The Village of Glenview

Lincoln Street


2023 public improvement project
Project description


The proposed Project includes approximately 1,850 feet of improvements on Lincoln Street from Colfax Avenue to Harrison Street. 
 The following major improvements are included in this project:

  • ​Installation of new 8-inch Polyvinyl Chloride (PVC) water main with new 1 ½-inch water service lines and b-boxes
  • Storm sewer improvements
  • New curb and gutter
  • New sidewalks
  • Road reconstruction with asphalt pavement
  • Parkway restorations with sod

LincolnMap2023.png

Contact information

Project Manager: Tim Schwister, Project Manager
(847) 904-4422

tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: A Lamp Concrete Contractors, Inc. of Schaumburg, Illinois      

Budget: $2.8 million

​​​Tentative Schedule

  • ​​​Bid notice published – February 9, 2023 
  • Bid opening date – February 23, 2023 
  • Bid award – March 21, 2023 
  • Pre-construction meeting – April 13, 2023
  • Approximate starting date of construction – April 2023
  • Approximate completion of construction – Late August 2023
Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.


​​​Notices

Pre-construction meeting letter

​​​Handouts

Design meeting handout

​​​Board of Trustees actions

March 21, 2023 -- Contract award to A Lamp Concrete Contractors, Inc., of Schaumburg, Ill.

Resolution

Staff Report

​​​Project Updates

Sign up​ to be emailed project updates.​​


  
  
  
  
  
  
  
Update
  
  
  
2023 Lincoln Street Improvements9/15/2023Published9/8/2023 2:36 PMTim Schwister 847-904-4422On schedule

The week of September 5, the contractor will complete standardized testing as well as installation of the new sod.

The week of September11, the contractor is scheduled to install the final layer of asphalt.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

 

We ask that you please drive slow through the construction sites. This is for your safety as well as the construction workers and other pedestrians. This will also help to curtail the dust from the construction.

Please watch for further information via the project website at: https://www.glenview.il.us/Pages/LincolnStreet.aspx or by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.

 


9/15/2023Phase III Construction
  
2023 Lincoln Street Improvements9/1/2023Published8/25/2023 3:14 PMTim Schwister 847-904-4422On schedule

The week of August 21, the contractor installed the first layer of asphalt. The contractor also re-instated all the driveways. The contractor will also adjust the structures in the road as well as complete the final leak detection and sewer televising.

The week of August 28, the contractor will complete standardized testing as well as installation of the new sod.

Please watch for hand delivered notices for when you are asked to be out of your driveway.

 We ask that you please drive slow through the construction sites. This is for your safety as well as the construction workers and other pedestrians. This will also help to curtail the dust from the construction.

Please watch for further information via the project website at: https://www.glenview.il.us/Pages/LincolnStreet.aspx or by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.


9/1/2023Phase III Final Landscape and Paving
  
2023 Lincoln Street Improvements8/24/2023Published8/18/2023 2:27 PMTim Schwister 847-904-4422On Schedule

The week of August 14, the contractor completed the new curb and sidewalk installation. The contractor began excavating the road and placing the aggregate base in advance of the first layer of new pavement.
The week of August 21, the contractor will install the first layer of asphalt. The contractor will also adjust the structures in the road as well as complete the final leak detection and sewer televising.
Please watch for hand delivered notices for when you are asked to be out of your driveway.
 We ask that you please drive slow through the construction sites. This is for your safety as well as the construction workers and other pedestrians. This will also help to curtail the dust from the construction.
Please watch for further information via the project website at: https://www.glenview.il.us/Pages/LincolnStreet.aspx  or by hand delivered notices.

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.



8/18/2023Phase 2 Roadway Reconstruction
1 - 3Next