The Village of Glenview

Lilac Avenue Improvements


2023 public improvement project

Project Summary

The proposed Project includes approximately 920 feet of improvements on Lilac Avenue from Maple Street to Milwaukee Avenue.

 The following major improvements are included in this project:

 

  • Replacement of 1,136 feet new 8-inch water main with new 1 ½-inch water service lines and b-boxes
  • 1,050 feet of storm sewer improvements
  • Spot replacement of curb and gutter, sidewalk, and driveway apron repairs, as needed.
  • Road reconstruction with asphalt pavement
  • Parkway restorations with sod

     

    Contractor: Dimeo Brothers, Inc. of Elk Grove Village, Illinois            

    Budget: $1.2 Million​

Project Location Map


Contact Information

Project Manager: Tim Schwister

847-904-4422

tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb

847-904-4414

awebb@glenview.il.us


​​​Tentative Schedule

  • Bid notice published – November 17, 2022
  • Bid opening date – December 6, 2022
  • Bid award – March 21, 2023
  • Pre-construction meeting – May 11, 2023
  • Approximate starting date of construction – July 2023
  • Approximate completion of construction – October 2023

     

    Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.



Notices

Lilac Pre-Construction Meeting Letter.pdf

Handouts

Lilac Design Open House Handout.pdf

Board of Trustees Actions​​​​​

Feb. 7, 2023 -- Lilac-Maclean Contract Award Board Report.pdf


  
  
  
  
  
  
  
Update
  
  
  
2023 Lilac Avenue Improvements11/17/2023Published11/10/2023 4:00 PMTim Schwister 847-904-4422On schedule

The week of November 6, the contractor will complete the installation of topsoil and the new sod in the affected areas. The contractor completed pavement milling as well as adjusting manholes this week.

The week of November 13, the contractor will complete the final layer of asphalt.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

 

Please watch for further information via the project website at:

https://www.glenview.il.us/Pages/2023LilacAvenueImprovements.aspxor by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.


11/17/2023Final Asphalt and Punchlist items
  
2023 Lilac Avenue Improvements11/10/2023Published11/3/2023 4:03 PMTim Schwister 847-904-4422On schedule

The week of October 30, the contractor has completed patching the utility trenches. The contractor has also begun preparing for the installation of the final landscaping, including new sod.

The week of November 6 the contractor will complete the installation of topsoil and the new sod in the affected areas. The contractor is also scheduled to begin pavement milling Thursday or Friday of this week. The following week the contractor will then raise manholes and perform the final water and sewer testing prior to the final layer of asphalt.

Please watch for further information via the project website at:

https://www.glenview.il.us/Pages/2023LilacAvenueImprovements.aspxor by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.


11/10/2023Pavement Patching and Landscaping
  
2023 Lilac Avenue Improvements11/10/2023Published11/3/2023 4:10 PMTim Schwister 847-904-4422On schedule

The week of October 30, the contractor has completed patching the utility trenches. The contractor has also begun preparing for the installation of the final landscaping, including new sod.

The week of November 6 the contractor will complete the installation of topsoil and the new sod in the affected areas. The contractor is also scheduled to begin pavement milling Thursday or Friday of this week. The following week the contractor will then raise manholes and perform the final water and sewer testing prior to the final layer of asphalt.

Please watch for further information via the project website at:

https://www.glenview.il.us/Pages/2023LilacAvenueImprovements.aspxor by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.


11/10/2023Pavement Patching and Landscaping
1 - 3Next
Sign up​ to be emailed project updates.​​