Juniper Road reconstruction


2021 public improvement project
Contact information

Project Manager: Tim Schwister
(847) 904-4526
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements on 0.3 miles of Juniper Road between Glenview Road​ and Wilmette Avenue include:

  • installation of 8-inch Polyvinyl Chloride  (PVC) water main and water services to replace existing deteriorating 6-inch cast iron water mains
  • installation of 12-inch to 18-inch storm sewer to improve storm water conveyance, as well as drain the public right-of-way and roadway, facilitated by dedication on the east side of a 10-foot easement
  • sanitary sewer improvements, including pipe and sanitary manhole repairs
  • reconstruction of the road with new asphalt pavement after underground utilities replacement/upgrades

​Project information​

Contractor: Joel Kennedy Constructing Corp. of Chicago​

Budget: $1,350,345 (bid with Beaver Lane improvement project)

Location mapClick here

Tentative schedule

  • Contract award -- March 2, 2021 
  • Resident preconstruction meeting -- April 14, 2021
  • Approximate start of construction -- April 19, 2021
  • Approximate completion of construction -- July 2021​

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval. ​​​

  
  
  
  
  
  
  
Update
  
  
  
Juniper Road reconstruction9/17/2021Published7/9/2021 3:22 PMTim Schwister 847-904-4422On Schedule

This past week the contractor continued various base repairs in preparation for the first layer of new asphalt. 

During the week of July 12, the contractor plans to complete various base repairs. The contractor is tentatively scheduled  to place the first layer of asphalt mid to late next week.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.

Thank you for your patience.

7/12/2021Roadway construction
  
Juniper Road reconstruction8/5/2021Published7/30/2021 12:18 PMTim Schwister 847-904-4422On Schedule

This past week the contractor re-instated driveways, completed the water main leak detection, as well as began preparation for landscaping.

During the week of August 2, The contractor is scheduled to continue the landscaping work in preparation for placing the sod.
 
Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.
Thank you for your patience. ​


7/30/2021Phase 3 Parkway Restoration
  
Juniper Road reconstruction7/31/2021Published7/23/2021 4:14 PMTim Schwister 847-904-4422On Schedule

This past week the contractor completed the grading of the base of the road and placed the first layer of new asphalt. 

During the week of July 26, The contractor is tentatively scheduled begin the landscaping work in preparation of sod. Sod will be placed when teperatures are more conducive for growth. The contractor will also complete the standardized testing of the water main. Furthermore the contractor will reinstate driveways.
 
Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.
Thank you for your patience. ​


7/25/2021Phase 2 Roadway Reconstruction
1 - 3Next

​Find all project updates here.

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.