East of Harms Stormwater Phase II


2019 public improvement project

​​Contact information

Project Manager: Mike DeBennette
(847) 904-4266
mdebennette@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

The project includes approximately 1.0 mile of water main, storm sewer, sanitary sewer and roadway improvements on Wilmette Avenue, Heatherfield Lane, Sherwood Road, Beech Drive, Mark Drive, as well as the Avoca West School parking lot in the neighborhood located East of Harms Road.

The following major improvements are included in this contract:

  • Water main improvements consist of the installation of approximately 4,200 feet of 8-inch and 1,100 feet of 12-inch polyvinyl chloride (PVC) water main pipes and replacement of water services. The new water mains will replace the existing, deteriorated cast iron water mains.
  • The storm sewer improvements include construction of additional storm sewer pipes ranging from 24-inches to 48-inches in diameter to address conveyance limitations of the existing storm sewer system. The storm sewer component of this project is partially funded through a $500,000 grant from Metropolitan Reclamation District of Greater Chicago (MWRD).
  • The sanitary sewer improvements consist of pipe repairs, removal, and replacement of sanitary sewer manholes and services replacement, if necessary.
  • Pavement reconstruction improvements consist of the complete removal of the existing pavement and replacement with new asphalt pavement, as well as replacement of the existing curb and gutter.

The project has been divided into two areas:

Area 1: Wilmette Avenue, Heatherfield Lane

Area 2: Sherwood Road, Beech Drive, Mark Drive, Cariann Lane

 

 

 

 

 

 

 

 

 

 

 

 

 

 

This project is the next phase of improvements in the East of Harms neighborhood.  Learn more about the first phase here.

On February 5, 2019, the Village Board of Trustees authorized execution of an intergovernmental agreement with the Metropolitan Water Reclamation District of Greater Chicago and an easement agreement with Avoca School District 37 for this project.

Project information and updates

Public open house design meeting: Tuesday, December 11, 2018

Pre-construction open house: 6 to 7 p.m. Monday, April 29, 2019

Contractor: DiMeo Brothers, Inc.

Budget:  $5,278,563

Project map: Click here

Tentative schedule

  • Bid opening: March 5, 2019
  • Bid Award recommendation: April 4, 2019
  • Anticipated construction start:
    • Area 1 -- May 6, 2019
    • Area 2 -- June 17, 2019
  • Anticipated completion date:
    • Area 1 -- October 25, 2019
    • Area 2 -- August 16, 2019

The schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
East of Harms Phase II - Wilmette Avenue/Heatherfield Lane/Sherwood Road/Beech Drive10/13/2019Published10/4/2019 7:54 AMMike DeBennette 847-904-4266On Schedule

​This past week the contractor finished pouring the new curb on Heatherfield Lane and Hunter Road and began backfilling behind the new curb. The contractor also began reinstating driveway aprons.

During the week of October 7th, the contractor plans to finish backfilling behind the new curb on Heatherfield Lane and Hunter Road and reinstating the driveway aprons. The contractor is also tentatively scheduled to place the first layer of asphalt on Heatherfield Lane and Hunter Road in the middle of the week, weather permitting. 


During this phase of construction, the contractor will be working in the street and the parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
10/7/2019Phase 2 - Roadway Reconstruction
  
East of Harms Phase II - Wilmette Avenue/Heatherfield Lane/Sherwood Road/Beech Drive10/6/2019Published9/30/2019 12:53 PMMike DeBennette 847-904-4266On Schedule

​This past week the contractor completed various subgrade improvements on Wilmette Avenue, and Hunter Road, from Heatherfield Lane to Wilmette Avenue. The contractor also backfilled behind the curb on Hunter Road.

During the week of September 30th, the contractor plans to finish removing the curb on Heatherfield Lane and Hunter Road in preparation for new curb. The contractor also plans to begin reinstating driveway aprons. 

While construction is occurring on each street, that street will be closed to through traffic, however alternate routes will be provided. The closures on each street will be a moving closure, meaning that the specific area of the street that is closed will change depending on where the contractor is working. The contractor will work as quickly as possible to restore traffic, but we ask for your patience with the road closures. Please adjust your schedule accordingly. 

During this phase of construction, the contractor will be working in the street and the parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
9/30/2019Phase 2 - Roadway Reconstruction
  
East of Harms Phase II - Wilmette Avenue/Heatherfield Lane/Sherwood Road/Beech Drive9/29/2019Published9/20/2019 2:19 PMMike DeBennette 847-904-4266On Schedule
This past week the contractor completed various subgrade improvements on Wilmette Avenue to prepare the roadway for the new asphalt. The contractor also poured new curb and gutter on Wilmette Avenue and Hunter.

During the week of September 23rd, the contractor plans to complete various subgrade improvements on Heatherfield Lane in preparation for the new asphalt. Towards the end of the week the contractor plans to continue excavation on Heatherfield Lane. 

While construction is occurring on each street, that street will be closed to through traffic, however alternate routes will be provided. The closures on each street will be a moving closure, meaning that the specific area of the street that is closed will change depending on where the contractor is working. The contractor will work as quickly as possible to restore traffic, but we ask for your patience with the road closures. Please adjust your schedule accordingly. 
 
During this phase of construction, the contractor will be working in the street and the parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
9/23/2019Phase 2 - Roadway Reconstruction
1 - 3Next

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.