The Village of Glenview

Montgomery Lane reconstruction - Phase II


2021 public improvement project

​Contact information

Project  Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us​​

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements to about one-quarter of a mile of Montgomery Lane, north of McArthur Drive, including Golf and Cedar courts, include: 

  • installing about 1,300 linear feet of 8-inch Polyvinyl Chloride (PVC) water main and water services to replace existing, deteriorating 6-inch cast iron water mains 
  • installing about 1,500 feet of 12-inch to 18-inch storm sewer to improve storm water conveyance
  • sanitary pipe repairs and service replacements, if necessary
  • pavement improvements, including removal and replacement of the asphalt pavement, sidewalks and concrete curb and gutter

Project information and updates​

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget: $1,379,386

Location map: Click here

Tentative schedule

  • ​Bid award: January 19, 2021
  •  Resident preconstruction meeting: March 5, 2021
  • Tentative construction start: March 29, 2021
  • Tentative construction completion: July 15, 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are from  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
Montgomery Lane reconstruction Phase II8/5/2021Published7/30/2021 12:25 PMTim Schwister 847-904-4422On Schedule

This past week the contractor began mobilizing equipment and materials to Montgomery Lane. The contractor also pulverized the existing pavement in advance of water main installation next week.
During the week of August 2, the contractor will begin phase one, the underground improvements phase of the project. During this phase the contractor will install new storm and sanitary pipe and structures and the install new water main and water services which will connect each house to the new main line. During this week the contractor will begin installing the new water main.

On Monday August 2 the contractor is scheduled to complete a water main connection in advance of beginning the new water main installation. While water main connection work is being completed, residents will experience a water service interruption which could last up to two hours. You will be notified in advance of any water service interruption. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience. Once the new water connection has been made at Mcarthur  Drive the new water main installation will begin at Mcatrhur Drive and move north to Golf Ct.

Throughout this phase of construction, the contractor will be working in the street and parkway.

If you have any questions about the project or project updates please contact the Project Manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


7/30/2021Phase 1 Underground Utility Improvements
  
Montgomery Lane reconstruction Phase II7/24/2021Published7/16/2021 4:29 PMTim Schwister 847-904-4422On Schedule

Welcome to the project updates pages for the Montgomery Lane Improvements Project. Project updates will typically be posted on Fridays of each week. The contract was awarded to DiMeo Bros. Inc. and the project is anticipated to start toward end of July. The project will consist of new water main as well as new storm sewers and Sanitary sewer repairs. The project will also consist of new curbs, sidewalks as well as new pavement.

If you have any questions about the project or project updates please contact the Project Manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.

Please go to this project web page to sign up for weekly updates: https://www.glenview.il.us/Pages/Montgomery.aspx


7/18/2021Welcome Blog

​Find all project updates here.

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.