The week of August 1, the contractor landscaping on south side of the street behind the new curb.
The week of August 8, the contractor will also continue grading and prepping the stone base in advance of the first layer of new asphalt. The first new layer of asphalt is tentatively scheduled for August 11 or August 12. When the contractor is grading the road in advance of the first layer of asphalt as well as the day of the installation of the new asphalt, we are asking that you park off site during this phase of construction.
The contractor will be working this Saturday August 6, to begin grading and prepping the stone base in advance of the first layer of new asphalt.
Please watch for hand delivered notices prior to this activity.
Throughout this phase of construction, the contractor will be working in the street and parkway.
Please watch for informational notices delivered to the front door of your home. Further information may also be found on the project website: www.glenview.il.us/Pages/Larch%20Avenue%20Improvements.aspx
Please remember that all work and correlating dates and times are dependent on suitable weather.
If you have any questions about the project or project updates, please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or by phone (847) 904-4421.
Thank You for your patience.