The Village of Glenview

Larch Avenue Improvements


2022 public improvement project

​Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

The proposed Projects include approximately 0.20 miles of improvements on Larch Avenue between Maple Street and Magnolia Street. The following major improvements are included in the contract:

  • Replacement of existing deteriorated 6-inch cast iron water main with new 8-inch diameter Polyvinyl Chloride (PVC) water main
  • Upgrade existing storm sewer system
  • Reconstruct asphalt roadway, including limited curb and gutter replacement
  • ​Restore the parkway with sod

Project information and updates​

Contractor: H. Linden and Sons Sewer and Water Inc.

Budget: $1.2 million​

Tentative Schedule

  • Bid award -- April 5, 2022 (Read Staff Report​)
  • Resident preconstruction meeting -- April 7, 2022; 6 p.m.​​
  • Approximate start of construction --April 18, 2022
  • Approximate completion of construction -- July 29, 2022​

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​


  
  
  
  
  
  
  
Update
  
  
  
2022 Larch Avenue Improvements8/25/2022Published8/22/2022 9:38 AMTom Hagerty 847-904-4421On Schedule

The week of August 15, the contractor adjusted the manholes in the pavement to their final grade. The contractor also completed the final testing for the leak detection and storm sewer televising in advance of the final layer of asphalt.

The week of August 22, the contractor is tentatively scheduled to complete the final layer of asphalt.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.  Add a statement about the surveys….THANKS
 

Throughout this phase of construction, the contractor will be working in the street and parkway.

Please watch for informational notices delivered to the front door of your home. Further information may also be found on the project website: www.glenview.il.us/Pages/Larch%20Avenue%20Improvements.aspx

Please remember that all work and correlating dates and times are dependent on suitable weather.

If you have any questions about the project or project updates, please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or by phone (847) 904-4421.

Thank You for your patience.​


8/19/2022Phase 3 Parkway Restoration
  
2022 Larch Avenue Improvements8/18/2022Published8/12/2022 4:13 PMTom Hagerty 847-904-4421On Schedule

The week of August 8, the contractor completed grading and prepping the stone base and placed the first layer of new asphalt.

The week of August 15, the contractor will adjust the manholes in the pavement to their final grade. The contractor will also complete the final testing for the leak detection and storm sewer televising.

Please watch for hand delivered notices prior to this activity.

Throughout this phase of construction, the contractor will be working in the street and parkway.

Please watch for informational notices delivered to the front door of your home. Further information may also be found on the project website: www.glenview.il.us/Pages/Larch%20Avenue%20Improvements.aspx

Please remember that all work and correlating dates and times are dependent on suitable weather.

If you have any questions about the project or project updates, please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or by phone (847) 904-4421.

Thank You for your patience.​


8/12/2022 Phase 2 Roadway Reconstruction
  
2022 Larch Avenue Improvements8/12/2022Published8/5/2022 1:57 PMTom Hagerty 847-904-4421On Schedule

The week of August 1, the contractor landscaping on south side of the street behind the new curb.

The week of August 8, the contractor will also continue grading and prepping the stone base in advance of the first layer of new asphalt. The first new layer of asphalt is tentatively scheduled for August 11 or August 12. When the contractor is grading the road in advance of the first layer of asphalt as well as the day of the installation of the new asphalt, we are asking that you park off site during this phase of construction.

The contractor will be working this Saturday August 6, to begin grading and prepping the stone base in advance of the first layer of new asphalt.

Please watch for hand delivered notices prior to this activity.

Throughout this phase of construction, the contractor will be working in the street and parkway.

Please watch for informational notices delivered to the front door of your home. Further information may also be found on the project website: www.glenview.il.us/Pages/Larch%20Avenue%20Improvements.aspx

Please remember that all work and correlating dates and times are dependent on suitable weather.

If you have any questions about the project or project updates, please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or by phone (847) 904-4421.

Thank You for your patience.​


8/5/2022Phase II Roadway Improvements
1 - 3Next

​Find all project updates here.​​

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.​

 ​





​​