The Village of Glenview

Wildberry Water Main Improvements


2024 public improvement project
Project description


The proposed Project includes approximately .28 miles of improvements on Wildberry Drive from Tanglewood Drive to Waukegan Road.
 
 The following major improvements are included in this project:

  • ​Installation of approximately 1,000 feet of new 8-inch Polyvinyl Chloride (PVC) water main and 1,000 feet of water main lining in the existing water main in hard to access locations.
  • Pavement patching
  • Parkway and driveway restoration

LincolnMap2023.png

Contact information

Project Manager: Tim Schwister
(847) 904-4422

tschwister@glenview.il.us

Engineering Inspector: Dayvohn Braxton
(847) 904-4238
dbraxton@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: DiMeo Brothers Inc. of Elk Grove Village, Illinois   

Budget: $937,000

​​​Tentative Schedule

  • Bid award date – Anticipated February 2024 
  • Resident pre-construction meeting – February 27, 2024
  • Approximate starting date of construction – March 2024
  • Approximate completion of construction – June 2024
Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.


​​​Notices

Pre-construction meeting letter​

​​​Handouts

Pre-construction meeting presentation

​​​Board of Trustees actions

Resolution & Staff Report​

​​​Project Updates

Sign up​ to be emailed project updates.​​


  
  
  
  
  
  
  
Update
  
  
  
2024 Wildberry Water Main Improvements4/26/2024Published4/19/2024 3:25 PMTim Schwister 847-904-4422On Schedule
During the week of April 15, 2024,. the contractor continued mobilization for the project. This includes utility markings, layout and pavement saw cutting in advance of the new water main. The contractor will also stage material throughout the project including pipe and manholes.
During the week of April 22, 2024, the contractor will begin small excavations to locate various underground utilities in preparation for the installation of the new water main. These small excavations help ensure the existing utilities will not be damaged during installation of the new water main.
Please watch for further information via the project website at: https://www.glenview.il.us/Pages/24Wildberry.aspx or by hand delivered notices.

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.

4/19/2024Project Mobilazation
  
2024 Wildberry Water Main Improvements4/19/2024Published4/12/2024 3:55 PMTim Schwister 847-904-4422On Schedule
During the week of April 8, 2024, the contractor continued mobilization for the project. This includes utility markings, layout and pavement saw cutting in advance of the new water main. The contractor will also stage material throughout the project including pipe and manholes.
During the week of April 15, 2024, the contractor will begin small excavations to locate various underground utilities in preparation for the installation of the new water main. These small excavations help ensure the existing utilities will not be damaged during installation. The contractor will also stage material throughout the project including pipe and manholes.
Please watch for further information via the project website at: https://www.glenview.il.us/Pages/24Wildberry.aspx or by hand delivered notices.

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.

4/12/2024Project Mobilization
  
2024 Wildberry Water Main Improvements4/12/2024Published4/10/2024 10:04 AMTim Schwister 847-904-4422On Schedule
During the week of April 1, 2024, the contractor continued mobilization for the project. This includes utility markings, layout and pavement saw cutting in advance of the new water main. The contractor will also stage material throughout the project including pipe and manholes.

During the week of April 8, 2024, the contractor will continue mobilization for the project. This includes utility markings, layout and pavement saw cutting in advance of the new water main. The contractor will also stage material throughout the project including pipe and manholes.

Please watch for further information via the project website at: https://www.glenview.il.us/Pages/24Wildberry.aspx or by hand delivered notices.

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-442
4/5/2024Project Mobilazation