Project description
Glenview Road from Milwaukee Avenue to Pfingsten Road and Frontage Road between Nell Lane and Pfingsten Road:
- Replacement of existing water main
- Patch asphalt roadway on Glenview Road
- Resurface asphalt roadway on Frontage Road, including spot curb and gutter repairs
- Restore the parkway
Project information and updates
Contractor: DiMeo Brothers Inc. of Elk Grove Village
Budget: $1,353,333 (bid with River Drive water main replacement project)
Project number: E20-0025
Location map:
Click here
Tentative schedule
- Bid award -- April 8, 2021
- Resident preconstruction meeting -- April 16, 2021
- Tentative construction start -- May 3, 2021
- Tentative completion of construction -- September 30, 2021
Schedule may be revised due to inclement weather or other unforeseen circumstances.
Work hours: 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. Saturday. Work outside these hours will require Village approval.