The Village of Glenview

Juniper Road reconstruction


2021 public improvement project
Contact information

Project Manager: Tim Schwister
(847) 904-4526
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements on 0.3 miles of Juniper Road between Glenview Road​ and Wilmette Avenue include:

  • installation of 8-inch Polyvinyl Chloride  (PVC) water main and water services to replace existing deteriorating 6-inch cast iron water mains
  • installation of 12-inch to 18-inch storm sewer to improve storm water conveyance, as well as drain the public right-of-way and roadway, facilitated by dedication on the east side of a 10-foot easement
  • sanitary sewer improvements, including pipe and sanitary manhole repairs
  • reconstruction of the road with new asphalt pavement after underground utilities replacement/upgrades

​Project information​

Contractor: Joel Kennedy Constructing Corp. of Chicago​

Budget: $1,350,345 (bid with Beaver Lane improvement project)

Location mapClick here

Tentative schedule

  • Contract award -- March 2, 2021 
  • Resident preconstruction meeting -- April 14, 2021
  • Approximate start of construction -- April 19, 2021
  • Approximate completion of construction -- July 2021​

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval. ​​​

  
  
  
  
  
  
  
Update
  
  
  
Juniper Road reconstruction5/22/2021Published5/14/2021 11:19 AMTim Schwister 847-904-4422On Schedule

​This past week the contractor finished removing all marked trees. 

During the week of May 17, the contractor plans to begin phase I, the underground improvements portion of this project. During this phase the contractor will install new storm sewer, install new sanitary services, and install new water main and water services. Next week the contractor will begin installing the new water main. 

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.

Thank you for your patience. 



5/16/2021Phase 1 - Underground Utility Work
  
Juniper Road reconstruction5/15/2021Published5/7/2021 8:29 AMTim Schwister 847-904-4422On Schedule

​This past week the contractor finished laying out the proposed improvements and mobilizing equipment onsite. Additionally, the contractor removed trees marked for removal. 

During the week of May 10, the contractor plans to begin phase I, the underground improvements portion of this project. During this phase the contractor will install new storm sewer, install new sanitary services, and install new water main and water services. During this week the contractor will begin installing the new water main.

Throughout this phase of construction, the contractor will be working in the street and parkway. Please note that construction hours are 7AM to 7PM Monday through Friday and 9AM to 5PM on Saturday, if necessary. ​
Thank you for your patience. 



5/9/2021Phase 1 - Underground Utility Work
  
Juniper Road reconstruction5/8/2021Published4/28/2021 10:18 AMTim Schwister 847-904-4422On Schedule

​This past week the contractor began laying out the proposed improvements and moving equipment onsite. 

During the week of May 3, the contractor plans to finish laying out the proposed improvements and mobilizing equipment. Additionally, towards the end of the week, the contractor plans to begin phase one, the underground improvements portion of the project. During this phase the contractor will install new storm pipe and structures and the install new water main and water services which will connect each house to the new main line. During this week the contractor will begin installing the new water main.

Throughout this phase of construction, the contractor will be working in the street and parkway. 
Thank you for your patience. 



5/2/2021Phase 1 - Underground Utility Work
1 - 3Next

​Find all project updates here.

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.