The Village of Glenview

2022 Street Resurfacing Project


2022 public improvement project

​Project description

The Village's FY2022 Road Improvement Project includes resurfacing of approximately two (2) miles of roadways consisting of nine (9) street sections and one alley (see attached Location Map), the replacement of water main on Robincrest and adjacent cul-de-sacs, and the implementation of the annual MARS Program. The MARS program consists of asph​​alt resurfacing of sections of streets that are less than a complete roadway resurfacing and more than a pothole patching. The following street are planned for asphalt resurfacing in 2022:​

​Street Name
​From
​To
​Robincrest Lane (Water)
Harlem Avenue​
Shermer Road
​Spruce Street (Water)
Robincrest Lane​
Central Road​
Wissing Lane (Water)​
​Robincrest Lane
​South End
​Garden Court (Water)
​Robincrest Lane
​North End
​Warren Road (Water)
​Warren Road
​West End
​Lincoln Street
​Robincrest Lane
​Central Road
​Iroquois Drive
​Mohawk Lane
​Mohawk Lane
​Waukegan Road Alley
​Colfax Avenue
​South End
​Harrison Street
​Greenwood Road
​Warren Road
​Depot Street
​Commuter Parking
​Tinker Way
​MARS Asphalt
​Various locations
View Project Map


Scope of Work​

The following major improvements are included in this contract:

  • ​The proposed storm sewer improvements consist of minor repair work, including installing approximately 2600 feet of 12-inch to 36-inch storm sewer to improve stormwater conveyance.
  • The proposed minor sanitary sewer improvements consist of sanitary manhole replacement, sanitary sewer repair or sanitary sewer services replacement as necessary.
  • The proposed pavement improvements consist of approximately 10,600 linear feet of roadway resurfacing or pavement patching within the listed street segments. The pavement improvement work will follow the underground utility repairs and incorporate repair of adjacent impacted areas, including driveway, sidewalk, curb and gutter removal, and replacement.
  • On Robincrest, including adjacent cul-de-sacs, and the Warren cul-de-sac, the improvements consist of water main replacement, along with services, followed by pavement patching and full roadway resurfacing. As part of the implementation of the updated Water Main Master Plan a section of water main between Warren and Harrison was identified as a priority candidate for water main replacement. Therefore 650 feet of water main replacement adjacent to Warren culde-sac and Harrison was added as an option.
  • The 2022 MARS Program consists of approximately 2,000 square yards of resurfacing of various roadways within the Village. The resurfacing locations are evaluated and updated annually by the Public Works Department.​

Project information and updates​

Contractor: Martam Construction Inc. of Elgin, Ill.

Budget: $4.4 million

Contact information

Project Manager: Tom Hagerty
(847) 904-4221
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us


Tentative Schedule

  • Bid award -- April 19, 2022
  • Resident preconstruction meeting -- May 12, 2022, 6 p.m. at the intersection of Robincrest and Spruce
  • Approximate start of construction --June 6, 2022
  • Approximate completion of construction -- Sept. 23, 2022

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​


​Find all project updates here.​​

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.​

 





​​