The Village of Glenview

Juniper Road reconstruction


2021 public improvement project
Contact information

Project Manager: Tim Schwister
(847) 904-4526
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements on 0.3 miles of Juniper Road between Glenview Road​ and Wilmette Avenue include:

  • installation of 8-inch Polyvinyl Chloride  (PVC) water main and water services to replace existing deteriorating 6-inch cast iron water mains
  • installation of 12-inch to 18-inch storm sewer to improve storm water conveyance, as well as drain the public right-of-way and roadway, facilitated by dedication on the east side of a 10-foot easement
  • sanitary sewer improvements, including pipe and sanitary manhole repairs
  • reconstruction of the road with new asphalt pavement after underground utilities replacement/upgrades

​Project information​

Contractor: Joel Kennedy Constructing Corp. of Chicago​

Budget: $1,350,345 (bid with Beaver Lane improvement project)

Location mapClick here

Tentative schedule

  • Contract award -- March 2, 2021 
  • Resident preconstruction meeting -- April 14, 2021
  • Approximate start of construction -- April 19, 2021
  • Approximate completion of construction -- July 2021​

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval. ​​​

  
  
  
  
  
  
  
Update
  
  
  
2021 Juniper Road reconstruction9/17/2021Published7/9/2021 3:22 PMTim Schwister 847-904-4422On Schedule

This past week the contractor continued various base repairs in preparation for the first layer of new asphalt. 

During the week of July 12, the contractor plans to complete various base repairs. The contractor is tentatively scheduled  to place the first layer of asphalt mid to late next week.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.

Thank you for your patience.

7/12/2021Roadway construction
  
2021 Juniper Road reconstruction9/16/2021Published9/10/2021 12:41 PMTim Schwister 847-904-4422On Schedule

The week of September 13 the contractor will begin the final landscaping including the sod installation.
 

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.​​

If you have any questions about the project or project updates please contact the Project Manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.


9/10/2021Project Completion
  
2021 Juniper Road reconstruction9/9/2021Published9/3/2021 2:02 PMTim Schwister 847-904-4422On Schedule

This past week there was no work performed on Juniper.

The week of September 7 the contractor will begin the final landscaping including the sod installation.
 
Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.

Thank you for your patience. ​


9/3/2021Phase 3 Parkway Restoration
1 - 3Next

​Find all project updates here.

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.