The Village of Glenview

Glenview Road improvements


2021 public improvement project

Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Glenview Road from Milwaukee Avenue to Pfingsten Road and Frontage Road between Nell Lane and Pfingsten Road:

  • Replacement of existing water main
  • Patch asphalt roadway on Glenview Road
  • Resurface asphalt roadway on Frontage Road, including​ spot curb and gutter repairs
  • Restore the parkway

Project information and updates

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget: $1,353,333 (bid with River Drive water m​ain replacement project)

Project number: E20-0025

Location map: Click ​here 

Tentative schedule

  • Bid award -- April 8, 2021
  • Resident preconstruction meeting --  April 16, 2021
  • Tentative construction start -- May 3,  2021
  • Tentative completion of construction -- September 30,​ 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours: 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
2021 Glenview Road water main replacement9/2/2021Published8/27/2021 3:08 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor completed the landscaping along Glenview Road.

 

Good News! The project is completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.​


8/27/2021Project Completion
  
2021 Glenview Road water main replacement8/26/2021Published8/20/2021 11:31 AMTom Hagerty 847-904-4421On Schedule

This past week the contractor completed the curb and sidewalk removal and replacement. Additionally the contractor completed the asphalt patching on Glenview Rd. The contractor also prepared the aggregate base and completed the paving of the frontage road east of the school.

The contractor also has prepared the parkways along Glenview Rd. in advance of the new sod.

 

During the week of August 23, the contractor will install new sod for the project along Glenview Rd.

During this work there will be daily lane closures on Glenview Road to help facilitate construction. Please be alert and follow road construction signage and flagger directions.

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.​


8/20/2021Phase 2 Roadway Reconstruction
  
2021 Glenview Road water main replacement8/19/2021Published8/13/2021 3:08 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor removed and replaced select curb and sidewalk on Glenview Road. The contractor also began trench patching on Glenview Road. Additionally the contractor removed the pavement on the frontage road. The contractor plans on working Saturday on preparing the road base for the first layer of asphalt on the frontage road as well as trench patching on Glenview Road.

During the week of August 16, the contractor will pave the frontage road as well as complete the trench patching on Glenview Road

During this work there will be daily lane closures on Glenview Road to help facilitate construction. Please be alert and follow road construction signage and flagger directions.

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.​


8/13/2021Phase 2 Roadway Reconstruction
1 - 3Next

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.