The Village of Glenview

Lilac Avenue Improvements


2023 public improvement project

Project Summary

The proposed Project includes approximately 920 feet of improvements on Lilac Avenue from Maple Street to Milwaukee Avenue.

 The following major improvements are included in this project:

 

  • Replacement of 1,136 feet new 8-inch water main with new 1 ½-inch water service lines and b-boxes
  • 1,050 feet of storm sewer improvements
  • Spot replacement of curb and gutter, sidewalk, and driveway apron repairs, as needed.
  • Road reconstruction with asphalt pavement
  • Parkway restorations with sod

     

    Contractor: Dimeo Brothers, Inc. of Elk Grove Village, Illinois            

    Budget: $1.2 Million​

Project Location Map


Contact Information

Project Manager: Tim Schwister

847-904-4422

tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb

847-904-4414

awebb@glenview.il.us


​​​Tentative Schedule

  • Bid notice published – November 17, 2022
  • Bid opening date – December 6, 2022
  • Bid award – March 21, 2023
  • Pre-construction meeting – May 11, 2023
  • Approximate starting date of construction – July 2023
  • Approximate completion of construction – October 2023

     

    Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.



Notices

Lilac Pre-Construction Meeting Letter.pdf

Handouts

Lilac Design Open House Handout.pdf

Board of Trustees Actions​​​​​

Feb. 7, 2023 -- Lilac-Maclean Contract Award Board Report.pdf


  
  
  
  
  
  
  
Update
  
  
  
2023 Lilac Avenue Improvements9/22/2023Published9/15/2023 2:40 PMTim Schwister 847-904-4422On schedule

The week of September 11 the contractor will began installing the new water main from Milwaukee Avenue to Maple Street. The contractor began at Milwaukee Avenue and working west.

The week of September 18, the contractor will continue installing the water main from Milwaukee Avenue working west to Maple Street. The contractor is anticipated to complete the installation of the new water main at the end on this week. Once completed the contractor will perform standardized testing on the new water main including Pressure testing as well as chlorinating the new water line.

Please watch for further information via the project website at:

https://www.glenview.il.us/Pages/2023LilacAvenueImprovements.aspxor by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.


9/22/2023Phase I Water Main
  
2023 Lilac Avenue Improvements9/15/2023Published9/8/2023 2:38 PMTim Schwister 847-904-4422On schedule

The week of September 5 the contractor will began installing the new water main from Milwaukee Avenue to Maple Street. The contractor began at Milwaukee Avenue and working west.

The week of September 11, the contractor will continue installing the water main from Milwaukee Avenue working west to Maple Street. The contractor is anticipated to complete the installation of the new water main at the end on this week. Once completed the contractor will perform standardized testing on the new water main including Pressure testing as well as chlorinating the new line.

Please watch for further information via the project website at:

https://www.glenview.il.us/Pages/2023LilacAvenueImprovements.aspxor by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.


9/15/2023Phase I Underground
  
2023 Lilac Avenue Improvements9/1/2023Published8/25/2023 3:21 PMTim Schwister 847-904-4422On schedule

The week of August 21, 2023, the contractor began to stage material throughout the project including pipe and manholes. The contractor also began saw cutting in advance of the new utility installation.

The week of August 28 the contractor will begin installing the new water main from Milwaukee Avenue to Maple Street. The contractor will begin at Milwaukee Avenue and working west.

Please watch for further information via the project website at:

https://www.glenview.il.us/Pages/2023LilacAvenueImprovements.aspxor by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.


9/1/2023Phase I Underground
1 - 3Next