Greenbriar Drive reconstruction


2020 public improvement project

Contact information

Project Manager: Mike DeBennette
(847) 904-4266
mdebennette@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements on Greenbriar Drive from Greenwood Road to Lotus Lane include:

  • installing 8-inch Polyvinyl Chloride (PVC) water main and water services
  • installing 12-inch to 24-inch storm sewer to improve storm water conveyance
  • sanitary pipe repairs, removal and replacement of sanitary sewer manholes and service replacements, if necessary
  • pavement improvements, including removal and replacement of the existing curb and gutter and concrete pavements with installation of new asphalt pavement.

Project information and updates

Please note: ​​​Contractors and construction workers will follow these guidelines to keep themselves and the public safe during the COVID-19 pandemic.

Contractor: DiMeo Brothers Inc. of Elk Grove Village 

Budget: $2,187,726 (with Covert Road/Briarhill Road project) 

Location map: Click here

Tentative schedule

  • Bid award -- March 3, 2020
  • Preconstruction meeting -- March 17, 2020
  • Tentative construction start -- April 6, 2020
  • Tentative completion of construction -- July 10, 2020​

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
Update
  
  
Greenbriar Drive reconstruction9/26/2020Published9/18/2020 9:18 AMTom Hagerty 847-904-4421On Schedule

This past week the contractor began excavating the road in preparation for the new curbs and asphalt roadway.

During the week of September 21, the contractor will continue excavating the roadway in preparation for new curbs and asphalt. Tentatively beginning Wednesday September 23, the Group A road closure will begin. Group A area includes Greenbirar Drive from Greenwood Road to 3232 Greenbriar Drive. During this time the contractor will be removing and replacing the curb and gutter, grading the roadway, re-establishing driveway aprons, and placing the first layer of asphalt. This shutdown is expected to last from September 23 through October 2, weather permitting. 

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM.

Thank you for your patience.

9/20/2020Phase 2 Roadway Reconstruction
Greenbriar Drive reconstruction9/19/2020Published9/11/2020 9:54 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor finished installing the new storm sewer on Greenbriar Drive. 

During the week of September 14, the contractor will begin excavating the road in preparation for the new curbs and asphalt roadway. 

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. 



9/13/2020Phase 2 - Roadway Reconstruction
Greenbriar Drive reconstruction9/12/2020Published9/4/2020 8:57 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor finished transferring the new water services to the new main line. The contractor also began installing the new storm sewer on Greenbriar Drive. 

During the week of September 8, the contractor plans to finish installing the new storm sewer on Greenbriar Drive. After the storm sewer upgrades have been completed, the contractor will begin excavating the roadway in preparation for the new curbs and asphalt roadway. 

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. ​


9/6/2020Phase 1 - Underground Utility Work