Beaver Lane reconstruction


2021 public improvement project

​​Contact information

Project Manager: Tim Schwister
(847) 904-4526​
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414​​
awebb@glenview.il.us

Project description

Improvements to Beaver Lane from Wilmette Avenue to the south cul-de-sac include:

  • Replacing existing water main with new 9-inch diameter water main
  • Upgrading existing storm sewers
  • Repairing existing sanitary sewers
  • Installing new concrete curb and gutter
  • Constructing new asphalt pavement

See the PowerPoint from the November 23, 2020 Design Open House here.

​Project information​

Contractor: Joel Kennedy Construction Corp. of Chicago​

Budget: $1,350,345 (bid with Juniper Road improvements project)

Location map: Click here

Tentative schedule​

  • Contract awarded -- March 2, 2021
  • Pre-construction meeting -- TBA​
  • Approximate start of construction -- June 1, 2021
  • Approximate completion of construction -- August 15, 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval. ​​ 

  
  
  
  
  
  
  
Update
  
  
  
Beaver Lane reconstruction8/5/2021Published7/30/2021 12:22 PMTim Schwister 847-904-4422On Schedule

This past week the contractor did not work on Beaver Lane.

During the week of August 1, The contractor is scheduled continue the landscaping work in preparation of sod. Sod will be placed when temperatures are more conducive for growth.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.
If you have any questions about the project or project updates please contact the Project Manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.

 Thank you for your patience. ​


7/30/2021Phase 3 Parkway Restoration
  
Beaver Lane reconstruction7/31/2021Published7/23/2021 4:17 PMTim Schwister 847-904-4422On Schedule

This past week the contractor placed sod in the affected areas on Beaver Ln.

The week of July 26 there is no work scheduled for Beaver.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.
Thank you for your patience. ​


7/25/2021Phase 3 Parkway Restoration
  
Beaver Lane reconstruction7/24/2021Published7/16/2021 4:17 PMTim Schwister 847-904-4422On Schedule

This past week the contractor plans to begin landscaping by placing topsoil within the disturbed areas and is anticipated to place sod the week of July 19.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.
Thank you for your patience. ​


7/18/2021Phase 3 Parkway Restoration
1 - 3Next

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.