Valley Lo Water Main Improvements


2024 -2025 public improvement project
Project description


The proposed Project includes approximately .7 miles of improvements on Valley Lo Lane from Tanglewood Drive to Wildberry Drive broken down into two phases.

  • Phase I is in 2024 (blue) from Monroe Avenue to Wildberry Drive
  • Phase II is in 2025 (red) from Monroe Avenue to Tanglewood Drive 
 
The following major improvements are included in this project:

  • ​Installation of approximately 1,600 feet (Phase I) and 1,400 feet (Phase II) of 8-inch Polyvinyl Chloride (PVC) water main with new 1.5-inch water service lines and b-boxes
  • Pavement patching
  • Parkway and driveway restoration for areas affected during construction
  • Resurfacing all of Valley Lo Lane after water main is completed in 2025

Valley Lo Water Main.jpg

Contact information

Project Manager: Tim Schwister​
(847) 904-4422

tschwister@glenview.il.us

Engineering Inspector: Dayvohn Braxton
(847) 904-4238
dbraxton@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: DiMeo Brothers Inc. of Elk Grove Village, Illinois

Budget: Phase I - $924,000; Phase II - $596,000

​​​Tentative Schedule

  • Bid award date – Anticipated February 2024
  • Resident pre-construction meeting – February 27, 2024​
  • Approximate starting date of construction – March 2024 (Phase I); March 2025 (Phase II)
  • Approximate completion of construction – June 2024 (Phase I); May 2024 (Phase II)
Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.


​​​Notices

Pre-construction meeting letter​

​​​Handouts

Pre-construction meeting presentation

​​​Board of Trustees actions

Resolution & Staff Report​

​​​Project Updates

Sign ​up​ to be emailed project updates.​​


  
  
  
  
  
  
  
Update
  
  
  
2024 Valley Lo Water Main Improvements4/26/2024Published4/19/2024 3:29 PMTim Schwister 847-904-4422On Schedule
The week of April 15 the contractor continued installing water main working towards Wildberry. Throughout this phase of construction, the contractor will be working in the street. installation of the new water main is anticipated to last approximately two weeks.
The week of April 22 the contractor will continue installing water main on the south portion of Valley Lo. The contractor is tentatively scheduled to begin installing new water services to each home.. The new water services connect each house with a new 1.5” copper water service line as well as a new b-box and water shut off. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.  
Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website at: https://www.glenview.il.us/Pages/24-25ValleyLo.aspx  or by hand delivered notices.

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
4/19/2024Phase I Underground work
  
2024 Valley Lo Water Main Improvements4/19/2024Published4/12/2024 3:51 PMTim Schwister 847-904-4422On Schedule
The week of April 8 the contractor continued installing water main working towards Wildberry. Throughout this phase of construction, the contractor will be working in the street. installation of the new water main is anticipated to last approximately two weeks.
The week of April 15 the contractor will continue installing water main and working towards the south from 2116 Valley Lo.
Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website at: https://www.glenview.il.us/Pages/24-25ValleyLo.aspx  or by hand delivered notices.

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.
4/12/2024Phase I Underground work
  
2024 Valley Lo Water Main Improvements4/12/2024Published4/8/2024 2:36 PMTim Schwister 847-904-4422On Schedule
The week of April 1 the contractor continued installing water main working towards Wildberry. Throughout this phase of construction, the contractor will be working in the street. installation of the new water main is anticipated to last approximately three weeks.
The week of April 8 the contractor will continue installing water main starting where they left off the previous week and working towards Wildberry.
Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website at: https://www.glenview.il.us/Pages/24-25ValleyLo.aspx  or by hand delivered notices.

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.

4/5/2024Phase I Construction Water Main Installation