The Village of Glenview

Hunter Road/Hunter Court reconstruction


2020 public improvement project

Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us 

Engineering Division Manager:  Adriana Webb
(847) 904-4414
awebb@glenview.il.us                

Project description

The project includes approximately 0.4 miles of improvements on Hunter Road and Hunter Court from Heatherfield Lane to Ferndale Road, including installation of 8-inch Polyvinyl Chloride (PVC) water main and water services; installation of 12-inch to 24-inch storm sewer​ to improve stomwater conveyance; repairs, removal and replacement of sanitary sewer manholes and service replacements, if necessary; and removal and replacement of the existing curb and gutter and concrete pavement with new asphalt pavement. 

Project information and updates

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget:  $1,608,702 (with Church Street project)

Location map:  Click here

Tentative schedule

  • Bid opening -- February 18, 2020
  • Preconstruction meeting -- March 17, 2020
  • Tentative construction start date -- April 6, 2020
  • Estimated completion date -- July 10, 2020​

The schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. Saturday. Work outside these hours will require Village approval. 

  
  
  
  
  
  
  
Update
  
  
  
Hunter Road/Hunter Court reconstruction4/11/2020Published4/3/2020 6:43 PMTom Hagerty 847-904-4421On Schedule

​This past week the contractor finished installing the water main pipe and began installing the new sanitary sewer services. These sanitary services connect each house to the mainline.

During the week of April 5, the contractor plans to finish installing the new sanitary sewer services. After the sanitary services have been updated, the contractor will begin installing the new storm sewer mainline and services.

During this phase of construction, the contractor will be working in the street and parkway. This phase of construction is expected to last about eight weeks, weather permitting. Impact to the residents should be minimal, however; we ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM.

Thank you for your patience. ​

4/5/2020Phase 1 - Underground Utility Work
  
Hunter Road/Hunter Court reconstruction4/4/2020Published3/30/2020 6:38 AMTom Hagerty 847-904-4421On Schedule

This past week the contractor began removing the existing pavement and installing the new water main pipe. The contractor is delaying any water connections that might disrupt water service to the adjacent residences until later on in the project.​

During the week of March 30, the contractor plans to finish installing the new water main. Once the water main installation is complete, the contractor plans to begin installing new sanitary sewer services which will connect each house to the mainline.  

During this phase of construction, the contractor will be working in the street and parkway. This phase of construction is expected to last about eight weeks, weather permitting. Impact to the residents should be minimal, however; we ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM.

Thank you for your patience. ​


3/29/2020Phase 1 - Underground Utility Work
  
Hunter Road/Hunter Court reconstruction3/28/2020Published3/20/2020 7:11 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor finished laying out the work and mobilizing equipment onsite. 

During the week of March 23, the contractor plans to begin phase I of this project. Phase I includes upgrading the storm and sanitary sewer mainlines and structures and installing new water services and b-boxes. Throughout the week of the 23, the contractor will begin removing the existing pavement and upgrading the water main. 

During this phase of construction, the contractor will be working in the street and parkway. This phase of construction is expected to last about eight weeks, weather permitting. Impact to the residents should be minimal, however; we ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 

Thank you for your patience. 

3/22/2020Phase 1 - Underground Utility Work
1 - 3Next

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.