The Village of Glenview

Montgomery Lane reconstruction - Phase II


2021 public improvement project

​Contact information

Project  Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us​​

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements to about one-quarter of a mile of Montgomery Lane, north of McArthur Drive, including Golf and Cedar courts, include: 

  • installing about 1,300 linear feet of 8-inch Polyvinyl Chloride (PVC) water main and water services to replace existing, deteriorating 6-inch cast iron water mains 
  • installing about 1,500 feet of 12-inch to 18-inch storm sewer to improve storm water conveyance
  • sanitary pipe repairs and service replacements, if necessary
  • pavement improvements, including removal and replacement of the asphalt pavement, sidewalks and concrete curb and gutter

Project information and updates​

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget: $1,379,386

Location map: Click here

Tentative schedule

  • ​Bid award: January 19, 2021
  •  Resident preconstruction meeting: March 5, 2021
  • Tentative construction start: March 29, 2021
  • Tentative construction completion: July 15, 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are from  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
Montgomery Lane reconstruction Phase II10/21/2021Published10/15/2021 2:16 PMTim Schwister 847-904-4422On Schedule

This past week the contractor will begin placing the new curb and sidewalk on both sides of Montgomery from Golf Ct to McArthur including Golf and Cedar Courts.

During the week of October 18, the contractor began grading the parkways in advance of installation of the new sod. The contractor will also prepare the roadway for the installation of the first layer of new asphalt. The contractor is scheduled to place the first layer of asphalt the mid to late next week.

Throughout this phase of construction, the contractor will be working in the street and parkway.

If you have any questions about the project or project updates please contact the Project Manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.

​ 


10/15/2021Phase 2 Roadway Reconstruction
  
Montgomery Lane reconstruction Phase II10/14/2021Published10/11/2021 2:43 PMTim Schwister 847-904-4422On Schedule

This past week the contractor began excavating the roadway in advance of the new curb.

During the week of October 11, the contractor will begin placing the new curb and sidewalk on both sides of Montgomery from Golf Ct to McArthur including Golf and Cedar Courts. Please watch for hand delivered letters with further instruction for parking during the new curb installation and the first layer of new asphalt.

Throughout this phase of construction, the contractor will be working in the street and parkway.

If you have any questions about the project or project updates please contact the Project Manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


10/8/2021Phase 2 Roadway Reconstruction
  
Montgomery Lane reconstruction Phase II10/7/2021Published10/1/2021 2:07 PMTim Schwister 847-904-4422On Schedule

This past week the contractor completed upgrading the storm sewer. The contractor began excavating the roadway in advance of the new curb.

During the week of October 4, the contractor will continue excavating the roadway in advance of the new curbs.

Throughout this phase of construction, the contractor will be working in the street and parkway.

If you have any questions about the project or project updates please contact the Project Manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


10/1/2021Phase 1 Underground Utility Improvements
1 - 3Next

​Find all project updates here.

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.