The Village of Glenview

Montgomery Lane reconstruction - Phase II


2021 public improvement project

​Contact information

Project  Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us​​

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements to about one-quarter of a mile of Montgomery Lane, north of McArthur Drive, including Golf and Cedar courts, include: 

  • installing about 1,300 linear feet of 8-inch Polyvinyl Chloride (PVC) water main and water services to replace existing, deteriorating 6-inch cast iron water mains 
  • installing about 1,500 feet of 12-inch to 18-inch storm sewer to improve storm water conveyance
  • sanitary pipe repairs and service replacements, if necessary
  • pavement improvements, including removal and replacement of the asphalt pavement, sidewalks and concrete curb and gutter

Project information and updates​

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget: $1,379,386

Location map: Click here

Tentative schedule

  • ​Bid award: January 19, 2021
  •  Resident preconstruction meeting: March 5, 2021
  • Tentative construction start: March 29, 2021
  • Tentative construction completion: July 15, 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are from  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
2021 Montgomery Lane reconstruction Phase II11/11/2021Published11/5/2021 3:45 PMTim Schwister 847-904-4422On Schedule

This past week the contractor completed the grading of the parkways as well as completed the installation of the new sod.

During the week of November 8, the contractor will complete the final layer of asphalt.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.
 

If you have any questions about the project or project updates please contact the Project Manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


11/5/2021Project Completion
  
2021 Montgomery Lane reconstruction Phase II11/4/2021Published10/29/2021 3:48 PMTim Schwister 847-904-4422On Schedule

This past week the contractor continued grading the parkways in advance of installation of the new sod. The contractor will also complete the final layer of asphalt on the driveways.

During the week of November 1, the contractor will complete the grading of the parkways as well as complete the installation of the new sod.

Throughout this phase of construction, the contractor will be working in the street and parkway.

If you have any questions about the project or project updates please contact the Project Manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


10/29/2021Phase 3 Parkway Restoration
  
2021 Montgomery Lane reconstruction Phase II10/28/2021Published10/22/2021 2:07 PMTim Schwister 847-904-4422On Schedule

This past week the contractor began grading the parkways in advance of installation of the new sod. The contractor also completed curb and sidewalk installation as well as installing the first layer of new asphalt on Montgomery from Golf Ct to McArthur including Golf and Cedar Courts.

During the week of October 25, the contractor continues grading the parkways in advance of installation of the new sod. The contractor will also complete the final layer of asphalt on the driveways.

Throughout this phase of construction, the contractor will be working in the street and parkway.

If you have any questions about the project or project updates please contact the Project Manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


10/22/2021Phase 3 Parkway Restoration
1 - 3Next

​Find all project updates here.

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.