The Village of Glenview

2022 Street Resurfacing Project


2022 public improvement project

​Project description

The Village's FY2022 Road Improvement Project includes resurfacing of approximately two (2) miles of roadways consisting of nine (9) street sections and one alley (see attached Location Map), the replacement of water main on Robincrest and adjacent cul-de-sacs, and the implementation of the annual MARS Program. The MARS program consists of asph​​alt resurfacing of sections of streets that are less than a complete roadway resurfacing and more than a pothole patching. The following street are planned for asphalt resurfacing in 2022:​

​Street Name
​From
​To
​Robincrest Lane (Water)
Harlem Avenue​
Shermer Road
​Spruce Street (Water)
Robincrest Lane​
Central Road​
Wissing Lane (Water)​
​Robincrest Lane
​South End
​Garden Court (Water)
​Robincrest Lane
​North End
​Warren Road (Water)
​Warren Road
​West End
​Lincoln Street
​Robincrest Lane
​Central Road
​Iroquois Drive
​Mohawk Lane
​Mohawk Lane
​Waukegan Road Alley
​Colfax Avenue
​South End
​Harrison Street
​Greenwood Road
​Warren Road
​Depot Street
​Commuter Parking
​Tinker Way
​MARS Asphalt
​Various locations
View Project Map


Scope of Work​

The following major improvements are included in this contract:

  • ​The proposed storm sewer improvements consist of minor repair work, including installing approximately 2600 feet of 12-inch to 36-inch storm sewer to improve stormwater conveyance.
  • The proposed minor sanitary sewer improvements consist of sanitary manhole replacement, sanitary sewer repair or sanitary sewer services replacement as necessary.
  • The proposed pavement improvements consist of approximately 10,600 linear feet of roadway resurfacing or pavement patching within the listed street segments. The pavement improvement work will follow the underground utility repairs and incorporate repair of adjacent impacted areas, including driveway, sidewalk, curb and gutter removal, and replacement.
  • On Robincrest, including adjacent cul-de-sacs, and the Warren cul-de-sac, the improvements consist of water main replacement, along with services, followed by pavement patching and full roadway resurfacing. As part of the implementation of the updated Water Main Master Plan a section of water main between Warren and Harrison was identified as a priority candidate for water main replacement. Therefore 650 feet of water main replacement adjacent to Warren culde-sac and Harrison was added as an option.
  • The 2022 MARS Program consists of approximately 2,000 square yards of resurfacing of various roadways within the Village. The resurfacing locations are evaluated and updated annually by the Public Works Department.​

Project information and updates​

Contractor: Martam Construction Inc. of Elgin, Ill.

Budget: $4.4 million

Contact information

Project Manager: Tom Hagerty
(847) 904-4221
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us


Tentative Schedule

  • Bid award -- April 19, 2022
  • Resident preconstruction meeting -- May 12, 2022, 6 p.m. at the intersection of Robincrest and Spruce
  • Approximate start of construction --June 6, 2022
  • Approximate completion of construction -- Sept. 23, 2022

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​


  
  
  
  
  
  
  
Update
  
  
  
2022 2022 Street Resurfacing Project8/12/2022Published8/5/2022 1:50 PMTom Hagerty 847-904-4421On Schedule

The week of August 1, the contractor began installing the new storm sewer and water main on the Warren Road cul de sac.

The week of August 8, installation of the new water main and storm sewer on the Warren Road cul-de-sac has been temporarily stopped due to a conflict with Nicor gas services. We are working with NICOR to resolve this as soon as possible. Please look for handouts delivered to each home.

Throughout this phase of construction, the contractor will be working in the street and parkway. The contractor will begin installing new sanitary manholes near the end of the week.

Please remember that all work and correlating dates and time frames are dependent on suitable weather.

There will be a resident / Business owner pre-construction meeting at Colfax and the alley east of Waukegan Road on August 10, 2022, at 6:00 p.m. This will be an informative meeting to discuss the upcoming alley improvements south of Colfax.

Throughout this phase of construction, the contractor will be working in the street and parkway

Please watch for informational notices delivered to the front door of your home. Further information may also be found on the project website:

www.glenview.il.us/Pages/2022%20Street%20Resurfacing%20Project.aspx

If you have any questions about the project or project updates, please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or by phone at (847) 904-4421.

Thank You for your patience​


8/5/2022Phase I Underground
  
2022 2022 Street Resurfacing Project8/4/2022Published7/29/2022 3:52 PMTom Hagerty 847-904-4421On Schedule

Please find below the list of street this year for watermain work and resurfacing.

Street NameFromTo
Robincrest Lane (Water)Harlem AvenueShermer Road
Spruce Street (Water)Robincrest LaneCentral Road
Wissing Lane (Water)Robincrest LaneSouth End
Garden Court (Water)Robincrest LaneNorth End
Warren Road (Water)Warren RoadWest End
Lincoln Street Robincrest LaneCentral Road
Iroquois DriveMohawk Lane Mohawk Lane
Waukegan Road AlleyColfax AvenueSouth End
Harrison StreetGreenwood Road Warren Road
Depot StreetCommuter Parking Tinker Way

 

The week of July 25, the contractor completed installing four water valves on Warren Road at  Harrison Street. The contractor also began installing water main and storm sewer on the Warren Road cul-de-sac.

The week of August 1, the contractor will installing water main and storm sewer on the Warren Road cul-de-sac. Please look for handouts delivered to each home.

Throughout this phase of construction, the contractor will be working in the street and parkway. The contractor will begin installing new sanitary manholes near the end of the week.

Please remember that all work and correlating dates and time frames are dependent on suitable weather.

There will be a resident / Business owner pre-construction meeting at Colfax and the alley east of Waukegan Road on August 10, 2022 at 6:00 p.m. This will be an informative meeting to discuss the upcoming alley improvements south of Colfax.

Throughout this phase of construction, the contractor will be working in the street and parkway

Please watch for informational notices delivered to the front door of your home. Further information may also be found on the project website:

www.glenview.il.us/Pages/2022%20Street%20Resurfacing%20Project.aspx

If you have any questions about the project or project updates, please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or by phone at (847) 904-4421.

Thank You for your patience​


7/29/2022Phase 1 Underground Utility Improvements
  
2022 2022 Street Resurfacing Project7/29/2022Published7/25/2022 7:12 AMTom Hagerty 847-904-4421On Schedule

The week of July 18, The contractor began mobilizing equipment and material on Warren Road at Harrison.

The week of July 25, the contractor will begin installing four water valves on Warren Road at  Harrison Street. The contractor is tentatively scheduled to begin installing water main and storm sewer on the Warren Road cul-de-sac. When this occurs, each resident will be notified that they will have to be out of the driveways during the day for this construction. Please look for handouts delivered to each home.

Throughout this phase of construction, the contractor will be working in the street and parkway. the contractor will begin installing new sanitary manholes near the end of the week

Please remember that all work and correlating dates and time frames are dependent on suitable weather.

Throughout this phase of construction, the contractor will be working in the street and parkway

Please watch for informational notices delivered to the front door of your home. Further information may also be found on the project website:

www.glenview.il.us/Pages/2022%20Street%20Resurfacing%20Project.aspx

If you have any questions about the project or project updates, please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or by phone at (847) 904-4421.

Thank You for your patience​


7/25/2022Phase I Underground
1 - 3Next

​Find all project updates here.​​

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.​

 





​​