The Village of Glenview

Elm Street Improvements


2024 public improvement project
Project description


The proposed Project includes approximately 600 feet of improvements on Elm Street from Colfax Avenue to Harrison Street.
 
 The following major improvements are included in this project:

  • ​Installation of 600 feet of new 8-inch Polyvinyl Chloride (PVC) water main with new 1 ½-inch water service lines and b-boxes
  • Replacement of 208 feet of existing storm sewer with new 12-inch and 18-inch storm sewer
  • New curb and gutter and 5-foot wide sidewalk. In-kind driveway apron repairs as needed
  • Road reconstruction with asphalt pavement
  • Parkway restorations with sod

LincolnMap2023.png

Contact information

Project Manager: Dayvohn Braxton
(847) 904-4238
dbraxton@glenview.il.us

Egineering ​Inspector: William Krueger
(847) 361-1049
wkrueger@glenview.il.us​

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: DiMeo Brothers Inc. of Elk Grove Village, Illinois

Budget: $878,000​

​​​Tentative Schedule

  • ​​​Design open house – October 16, 2023
  • Bid award – January 9, 2024
  • Resident pre-construction meeting – February 13, 2024, 6 p.m. at Village Hall
  • Approximate starting date of construction – March 2024
  • Approximate completion of construction – May 2024
Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.


​​​Notices

Pre-construction meeting letter​

Open House letter

​​​Handouts​

Design meeting presentation

Pre-construction meeting presentation

​​​Board of Trustees actions

Resolution & Staff Report

​​​Project Updates

Sign up​ to be emailed project updates.​​


  
  
  
  
  
  
  
Update
  
  
  
2024 Elm Street Improvements4/26/2024Published4/19/2024 3:42 PMTom Hagerty 847-904-4421On Schedule
During the week of April 15, 2024, the contractor will begin mobilizing for the project. This includes utility markings, layout and pavement pulverization in advance of the new water main. The contractor made the initial water connection at Harrison to begin the new water main going south to Colfax. The contractor began installing water main on Elm.
The week of April 22 the contractor will complete installing the new water main on Elm. After the new water main is installed and while standardized testing is taking place including pressure testing and water main chlorination. The contractor will begin installing storm sewer. The storm sewer will begin at Colfax and move towards Harrison.
Please watch for further information via the project website at:
https://www.glenview.il.us/Pages/24Elm.aspx  or by hand delivered notices.

 If you have any questions about the project or project updates please contact the project manager, Dayvohn Braxton by email dbraxton@glenview.il.us or phone (847) 904-4238.

4/19/2024Phase I Underground work
  
2024 Elm Street Improvements4/19/2024Published4/12/2024 4:08 PMTom Hagerty 847-904-4421On Schedule
During the week of April 15, 2024, the contractor will begin mobilizing for the project. This includes utility markings, layout and pavement pulverization in advance of the new water main. The contractor will also stage material throughout the project including pipe and manholes. Affected residents will be notified next week in advance about the water shutdown on Monday April 22, at Elm and Harrison for the new water main connection.
The week of April 22 the contractor will begin installing the new water main tentatively beginning on Harrison and working south towards Harrison. After the new water main is installed and while standardized testing is taking place including pressure testing and water main chlorination the contractor will begin installing storm sewer.


4/12/2024Project Mobilazation
  
2024 Elm Street Improvements4/12/2024Published4/10/2024 10:15 AMTom Hagerty 847-904-4421On Schedule
Welcome to the project updates page for the Elm Street Water Main Improvements Project. Project updates will typically be posted on Fridays of each week. The contract was awarded to DiMeo Brothers Inc. of Elk Grove Village Illinois.

During the week of April 8, 2024, the contractor will begin mobilizing for the project. This includes utility markings, layout and pavement saw cutting in advance of the new water main. The contractor will also stage material throughout the project including pipe and manholes.

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.
4/5/2024Project Mobilazation