The Village of Glenview

Glenview Road improvements


2021 public improvement project

Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Glenview Road from Milwaukee Avenue to Pfingsten Road and Frontage Road between Nell Lane and Pfingsten Road:

  • Replacement of existing water main
  • Patch asphalt roadway on Glenview Road
  • Resurface asphalt roadway on Frontage Road, including​ spot curb and gutter repairs
  • Restore the parkway

Project information and updates

Contractor: TBD

Budget: $1.1 million 

Project number: E20-0025

Location map: Click ​here 

Tentative schedule

  • Bid award -- March 2021
  • Resident preconstruction meeting --  April 2021
  • Tentative construction start -- April/May 2021
  • Tentative completion of construction -- July 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours: 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
Park Manor improvements9/26/2020Published9/18/2020 9:11 AMTim Schwister 847-904-4422On Schedule

This past week the contractor finished restoring the parkway and installing sod on Montgomery Lane, Parkview Road, and Washington Street.   

During the week of September 21, the contractor will place the final layer of asphalt. 

Good News! The project is completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

9/20/2020Project Completion
  
Park Manor improvements9/19/2020Published9/11/2020 11:15 AMTim Schwister 847-904-4422On Schedule

This past week the contractor began restoring the parkway and installing sod on Montgomery Lane, Parkview Road, and Washington Street.  The contractor also completed standardized testing on the newly installed storm and sanitary sewers. 

During the week of September 14, the contractor will continue restoring the parkway and installing sod. The final placement of asphalt surface is schedule for September 22.  

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. ​


9/13/2020Phase 3 - Parkway Restoration
  
Park Manor improvements9/12/2020Published9/4/2020 8:55 AMTim Schwister 847-904-4422On Schedule

​This past week the contractor finished re-instating the driveways on Montgomery Lane. The contractor also prepared the roadway and placed the first layer of asphalt on Montgomery Lane.  

During the week of September 8, the contractor will complete standardized testing on the newly installed storm and sanitary sewers.  

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. 

9/6/2020Phase 2 - Roadway Reconstruction