The Village of Glenview

Prairie Lawn Road


2023 public improvement project
Project description

The proposed Project includes approximately 0.25 miles of improvements on Prairie Lawn Road from Linneman Street to Glenview Road.

 The following major improvements are included in this project:

  •  Installation of approximately 1,400 feet of 8-inch Polyvinyl Chloride (PVC) water main with new 1 ½-inch water service lines and b-boxes
  • Installation of 700 feet of 12-inch to 24-inch storm sewer
  • Sanitary sewer manholes repair and replacement of sanitary services, if necessary
  • Replacement of curb and gutter and resurfacing of the road with asphalt pavement
  • Parkway restorations with sod​

​Contact information

Project Manager: Eric Pugh, Project Manager
(847) 904-4235
epugh@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: Pirtano Construction, Inc., of Addison, Ill.

Budget: $2.82 million

As part of Village construction projects, if lead water services are discovered, the Village offers a cost-sharing program to replace lead services. Learn more here​.

Tentative Schedule

  • Bid notice published -- Dec. 6, 2022
  • Bid opening date -- Dec. 20, 2022
  • Bid award -- Feb. 7, 2023
  • Pre-construction meeting -- March 9, 2023 
Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​​​​​

Notices

Pre-construction meeting letter

Handouts

Design meeting handout

Board of Trustees actions

Feb. 7, 2023 -- Contract award to Pirtano Construction, Inc

Staff report





  
  
  
  
  
  
  
Update
  
  
  
2023 Prairie Lawn Road Reconstruction​7/14/2023Published7/7/2023 4:25 PMEric Pugh 847-904-4235Completed

The week of July 5, the contractor is anticipated to place the final landscaping including the new sod.

The week of July 10, the contractor is also tentatively scheduled to place the final layer of asphalt.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

 

Please watch for further information via the project website: https://www.glenview.il.us/Pages/23PrairieLawnRoad.aspx or by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.


7/14/2023Phase III Construction Landscape and final asphalt
  
2023 Prairie Lawn Road Reconstruction​7/7/2023Published6/30/2023 3:41 PMEric Pugh 847-904-4235On schedule

The week of June 26, the contractor began installing topsoil in anticipation of final landscaping. 

The week of July 5, the contractor is anticipated to place the final landscaping including the new sod.

The week of July 10, the contractor will place the sod and final landscaping. The contractor is also tentatively scheduled to place the final layer of asphalt.

Please watch for further information via the project website: https://www.glenview.il.us/Pages/23PrairieLawnRoad.aspx or by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.


7/7/2023Phase II Road Construction
  
2023 Prairie Lawn Road Reconstruction​6/30/2023Published6/29/2023 2:32 PMEric Pugh 847-904-4235On schedule

The week of June 19, the contractor adjusted manholes and performed final utility testing.

The week of June 26, the contractor is scheduled to place the topsoil in advance of the sod. The sod placement will take place the week of July 3.

Please watch for further information via the project website: https://www.glenview.il.us/Pages/23PrairieLawnRoad.aspx or by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.


6/30/2023Phase III Final landscape and Road surface
1 - 3Next
Sign up​ to be emailed project updates.​