The Village of Glenview

Linneman Reconstruction


2024 public improvement project
Project description

The proposed Project includes approximately 0.6 miles of improvements on Linneman Street from Harlem Road to Elm Street and Elm Street from Linneman Street to Henley Street, including alleys to east and west of Spruce.

 The following major improvements are included in this project:

  • Installation of approximately 2,400 feet of 8-inch Polyvinyl Chloride (PVC) water main and services on Linneman Street and Spruce Street
  • Installation of 1,500 feet of new 12-inch storm sewer
  • Sanitary sewer manholes repair and replacement of sanitary services, if necessary
  • New curb and gutter and reconstruction of the road with new asphalt pavement

Linneman.png

Contact Information

Project Manager: Tom Hagerty, Project Manager
(847) 904-4421
thagerty@glenview.il.us

Engineering Inspector: Dayvohn Braxton
(847) 904-4238
dbraxton@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: DiMeo Brothers Inc. of Elk Grove Village, Illinois

Budget: $1.97 million

​​​Tentative Schedule

  • Bid Award Date: January 29, 2024

    • Resident pre-construction meeting – February 13, 2024, at Village Hall 6 p.m.

    • Approximate starting date of construction – March  2024

    • Approximate completion of construction – July/August 2024

     Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.


Notices

​​Pre-Construction Meeting Letter

Handouts

Design Open House Handout

Board of Trustees Actions​​​​​

Resolution

Staff Report​​




  
  
  
  
  
  
  
Update
  
  
  
2024 Linneman Reconstruction​2/23/2024Published2/20/2024 12:55 PMTom Hagerty 847-904-4421On Schedule

Welcome to the project updates page for the Linneman and Elm Street Reconstruction Project. Project updates will typically be posted on Fridays of each week. The contract was awarded to DiMeo Brothers Inc. of Elk Grove Village Illinois.

During the week of February 26, 2024, the contractor will begin mobilization for the project. This includes utility markings and layout and pavement saw cutting in advance of the new water main and storm sewer. The contractor will also stage material throughout the project including pipe and manholes.

The week of March 4, 2024, the contractor will begin installing new water main tentatively beginning at Elm Street and work towards Harlem Avenue. Installation of the new water main is anticipated to take four weeks.

Please remember these dates are dependent on suitable weather.

Please watch for further information via the project website at

or by hand delivered notices.

 

 If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.​


2/16/2024Project Initiation
Sign up​ to be emailed project updates.​