Project description

The project consists of approximately 2,400 feet of water main installation, 1,580 feet of storm sewer installation, HMA pavement removal, HMA surface removal, HMA pavement resurfacing, concrete curb and gutter removal and replacement, concrete sidewalk removal and replacement, miscellaneous driveway apron replacement, parkway restoration, and miscellaneous items of work.

Project information and updates

Resident Preconstruction meeting: Held June 14, 2018

Contractor: DiMeo Brothers Inc.

Budget:  $1,311,498

Project Blog: Weekly updates can be found on the project blog at: https://locustandlinden.blogspot.com/

Project map: Click here

Tentative schedule

Start date is July 9, 2018.

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.