Project description

Improvements on Greenbriar Drive from Greenwood Road to Lotus Lane include:

  • installing 8-inch Polyvinyl Chloride (PVC) water main and water services
  • installing 12-inch to 24-inch storm sewer to improve storm water conveyance
  • sanitary pipe repairs, removal and replacement of sanitary sewer manholes and service replacements, if necessary
  • pavement improvements, including removal and replacement of the existing curb and gutter and concrete pavements with installation of new asphalt pavement.

Project information and updates

Please note: ​​​Contractors and construction workers will follow these guidelines to keep themselves and the public safe during the COVID-19 pandemic.

Contractor: DiMeo Brothers Inc. of Elk Grove Village 

Budget: $2,187,726 (with Covert Road/Briarhill Road project) 

Location map: Click here

Tentative schedule

  • Bid award -- March 3, 2020
  • Preconstruction meeting -- March 17, 2020
  • Tentative construction start -- April 6, 2020
  • Tentative completion of construction -- July 10, 2020​

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
Update
  
  
Greenbriar Drive reconstruction7/11/2020Published7/2/2020 11:32 AMTom Hagerty 847-904-4421On Schedule

The contractor is scheduled to being work towards the end of the week of July 6. During this week the contractor will be onsite mobilizing equipment and laying out the work.  Then the contractor will begin phase I of the project, the underground improvements portion. Throughout this phase the contractor will be upgrading the storm and sanitary sewers and installing new water main.

If you have any questions please feel free to contact the Project Manager, Tom Hagerty at (847) 904-4421 or at thagerty@glenview.il.us


7/5/2020Start of Construction
Greenbriar Drive reconstruction6/20/2020Published6/12/2020 8:51 AMTom Hagerty 847-904-4421On Schedule

​The contractor, DiMeo Brothers, is scheduled to begin the project late-June. The contractor will first be onsite mobilizing equipment and laying out the work and will then begin phase I of the project. Throughout this phase the contractor will be upgrading the storm and sanitary sewer and installing new water main. 

If you have any questions please feel free to contact the Project Manager, Tom Hagerty at (847) 904-4421 or at thagerty@glenview.il.us

6/14/2020Start of Construction
Greenbriar Drive reconstruction6/6/2020Published5/29/2020 1:58 PMTom Hagerty 847-904-4421On Schedule

​Welcome to the project updates page for the Greenbriar Drive Improvements Project. DiMeo Brothers Contractors was awarded the project.

Project updates will typically be posted on Fridays of each week. If you have any questions please feel free to contact the Project Manager, Tom Hagerty at (847) 904-4421 or at thagerty@glenview.il.us

The contractor is scheduled to begin the project in early June. The contractor will first be onsite mobilizing equipment and laying out the work and will then begin phase I of the project. Throughout this phase the contractor will be upgrading the storm and sanitary sewer and installing new water main. 

5/31/2020Start of Construction