The Village of Glenview

2021 street resurfacing projects


2021 public improvement project

​Contact Information

Project Manager: Tom Hagerty
(847) 904-4421​
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us                                                                  

Project description

The proposed improvements consist of the repair of existing underground utility (sanitary and storm sewer) sections, repair of existing utility structures, partial or full removal of existing pavement, placement of new hot-mix asphalt,  and replacement of deteriorated sections of sidewalk and curb and gutters.  The project scope also includes partial resurfacing of damaged pavement sections in various locations, as per the Minor Area Repair Strategy (MARS) program. See the table below for the areas that will be included as part of this project.  

Street Name                                                                                                 Limits

Pynsky RoadPotter Road
east end
Crescent LanePotter Road
west end
Wilmette Avenue*west end
Long Road
Saratoga LaneMonterey Drive
Kittyhawk Lane
Cabot LaneSaratoga Lane
Monterey Drive
Monterey DriveWest Lake Avenue
Independence Avenue
Westleigh Drive (south)Westleigh Drive South
Aberdeen Drive
Summit DriveWestleigh Drive South
Aberdeen Drive
Brush Hill Lane​Summit Drive

Westleigh Drive

Hill Circle
​Central Road
​north cul-de-sac
Sumac Circle​west cul-de-sac

​east cul-de-sac

Cedarwood Lane​Linden Leaf Drive
​north cul-de-sac
Fir Street​​Shermer Road
​east cul-de-sac
Ardmore Avenue​Long Road
west end
Dale Street
​Long Road
west  end

Project information and updates

Contractor: Arrow Road Construction Co. of Elk Grove Village

Budget: $1,974,294

​Location map: Click ​here

* The Village of Glenview entered into an Intergovernmental Agreement with the Village of Wilmette regarding the resurfacing of Wilmette Avenue

Tentative schedule

  • Bid awarded -- April 20, 2021
  • Pre-construction meeting -- June 1, 2021
  • Approximate start of construction -- July 15, 2021
  • Anticipated completion of construction -- September 24, 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
2021 street resurfacing8/5/2021Published7/30/2021 12:23 PMTom Hagerty 847-904-4421On Schedule

During the week of July 26, the contractor completed re-instating driveways as well as completing underground repairs, the contractor also completed pouring the gaps in the curbs due to structure adjustments on Woodlawn Avenue and Hollywood Avenue, Brook Lane, Wilmette Avenue, Long Road, Ardmore Avenue, and Dale Street.

During the week of August 2, the contractor will remove the old surface layer of asphalt pavement on Woodlawn Avenue, Hollywood Avenue, Brook Lane, Wilmette Avenue, Long Road, Ardmore Avenue, and Dale Street as well as Pynsky Road and Crescent Lane. Additionally, the contractor is tentatively scheduled to begin placing the new asphalt surface on these streets early the week of August 9, 2021.

Please note that this project includes multiple streets throughout the Village, and because of this you will not see consistent work on your street from start to finish. Instead, the contractor plans to complete each phase of this project on all streets in each group before moving to the next phase.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 8 am to 5 pm on Saturdays, if necessary.
Thank you for your patience.  ​


7/30/2021Phase 2 Roadway Reconstruction
  
2021 street resurfacing7/31/2021Published7/23/2021 4:17 PMTom Hagerty 847-904-4421On Schedule

During the week of July 19, the contractor completed removing and replacing the marked curb and sidewalk on Woodlawn Avenue and Hollywood Avenue, Brook Lane, Wilmette Avenue, Long Road, Ardmore Avenue, and Dale Street. Furthermore, contractor also began re-instating driveways on these streets as well as completing underground repairs.

During the week of July 26, the contractor will remove the old surface layer of asphalt pavement on Woodlawn Avenue and Hollywood Avenue, Brook Lane, Wilmette Avenue, Long Road, Ardmore Avenue, and Dale Street.. Additionally, the contractor is tentatively scheduled to begin placing the new asphalt surface on these streets early the week of August 2, 2021.

Please note that this project includes multiple streets throughout the Village, and because of this you will not see consistent work on your street from start to finish. Instead, the contractor plans to complete each phase of this project on all streets in each group before moving to the next phase.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 8 am to 5 pm on Saturdays, if necessary.
Thank you for your patience.  ​


7/25/2021Phase 2 Roadway Reconstruction
  
2021 street resurfacing7/24/2021Published7/16/2021 4:18 PMTom Hagerty 847-904-4421On Schedule

During the week of July 12, the contractor began removing and replacing the marked curb and sidewalk on the north and east sides, starting on Woodlawn Avenue and Hollywood Avenue and then move  to Brook Lane, Wilmette Avenue, Long Road, Ardmore Avenue, and Dale Street.

On Friday July 16 the contractor will begin removing and replacing the marked curb and sidewalk on the south and west sides, starting on Hollywood Avenue and then move  to Brook Lane, Wilmette Avenue, Long Road, Ardmore Avenue, and Dale Street.  Furthermore, the contractor will begin the underground improvements on Woodlawn Avenue and Hollywood Avenue and then move to Brook Lane, Wilmette Avenue, Long Road, Ardmore Avenue, and Dale Street. This work is dependent on favorable weather and will be postponed to the next favorable day. If access to your driveway is impacted you will receive an additional notification stating where you can park your car during this phase of construction. You will also receive an additional notice when it is clear to park back in your driveway.

 
During the week of July 19, the contractor will finish the underground improvements on this group of streets. Once this has been completed the contractor will finish the curbs and sidewalks. Furthermore, the contractor will begin driveway restorations near the end of next week.

Please note that this project includes multiple streets throughout the Village, and because of this you will not see consistent work on your street from start to finish. Instead, the contractor plans to complete each phase of this project on all streets in each group before moving to the next phase.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 8 am to 5 pm on Saturdays, if necessary.
Thank you for your patience.  ​


7/18/2021Phase 2 Roadway Reconstruction
1 - 3Next

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.