The Village of Glenview

Hunter Road/Hunter Court reconstruction


2020 public improvement project

Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us 

Engineering Division Manager:  Adriana Webb
(847) 904-4414
awebb@glenview.il.us                

Project description

The project includes approximately 0.4 miles of improvements on Hunter Road and Hunter Court from Heatherfield Lane to Ferndale Road, including installation of 8-inch Polyvinyl Chloride (PVC) water main and water services; installation of 12-inch to 24-inch storm sewer​ to improve stomwater conveyance; repairs, removal and replacement of sanitary sewer manholes and service replacements, if necessary; and removal and replacement of the existing curb and gutter and concrete pavement with new asphalt pavement. 

Project information and updates

Please note: ​​​Contractors and construction workers will follow these guidelines to keep themselves and the public safe during the COVID-19 pandemic.

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget:  $1,608,702 (with Church Street project)

Location map:  Click here

Tentative schedule

  • Bid opening -- February 18, 2020
  • Preconstruction meeting -- March 17, 2020
  • Tentative construction start date -- April 6, 2020
  • Estimated completion date -- July 10, 2020​

The schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. Saturday. Work outside these hours will require Village approval. 

  
  
  
  
  
  
  
Update
  
  
  
Hunter Road Court reconstruction6/27/2020Published6/19/2020 2:11 PMTom Hagerty 847-904-4421Completed

​This past week the contractor began phase III, the parkway restoring phase of this project. During this week the contractor finished installing the sod and completed standardized testing on the new sanitary and storm sewer.    

On Monday June 22, the contractor is scheduled to place the final layer of asphalt, weather permitting.

Good News! The project is completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.


6/21/2020Project Completion
  
Hunter Road Court reconstruction6/20/2020Published6/12/2020 8:43 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor placed the first layer of asphalt, reinstated driveway aprons, and began backfilling behind the new curb.   

During the week of June 15, the contractor plans to begin phase III, the parkway restoration phase of this project. The contractor will be preparing the parkway for sod and completing standardized testing on the newly installed sanitary and storm sewer.

Throughout this phase of construction, the contractor will be working in the street and parkway.​

6/14/2020Phase 3 - Parkway Restoration
  
Hunter Road Court reconstruction6/13/2020Published6/5/2020 9:49 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor installed the new curb & gutter and re-established driveway aprons.  

During the week of June 8, the contractor plans to prepare the roadway for the first layer of asphalt and to place the first layer of asphalt in the middle of the week. 

Throughout this phase of construction, the contractor will be working in the street and parkway. Thank you for your patience. 

6/7/2020Phase 2 - Roadway Reconstruction
1 - 3Next

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.