The Village of Glenview

2021 street resurfacing projects


2021 public improvement project

​Contact Information

Project Manager: Tom Hagerty
(847) 904-4421​
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us                                                                  

Project description

The proposed improvements consist of the repair of existing underground utility (sanitary and storm sewer) sections, repair of existing utility structures, partial or full removal of existing pavement, placement of new hot-mix asphalt,  and replacement of deteriorated sections of sidewalk and curb and gutters.  The project scope also includes partial resurfacing of damaged pavement sections in various locations, as per the Minor Area Repair Strategy (MARS) program. See the table below for the areas that will be included as part of this project.  

Street Name                                                                                                 Limits

Pynsky RoadPotter Road
east end
Crescent LanePotter Road
west end
Wilmette Avenue*west end
Long Road
Saratoga LaneMonterey Drive
Kittyhawk Lane
Cabot LaneSaratoga Lane
Monterey Drive
Monterey DriveWest Lake Avenue
Independence Avenue
Westleigh Drive (south)Westleigh Drive South
Aberdeen Drive
Summit DriveWestleigh Drive South
Aberdeen Drive
Brush Hill Lane​Summit Drive

Westleigh Drive

Hill Circle
​Central Road
​north cul-de-sac
Sumac Circle​west cul-de-sac

​east cul-de-sac

Cedarwood Lane​Linden Leaf Drive
​north cul-de-sac
Fir Street​​Shermer Road
​east cul-de-sac
Ardmore Avenue​Long Road
west end
Dale Street
​Long Road
west  end

Project information and updates

Contractor: Arrow Road Construction Co. of Elk Grove Village

Budget: $1,974,294

​Location map: Click ​here

* The Village of Glenview entered into an Intergovernmental Agreement with the Village of Wilmette regarding the resurfacing of Wilmette Avenue

Tentative schedule

  • Bid awarded -- April 20, 2021
  • Pre-construction meeting -- June 1, 2021
  • Approximate start of construction -- July 15, 2021
  • Anticipated completion of construction -- September 24, 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
2021 street resurfacing9/16/2021Published9/10/2021 12:44 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor was working on final landscaping in both Group A and Group B streets which include the following:

    • Group A – resurfacing of the western part of the town. This group includes Pynsky Road, Crescent Lane, Saratoga Lane, Cabot Lane, Monterey Drive, Summit Drive, Brush Hill Lane, and Westleigh Drive.
    • Group B – resurfacing of the eastern part of town. This group includes, Wilmette Avenue, Ardmore Avenue, Dale Street, Long Road, Brook Lane, Brandon Road, Woodlawn Avenue, and Hollywood Avenue. 

 
Good News! The project is completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.​


9/10/2021Project Completion
  
2021 street resurfacing9/9/2021Published9/3/2021 2:05 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor was working on final landscaping in both Group A and Group B streets which include the following:

    • Group A – resurfacing of the western part of the town. This group includes Pynsky Road, Crescent Lane, Saratoga Lane, Cabot Lane, Monterey Drive, Summit Drive, Brush Hill Lane, and Westleigh Drive.
    • Group B – resurfacing of the eastern part of town. This group includes, Wilmette Avenue, Ardmore Avenue, Dale Street, Long Road, Brook Lane, Brandon Road, Woodlawn Avenue, and Hollywood Avenue. 

 

During the week of September 7, the contractor is scheduled to complete the landscape restoration and miscellaneous punch list work on streets in Group A and Group B.

 
Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 8 am to 5 pm on Saturdays, if necessary.
Thank you for your patience.  ​


9/3/2021Phase 3 Parkway Restoration
  
2021 street resurfacing9/2/2021Published8/27/2021 3:04 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor was working on final landscaping in both Group A and Group B streets which include the following:

    • Group A – resurfacing of the western part of the town. This group includes Pynsky Road, Crescent Lane, Saratoga Lane, Cabot Lane, Monterey Drive, Summit Drive, Brush Hill Lane, and Westleigh Drive.
    • Group B – resurfacing of the eastern part of town. This group includes, Wilmette Avenue, Ardmore Avenue, Dale Street, Long Road, Brook Lane, Brandon Road, Woodlawn Avenue, and Hollywood Avenue. 

 

During the week of August 30, the contractor is scheduled to complete the landscape restoration work on streets in Group A and Group B.

 
Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 8 am to 5 pm on Saturdays, if necessary.
Thank you for your patience.  ​


8/27/2021Phase 3 Parkway Restoration
1 - 3Next

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.