The Village of Glenview

2020 street resufacing projects


2020 public improvement project

​Contact Information

Project Manager: Mike DeBennette
(847) 904-4266
mdebennette@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us                                                                  

Project description

The proposed improvements consist of the repair of existing underground utility (sanitary and storm sewer) sections, repair of existing utility structures, partial or full removal of existing pavement, placement of new hot-mix asphalt,  and replacement of deteriorated sections of sidewalk and curb and gutters.  The project scope also includes partial resurfacing of damaged pavement sections in various locations, as per the Minor Area Repair Strategy (MARS) program. See the table below for the areas that will be included as part of this project.  

Street Name                                                                                                 Limits

Pinehurst DriveRoosevelt Avenuenorth end
Westfield LaneMiller Driveeast cul-de-sac
Miller DrivePfingsten RoadWestfield Lane
Kittyhawk LaneMonterey DriveIndependence Avenue
Midway LaneMonterey DriveIndependence Avenue
Westleigh Drive (Phase 1)Westleigh DriveWestleigh Drive South
Aberdeen DriveWestleigh DriveSummit Drive
Aberdeen Drive NorthAberdeen DriveAberdeen Drive
Camden Drive​Aberdeen Drive

Summit Drive

Wildeberry Drive​Aberdeen Drive​Aberdeen Drive
Independence Avenue​Patriot Boulevard

​Kittyhawk Lane

Bennington Court​Independence Avenue​south end
Redwood Lane​Coronet Road​east end
​Edgewood Lane​Coronet Road​east end
Lindenwood Lane​Rugen Road​east end
Laramie Avenue​Wilmette Avenue​Glenview Road
Long Road​Wilmette Avenue​Glenview Road
​Leamington Avenue​Wilmette Avenue​Beverly Lane
Beverly Lane​Long Road​Laramie Avenue
​Mulberry Court​Long Road​Laramie Avenue
Saranac Lane​Indian Ridge Drive​Indian Ridge Drive

Project information and updates

Contractor: TBD

Budget: 

Project Number:

Project Blog:

Location map: Click here

Tentative schedule

  • Bid opening --
  • Bid award --
  • IDOT approval of contract --
  • Approximate start of construction --
  • Anticipated completion of construction --

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
2020 Street resurfacing7/11/2020Published7/2/2020 11:34 AMTom Hagerty 847-904-4421On Schedule

Welcome to the project updates page for the Road Resurfacing Project. The contractor, Arrow Road Construction, was awarded the project.

Project updates will typically be posted on Fridays of each week. If you have any questions please feel free to contact the Project Manager, Tom Hagerty at (847) 904-4421 or at thagerty@glenview.il.us

This project consists of improving and resurfacing twenty-one (21) road sections and a total of approximately 5 miles of roadway.  The resurfacing will be split into two groups:

    • Group A – resurfacing of the western part of the town. This group includes Saranac Lane and Court, Miller Drive, Westfield Lane, Kittyhawk Lane,  Midway Lane, Independence Avenue, Bennington Court, Pinehurst Drive, and Lindenwood Lane.  This work will start the week of July 20th and is anticipated to be completed by the first week in September, weather permitting.
    • Group B  - resurfacing of the eastern part of town. This group includes, Aberdeen Drive, Camden Drive, Westleigh Drive,  Wildberry Drive, Edgewood Lane, Redwood Lane, Laramie Avenue, Lemington Avenue, Beverly Lane, Mulberry Court, and Long Road.  This work is anticipated to start in early August and will be completed in October, weather permitting.

The contractor is scheduled to begin the project the week of July 20, starting with Group A.  During this week the contractor plans to begin phase I of this project, which consists of underground storm sewer improvements.

Please note that this project includes multiple streets throughout the Village and because of this you will not see consistent work on your street from start to finish. Instead, the contractor plans to complete each phase of this project on all streets before moving to the next phase. We know that construction can be an interruption and we appreciate your patience throughout this project. 



7/5/2020Start of Construction

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.