The Village of Glenview

Longvalley Streambank Stabilization Project


2024 public improvement project
Project description


The proposed Project includes approximately 875 feet of streambank stabilization along the south bank of the West Fork North Branch Chicago River.

 The following major improvements are included in this project:

  • Stone toe streambank stabilization with a stone armoring treatment from the toe of the slope and native vegetation at the top of the slow overbank areas. The project will use rounded river stone similar to other improvements along the river.
  • Installation of two riffle structures.
  • Planting of over 30 trees and shrubs.
  • Native restoration of a vacant .40 acre parcel.

LincolnMap2023.png

Contact information

Project Manager: Eric Pugh
(847) 904-4235
epugh@glenview.il.us

Engineering Inspector: Dayvohn Braxton
(847) 904-4238
dbraxton@glenview.il.us

Senior Project Manager: Thomas Hagerty
(847) 904-4421
thagerty@glenview.il.us

Project information and updates​

Contractor: ENCAP Inc. of DeKalb, Illinois     

Budget: $646,280

​​​Tentative Schedule

  • Bid award date – Anticipated January 9, 2024 
  • Resident pre-construction meeting – February 15, 2024
  • Approximate starting date of construction – March 4, 2024
  • Approximate completion of construction – April 2024
Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.


​​​Notices

Pre-construction meeting letter​

​​​Handouts

Pre-construction presentation

​​​Board of Trustees actions

Resolution & Staff Report​

​​​Project Updates

Sign up​ to be emailed project updates.​​


  
  
  
  
  
  
  
Update
  
  
  
2024 Longvalley Streambank Stabilization Project4/26/2024Published4/19/2024 3:17 PMEric Pugh 847-904-4235On Schedule
During the week of April 15, 2024, the contractor continued excavation and stabilization of the new bank slope. In order to stabilize the streambank, the contractor began installing round rock along the river slope and riverbed. The contractor has taken the necessary precautions to stabilize the streambank and provide proper erosion control measures prior to beginning the excavation and earth moving construction activities.  They began excavation at the west end and work east. You may see a second crew out working on the streambank stabilization, this was decided to help expedite the project due to the numerous weather delays.

During the week of April 22, 2024, the contractor will continue excavation and stabilization of the new bank slope.

Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website at: https://www.glenview.il.us/Pages/2024LongvalleyStreambank.aspx  or by hand delivered notices.

If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.

4/19/2024Streambank Excavation
  
2024 Longvalley Streambank Stabilization Project4/19/2024Published4/12/2024 3:43 PMEric Pugh 847-904-4235On Schedule
During the week of April 8, 2024, the contractor continued excavation and stabilization of the new bank slope. The weather last week has caused some significant delays and the contractor is working very hard to get the project back on track. In order to stabilize the streambank, the contractor began installing round rock along the river slope and riverbed. The contractor has taken the necessary precautions to stabilize the streambank and provide proper erosion control measures prior to beginning the excavation and earth moving construction activities.  They began excavation at the west end and work east. The inclement weather restricted work this week.
During the week of April 15, 2024, the contractor will continue excavation and stabilization of the new bank slope.
Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website at: https://www.glenview.il.us/Pages/2024LongvalleyStreambank.aspx  or by hand delivered notices.

If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.
4/12/2024Streambank Excavation
  
2024 Longvalley Streambank Stabilization Project4/12/2024Published4/8/2024 2:39 PMEric Pugh 847-904-4235On Schedule
During the week of April 1, 2024, the contractor continued excavation and stabilization of the new bank slope. In order to stabilize the streambank, the contractor began installing round rock along the river slope and riverbed. The contractor has taken the necessary precautions to stabilize the streambank and provide proper erosion control measures prior to beginning the excavation and earth moving construction activities.  They began excavation at the west end and work east.

The inclement weather restricted work this week.

During the week of April 8, 2024, the contractor will continue excavation and stabilization of the new bank slope.

Please remember these dates are dependent on suitable weather.

Please watch for further information via the project website at: https://www.glenview.il.us/Pages/2024LongvalleyStreambank.aspx  or by hand delivered notices.

If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.
4/5/2024Streambank Stabilization