Dewes Street reconstruction


2018 public improvement project

​Contact Information

Project  Manager: Mike DeBennette
(847) 904-4266
mdebennette@glenview.il.us

Village of Glenview Engineering: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Approximately 1,680  feet of water main installation, 370 feet of storm sewer installation,  680 feet of sanitary sewer replacement, sanitary sewer service replacement and miscellaneous repairs, HMA pavement reconstruction, pavement patching, sidewalk removal and replacement where required, driveway apron replacement, excavation and site grading, and parkway restoration.

Project information and updates

Public open house presentation: Held December 20, 2017

Public open house design meeting: Held December 20, 2017. 

Contractor: Elanar Construction Co.

Budget: $953,193

Project Blog: https://toppdeweswagner.blogspot.com/

Project map: Click here

Tentative schedule

Start date July 16, 2018
  • Water main and service replacement (3 to 4 weeks)
  • Storm sewer installation (1 to 2 weeks)
  • Roadway excavation (2 to 3 weeks)
  • Concrete curb and gutter and driveway replacement, one side of the street at a time. Access will be provided. (3 to 4 weeks)
  • First layer of asphalt paving and asphalt driveway restoration (1 week)
  • Landscape restoration (1 week), following Labor Day
  • Asphalt resurfacing (1 day), following Labor Day
 
The schedule is pending and may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.