2022 public improvement project

Project description

Approximately 2700 feet of underground utility and road improvements on Chatham Road from Glenview Road to Central Parkway including:

  • Replacement of existing deteriorated 6-inch cast iron water main with new 12-inch diameter Polyvinyl Chloride (PVC) water main
  • Upgrade existing storm sewer system
  • Complete sanitary sewer repairs, including manhole repairs and pipe replacement​
  • Construct new asphalt pavement
  • Driveway apron replacement
  • Restore the parkway with sod

See this PowerPoint presentation

Project information and updates​

Contractor: DiMeo Brothers Inc.

Budget: $2.4 million

Project NumberE16-006

Location map



Tentative Schedule

  • Bid award -- April 19, 2022  (Read Staff Report​)
  • Resident preconstruction meeting -- May 18, 2022
  • Approximate start of construction --June 1, 2022
  • Approximate completion of construction -- September 30, 2022

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​

​Contact information

Project Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us





  
  
  
  
  
  
  
Update
  
  
  
2022 Chatham Road Reconstruction9/29/2022Published9/23/2022 2:47 PMTim Schwister 847-904-4422On Schedule

During the week of September 19, the contractor directionally drilled new water main between Chatham to the east side of the river.

The week of September 26, the contractor is scheduled to directionally drill new water main under the river and connecting it at  Central. The contractor is scheduled to install sod on Chatham weather permitting.

Please watch for informational notices delivered to the front door of your home.
Further information may also be found on the project website: https://www.glenview.il.us/Pages/Chatham%20Road%20Reconstruction.aspx

If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email at tschwister@glenview.il.us or by phone at (847) 904-4422.

Thank You for your patience​


9/23/2022Phase 1 Underground Utility Improvements
  
2022 Chatham Road Reconstruction9/22/2022Published9/19/2022 4:35 PMTim Schwister 847-904-4422On Schedule

During the week of September 12, the contractor reinstated the driveway aprons. The contractor began parkway grading the parkways as well as installing sod.

The week of September 19, the contractor will complete sod installation. The contractor will also directionally drill new water main under the river along Central Road.

Please watch for informational notices delivered to the front door of your home.
Further information may also be found on the project website: https://www.glenview.il.us/Pages/Chatham%20Road%20Reconstruction.aspx

If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email at tschwister@glenview.il.us or by phone at (847) 904-4422.

Thank You for your patience​


9/16/2022Phase 3 Parkway Restoration
  
2022 Chatham Road Reconstruction9/15/2022Published9/19/2022 7:15 PMTim Schwister 847-904-4422On Schedule

During the week of September 6, the contractor reinstated the driveway aprons. The contractor will also began parkway grading as well as installing sod.

The week of September 12, the contractor will continue reinstate the driveway aprons. The contractor will also continue parkway grading as well as begin installing sod.

Please watch for informational notices delivered to the front door of your home.
Further information may also be found on the project website: https://www.glenview.il.us/Pages/Chatham%20Road%20Reconstruction.aspx

If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email at tschwister@glenview.il.us or by phone at (847) 904-4422.

Thank You for your patience​


9/9/2022Phase 3 Parkway Restoration