The Village of Glenview

Longvalley Road/Woodland Drive reconstruction


2020 public improvement projects

​Contact information

Project Manager: Mike DeBennette
(847) 904-4466
mdebennette@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements on Longvalley Road from Woodland Drive to west cul-de-sac and Woodland Drive from Central Road to Coronet Road include:

  • replacement of existing water main
  • improvements to existing storm sewer system
  • repairs to various sanitary sewer, including pipe repairs, removal and replaement of sanitary sewer manholes and service replacements, if necessary
  • construction of a new asphalt roadway, including curb and gutter construction on Woodland Drive through Special Service Area 96
  • parkway restoration

Public hearings on establishing Special Service Area 96 were held February 18, 2020 and March 3, 2020. The Village Board of Trustees voted preliminary approval February​ 18 and final approval March 3.

Project information and updates

Please note: ​​​Contractors and construction workers will follow these guidelines to keep themselves and the public safe during the COVID-19 pandemic.​

Contractor: Bolder Contractors Inc. of Cary

Budget: $3,094,747​

Location map: Click here

Tentative schedule

  • Bid award -- May 28, 2020
  • Preconstruction meeting -- June 4, 2020
  • Approximate construction start --June 15, 2020
  • Estimated completion date -- October 30, 2020

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours: 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.