The Village of Glenview

2020 street resufacing projects


2020 public improvement project

​Contact Information

Project Manager: Tom Hagerty
(847) 904-4421​
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us                                                                  

Project description

The proposed improvements consist of the repair of existing underground utility (sanitary and storm sewer) sections, repair of existing utility structures, partial or full removal of existing pavement, placement of new hot-mix asphalt,  and replacement of deteriorated sections of sidewalk and curb and gutters.  The project scope also includes partial resurfacing of damaged pavement sections in various locations, as per the Minor Area Repair Strategy (MARS) program. See the table below for the areas that will be included as part of this project.  

Street Name                                                                                                 Limits

Pinehurst DriveRoosevelt Avenuenorth end
Westfield LaneMiller Driveeast cul-de-sac
Miller DrivePfingsten RoadWestfield Lane
Kittyhawk LaneMonterey DriveIndependence Avenue
Midway LaneMonterey DriveIndependence Avenue
Westleigh Drive (Phase 1)Westleigh DriveWestleigh Drive South
Aberdeen DriveWestleigh DriveSummit Drive
Aberdeen Drive NorthAberdeen DriveAberdeen Drive
Camden Drive​Aberdeen Drive

Summit Drive

Wildeberry Drive​Aberdeen Drive​Aberdeen Drive
Independence Avenue​Patriot Boulevard

​Kittyhawk Lane

Bennington Court​Independence Avenue​south end
Redwood Lane​Coronet Road​east end
​Edgewood Lane​Coronet Road​east end
Lindenwood Lane​Rugen Road​east end
Laramie Avenue​Wilmette Avenue​Glenview Road
Long Road​Wilmette Avenue​Glenview Road
​Leamington Avenue​Wilmette Avenue​Beverly Lane
Beverly Lane​Long Road​Laramie Avenue
​Mulberry Court​Long Road​Laramie Avenue
Saranac Lane​Indian Ridge Drive​Indian Ridge Drive

Project information and updates

Contractor: TBD

Budget: 

Project Number:

Project Blog:

Location map: Click here

Tentative schedule

  • Bid opening --
  • Bid award --
  • IDOT approval of contract --
  • Approximate start of construction --
  • Anticipated completion of construction --

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
2020 Street resurfacing10/24/2020Published10/16/2020 9:33 AMTom Hagerty 847-904-4421Completed

​This past week the contractor finished the asphalt patching on Burton Terrace and the landscape restoration on all streets.

During the week of October 19, the contractor will complete various small remaining items. The contractor is also tentatively scheduled to begin the minor asphalt repairs (MARS) patching towards the end of the week. The MARS patching includes 9,500 square yards of asphalt patching. 

Good News! The project is completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.



10/18/2020Project Completion
  
2020 Street resurfacing10/17/2020Published10/9/2020 1:30 PMTom Hagerty 847-904-4421On Schedule

​This past week the contractor finished the asphalt patching on Brett Lane and the landscape restoration on Group B streets. The contractor also completed the storm sewer upgrades on Burton Terrace. 

During the week of October 12, the contractor will continue the parkway restoration on Brett Lane and Burton Terrace. 

Group A includes Saranac Lane, Lindenwood Lane, Miller Drive, Westfield Lane, Pinehurst Drive, Kittyhawk Lane, Midway Lane, Independence Avenue, Bennington Court, Westleigh Drive, Aberdeen Drive, and Camden Drive. 

Group B includes, Wildberry Drive, Edgewood Lane, Redwood Lane, Laramie Avenue, Leamington Avenue, Beverly Lane, Mulberry Court, Long Road, Brett Lane, Burton Terrace, and Nottingham Alley. 

Please note that this project includes multiple streets throughout the Village and because of this you will not see consistent work on your street from start to finish. Instead, the contractor plans to complete each phase of this project on all streets before moving to the next phase. We know that construction can be an interruption and we appreciate your patience throughout this project. 



10/11/2020Phase 3 - Parkway Restoration
  
2020 Street resurfacing10/10/2020Published10/2/2020 11:38 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor removed and replaced the marked concrete curb and sidewalk and continued the rain garden work on Brett Lane. Additionally, the contractor finished the underground improvements on Nottingham Alley, removed the existing aggregate pavement, and placed the new asphalt on the alley. 

During the week of October 5, the contractor will complete the asphalt patching on Brett Lane and continue the landscaping work on group B streets. Additionally, the contractor is tentatively scheduled to begin the underground improvements on Burton Terrace. 
 
Group A includes Saranac Lane, Lindenwood Lane, Miller Drive, Westfield Lane, Pinehurst Drive, Kittyhawk Lane, Midway Lane, Independence Avenue, Bennington Court, Westleigh Drive, Aberdeen Drive, and Camden Drive. 

Group B includes, Wildberry Drive, Edgewood Lane, Redwood Lane, Laramie Avenue, Leamington Avenue, Beverly Lane, Mulberry Court, Long Road, Brett Lane, Burton Terrace, and Nottingham Alley. 

Please note that this project includes multiple streets throughout the Village and because of this you will not see consistent work on your street from start to finish. Instead, the contractor plans to complete each phase of this project on all streets before moving to the next phase. We know that construction can be an interruption and we appreciate your patience throughout this project. 



10/4/2020Phase 2 - Roadway Reconstruction
1 - 3Next

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.