The Village of Glenview

Larch Avenue Improvements


2022 public improvement project

​Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

The proposed Projects include approximately 0.20 miles of improvements on Larch Avenue between Maple Street and Magnolia Street. The following major improvements are included in the contract:

  • Replacement of existing deteriorated 6-inch cast iron water main with new 8-inch diameter Polyvinyl Chloride (PVC) water main
  • Upgrade existing storm sewer system
  • Reconstruct asphalt roadway, including limited curb and gutter replacement
  • ​Restore the parkway with sod

Project information and updates​

Contractor: H. Linden and Sons Sewer and Water Inc.

Budget: $1.2 million​

Tentative Schedule

  • Bid award -- April 5, 2022 (Read Staff Report​)
  • Resident preconstruction meeting -- April 7, 2022; 6 p.m.​​
  • Approximate start of construction --April 18, 2022
  • Approximate completion of construction -- July 29, 2022​

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​


  
  
  
  
  
  
  
Update
  
  
  
2022 Larch Avenue Improvements5/19/2022Published5/16/2022 10:43 AMTom Hagerty 847-904-4421On Schedule

During the week of May 9, 2022, the contractor continued installing storm sewer from approximately mid-block moving towards Magnolia.

During the week of May 16, 2022, the contractor will continue installing storm sewer on Larch Street. The storm sewer work is anticipated to take one week to complete.  While the contractor is working, the road will be closed at the point of excavation. If you must come and go throughout the day, you will have to do so from which ever end of your street is open.

Again, please watch for information delivered to your home. Throughout this phase of construction, the contractor will be working in the street and parkway.

Throughout this phase of construction, the contractor will be working in the street and parkway.

Please remember these dates are dependent on suitable weather.

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.

Please watch for further information via the project website at

www.glenview.il.us/Pages/Larch%20Avenue%20Improvements.aspx  or by hand delivered notices.​


5/13/2022Phase 1 Underground Utility Improvements
  
2022 Larch Avenue Improvements5/12/2022Published5/9/2022 9:43 AMTom Hagerty 847-904-4421On Schedule

During the week of May 2, 2022, the contractor continued installing storm sewer from approximately mid-block moving towards Maple Street.

During the week of May 9, 2022, the contractor will continue installing storm sewer on Larch Street. The storm sewer work is anticipated to take the next three weeks to complete.  While the contractor is working, the road will be closed at the point of excavation. If you must come and go throughout the day, you will have to do so from which ever end of your street is open.

Again, please watch for information delivered to your home. Throughout this phase of construction, the contractor will be working in the street and parkway.

Throughout this phase of construction, the contractor will be working in the street and parkway.

Please remember these dates are dependent on suitable weather.

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.

Please watch for further information via the project website at

www.glenview.il.us/Pages/Larch%20Avenue%20Improvements.aspx  or by hand delivered notices.​


5/6/2022Phase 1 Underground Utility Improvements
  
2022 Larch Avenue Improvements5/5/2022Published4/29/2022 3:38 PMTom Hagerty 847-904-4421On Schedule

During the week of April 25, 2022, the contractor continued installing storm sewer from approximately mid-block moving towards Maple Street.

During the week of May 2, 2022, the contractor will continue installing storm sewer on Larch Street. The storm sewer work is anticipated to take the next three weeks to complete.  While the contractor is working, the road will be closed at the point of excavation. If you must come and go throughout the day, you will have to do so from which ever end of your street is open.

Again, please watch for information delivered to your home. Throughout this phase of construction, the contractor will be working in the street and parkway.

Throughout this phase of construction, the contractor will be working in the street and parkway.

Please remember these dates are dependent on suitable weather.

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.

Please watch for further information via the project website at

www.glenview.il.us/Pages/Larch%20Avenue%20Improvements.aspx  or by hand delivered notices.​


4/29/2022Phase 1 Underground Utility Improvements
1 - 3Next

​Find all project updates here.​​

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.​

 ​





​​