The Village of Glenview

Linneman Reconstruction


2023 public improvement project
Project description

The proposed Project includes approximately 0.6 miles of improvements on Linneman Street from Larkdale Drive to Elm Street and Spruce Street from Linneman Street to Henley Street, including alleys to east and west of Spruce.

 The following major improvements are included in this project:

  • Installation of approximately 2,400 feet of 8-inch Polyvinyl Chloride (PVC) water main and new 1 ½ inch water services
  • Installation of 1,500 feet of new storm sewer
  • Sanitary sewer manholes repair and replacement of sanitary services, if necessary
  • New curb and gutter and reconstruction of the road with new asphalt pavement
  • Parkway restoration with sod
  • Alley improvements

Contact Information

Project Manager: Tom Hagerty, Project Manager
(847) 904-4421
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget: $2.48 million

​​​Tentative Schedule

  • Bid Award Date: February 7, 2023

    • Resident pre-construction meeting – March 2, 2023, at Village Hall 6:45 p.m.

    • Approximate starting date of construction – April 1, 2023

    • Approximate completion of construction – August 1, 2023

     Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are   7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.


Notices

​​Pre-Construction Meeting Letter

Handouts

Design Open House Handout

Board of Trustees Actions​​​​​

Feb. 7, 2023 -- Read Staff Report​​​




  
  
  
  
  
  
  
Update
  
  
  
2023 Linneman Reconstruction​8/18/2023Published8/11/2023 3:17 PMTom Hagerty 847-904-4421On schedule

The week of August 7th, the contractor completed installing the first layer of new asphalt in the alleys.  The contractor also completed the installation of the topsoil and began installing the new sod.

The week of August 14th, the contractor will prepare the road for the final layer of asphalt. This will include cleaning and priming the road. The primer is what makes the new asphalt adhere to the existing asphalt. The final asphalt work including priming is schedule for August 15 and 16 of next.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

 

Please watch for further information via the project website at: https://www.glenview.il.us/Pages/Linneman%20Reconstruction.aspx or by hand delivered notices.

 

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.


8/18/2023Final Paving
  
2023 Linneman Reconstruction​8/11/2023Published8/4/2023 3:30 PMTom Hagerty 847-904-4421On schedule

The week of July 31st, the contractor completed installing the first layer of new asphalt in the alleys.  The contractor also completed the installation of the topsoil and began installing the new sod.

The week of August 7th, the contractor will be completing the standardized testing including leak detection and sewer televising. The contractor will also complete the landscaping as well as standardized testing.

The final asphalt paving is scheduled the week of August 14. 

Please watch for further information via the project website at: https://www.glenview.il.us/Pages/Linneman%20Reconstruction.aspx or by hand delivered notices.

 

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.


8/11/2023Phase III Landscaping and final asphalt
  
2023 Linneman Reconstruction​8/4/2023Published7/28/2023 4:03 PMTom Hagerty 847-904-4421On schedule

The week of July 24th the contractor began excavating the alleys in advance of the new pavement. The contractor completed the balance of the curb and sidewalk near the alleys. The contractor also completed the installation of the topsoil in advance of the new sod.

The week of July 31st, the contractor is tentatively scheduled to install the first layer of new asphalt in the alley. The contractor will be completing the standardized testing including leak detection and sewer televising.

If you have an irrigation system in the right of way that needs to be repaired, the next two weeks would be appropriate for the repairs prior to the sod being installed.

We ask that you please drive slow through the construction sites. This is for your safety as well as the construction workers and other pedestrians. This will also help to curtail the dust from the construction.

Please watch for further information via the project website at: https://www.glenview.il.us/Pages/Linneman%20Reconstruction.aspx or by hand delivered notices.

 

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.


8/4/2023Phase III Landscaping
1 - 3Next
Sign up​ to be emailed project updates.​