northbrook and the Illinois Department of Transportation will be reponsible for funding and building the roadway improvements at a future point in time that will be compliant with IDOT’s Complete Streets guidelines.
------------------------------------------------------------------------------------------------------------------------
August 24, 2012 -- Beginning today, freight operations will increase the speed on the Milwaukee Subdivision at Shermer Road from 10 mph to 25 mph, according to Adrian Guerrero, director of Public Affairs for Union Pacific Railroad.
The Federal Railroad Administration completed an inspection this week at the site, and approved returning the track speed to its original 50 mph. Union Pacific intends to gradually increase the speed up to the approved level.
-------------------------------------------------------------------------------------------------------------------------
July 17, 2012 -- Representatives of Union Pacific Railroad (UP)
discussed the circumstances 
surrounding the July 4, 2012 freight train derailment and viaduct collapse on Shermer Road at a community meeting Monday, July 16, 2012, at the request of Glenview and Northbrook village officials.
More than two dozen Glenview and Northbrook residents asked questions about the July 4 accident, its relationship to earlier derailments near the same site, overall safety of the track and other railroad bridges through Glenview and Northbrook, and the necessity for freight trains to sound their horns overnight as they traverse the repair site.
Here’s some of the information UP related:
- The July 4 derailment was due to an overheated track expanding and buckling. It was described as a heat-related anomaly to the track that developed underneath the train as it approached the bridge from the south. A consulting engineering firm hired by UP determined there was no structural problem with the bridge. It was simply downstream from where the derailment occurred, which forced the rail cars to jackknife on the bridge, leading to its collapse.
- Inspectors traverse the rail corridor every day during hot weather looking for kinks in the rail. On July 4, a person responsible for maintaining the signal system noticed "something that didn’t look exactly right” and called an expert to have a second look. "We don't believe what he saw was severe enough to cause him to do anything more than he did," said David Connell, UP's vice president of engineering. The expert arrived at about the same time the accident occurred.
- Having trains travel at slower speeds on hot days would not have prevented the bridge collapse.
- The temporary embankment of crushed concrete built across Shermer Road to support the track so trains can continue to run is inspected weekly. Soil borings taken Friday, July 13, indicate there is a strong base below it.
- The November 1, 2009 derailment that occurred a couple hundred feet north of the Shermer Road viaduct on Union Pacific track involved a train operated by another company. A mechanical failure caused it to derail as a train was passing in the opposite direction.
- Work on the Shermer Road bridge that closed the roadway from June 27 to October 5, 2011 had been planned prior to the 2009 derailment to address concrete abutment concerns and replace beams that sit on top of the concrete piers.
- Although no crews have been working overnight at the repair site since Saturday, July 7, residents reported passing trains have been sounding their horns throughout the night. UP asked that residents note the time the train passed and report the whistle blowing by calling 1-888-877-7267.
--------------------------------------------------------------------------------------------------------------------------
July 10, 2012 -- At the request of Glenview and Northbrook officials, representatives of Union Pacific Railroad have agreed to appear at a community meeting to explain the circumstances of the July 4 derailment and viaduct collapse on Shermer Road that killed two Glenview residents. The UP officials can also discuss the safety history of the viaduct, the site of two prior derailments; information and schedules regarding construction of the replacement viaduct; and the condition of the track and other rail bridges in Glenview.
The meeting has been scheduled at 7 p.m. Monday, July 16, at
Glenbrook North High School, 2300 Shermer Road, in the Sheely Center for the Performing Arts.
Here is the detour map for motorists while Shermer Road is blocked. UP officials have estimated that it will take several months to design, procure and install a new, permanent viaduct. In the meantime, a temporary rail bed embankment constructed by UP is facilitating freight train traffic. At the request of Glenview and Northbrook officials, a Federal Railroad Administration inspector on Friday, July 6, 2012, examined the structure and confirmed the rail was safe to operate with temporary speed restrictions of 10 miles per hour.
To insure worker safety, the UP has been requiring approaching trains to blow their whistles while workers restore bridge, track and signal service. The horns will be sounded until that work is completed. (Horn blowing guidelines can be
found here.)
Residents and businesses can file claims relating to the derailment, viaduct collapse and temporary closure of Shermer Road between Holste Road and Willow Road by contacting Jeff Alaniz, UP’s claim representative, at (312) 777-2028 or by email to
jaalaniz@up.com.
UNION PACIFIC'S INSPECTION REPORTS
DOCUMENTS