The Village of Glenview

Church Street reconstruction


2020 public improvement project

​Contact Information

Project  Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

The project includes approximately 0.4 miles of improvements on Church Street from Grove Street to Pine Street, including installation of 8-inch Polyvinyl Chloride (PVC) water main and water services; installation of 12-inch to 24-inch storm sewer​ to improve stomwater conveyance; repairs, removal and replacement of sanitary sewer manholes and service replacements, if necessary; and removal and replacement of the existing curb and gutter and concrete pavement with new asphalt pavement.

Project information and updates

Please note​​​Contractors and construction workers will follow these g​uidelines to keep themselves and the public safe during the COVID-19 pandemic.

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget: $1,608,702 (with Hunter Road/Court project)

Project map: Click here

Tentative schedule

  • Bid award -- February 18, 2020
  • Preconstruction meeting -- March 17, 2020
  • Tentative construction start -- April 6, 2020
  • Tentative completion of construction -- July 10, 2020

The schedule is pending and may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.  

  
  
  
  
  
  
  
Update
  
  
  
Church Street reconstruction6/27/2020Published6/19/2020 2:12 PMTom Hagerty 847-904-4421Completed

​This past week the contractor was not onsite.   

On Monday June 22, the contractor is scheduled to place the final layer of asphalt, weather permitting.

Good News! The project is completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.​


6/21/2020Project Completion
  
Church Street reconstruction6/20/2020Published6/12/2020 8:44 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor finished restoring the parkway.  

During the week of June 15, the contractor will not be working on site. 
Two Week Look Ahead – During the week of June 22, the contractor is tentatively scheduled to place the final layer of asphalt.  

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 

6/14/2020Phase 3 - Parkway Restoration
  
Church Street reconstruction6/13/2020Published6/5/2020 9:49 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor began phase III, the parkway restoration phase of this project. The contractor continued preparing the parkway for sod and completed standardized testing on the newly installed sanitary and storm sewer. 

During the week of June 8, the contractor plans to install sod. 

Throughout this phase of construction, the contractor will be working in the street and parkway. Impact to the residents should be minimal, however; we ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 

Thank you for your patience. 

6/7/2020Phase 3 - Parkway Restoration
1 - 3Next

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.​