The Village of Glenview

2021 street resurfacing projects


2021 public improvement project

​Contact Information

Project Manager: Tom Hagerty
(847) 904-4421​
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us                                                                  

Project description

The proposed improvements consist of the repair of existing underground utility (sanitary and storm sewer) sections, repair of existing utility structures, partial or full removal of existing pavement, placement of new hot-mix asphalt,  and replacement of deteriorated sections of sidewalk and curb and gutters.  The project scope also includes partial resurfacing of damaged pavement sections in various locations, as per the Minor Area Repair Strategy (MARS) program. See the table below for the areas that will be included as part of this project.  

Street Name                                                                                                 Limits

Pynsky RoadPotter Road
east end
Crescent LanePotter Road
west end
Wilmette Avenue*west end
Long Road
Saratoga LaneMonterey Drive
Kittyhawk Lane
Cabot LaneSaratoga Lane
Monterey Drive
Monterey DriveWest Lake Avenue
Independence Avenue
Westleigh Drive (south)Westleigh Drive South
Aberdeen Drive
Summit DriveWestleigh Drive South
Aberdeen Drive
Brush Hill Lane​Summit Drive

Westleigh Drive

Hill Circle
​Central Road
​north cul-de-sac
Sumac Circle​west cul-de-sac

​east cul-de-sac

Cedarwood Lane​Linden Leaf Drive
​north cul-de-sac
Fir Street​​Shermer Road
​east cul-de-sac
Ardmore Avenue​Long Road
west end
Dale Street
​Long Road
west  end

Project information and updates

Contractor: Arrow Road Construction Co. of Elk Grove Village

Budget: $1,974,294

​Location map: Click ​here

* The Village of Glenview entered into an Intergovernmental Agreement with the Village of Wilmette regarding the resurfacing of Wilmette Avenue

Tentative schedule

  • Bid awarded -- April 20, 2021
  • Pre-construction meeting -- June 1, 2021
  • Approximate start of construction -- July 15, 2021
  • Anticipated completion of construction -- September 24, 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
2021 street resurfacing5/22/2021Published5/14/2021 11:22 AMTom Hagerty 847-904-4421On Schedule

​Welcome to the project updates page for the 2021 Road Resurfacing Project. The contractor, Arrow Road Construction, was awarded the project. Project updates will typically be posted on Fridays of each week. If you have any questions please feel free to contact the Project Engineer, Kim Wenzel, at (847) 904-4235 or at kwenzel@glenview.il.us or the Project Manager, Tom Hagerty, at (847) 904-4421 or at thagerty@glenview.il.us  


This project consists of improving and resurfacing nineteen (19) road sections and a total of approximately 4 miles of roadway.  The resurfacing will be split into two groups:
o Group A – resurfacing of the western part of the town. This group includes Pynsky Road, Crescent Lane, Saratoga Lane, Cabot Lane, Monterey Drive, Summit Drive, Brush Hill Lane, and Westleigh Drive  This work will start the week of May 17th and is anticipated to be completed by in July, weather permitting.
o Group B – resurfacing of the eastern part of town. This group includes, Wilmette Avenue, Ardmore Avenue, Dale Street, Long Road, Brook Lane, Brandon Road, Woodlawn Avenue, and Hollywood Avenue.  This work is anticipated to start in late June or early July and will by the end of September, weather permitting.

The contractor is scheduled to begin the project the week of May 17, starting with Group A.  During this week the contractor will begin saw cutting the marked curb and sidewalk in preparation for the underground improvements and concrete improvements.

Please note that this project includes multiple streets throughout The Village and because of this you will not see consistent work on your street from start to finish. Instead, the contractor plans to complete each phase of this project on all streets in each group before moving to the next phase. We know that construction can be an interruption and we appreciate your patience throughout this project. 

Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.

5/16/2021Start of Construction

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.