Project description

Improvements on Longvalley Road from Woodland Drive to west cul-de-sac and Woodland Drive from Central Road to Coronet Road include:

  • replacement of existing water main
  • improvements to existing storm sewer system
  • repairs to various sanitary sewer
  • construction of a new asphalt roadway, including curb and gutter construction on Woodland Drive through Special Service Area 96
  • parkway restoration

Public hearings on establishing Special Service Area 96 were held February 18, 2020 and March 3, 2020. The Village Board of Trustees voted preliminary approval February​ 18 and final approval March 3.

Project information and updates

Contractor: TBD

Budget: $2,824,115

Location map: Click here

Tentative schedule

  • Bid award -- April 2020
  • Preconstruction meeting -- May 2020
  • Approximate construction start -- May 2020
  • Estimated completion date -- October 2020

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours: 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.