Project description

In 2019, the Village secured a $1 million grant and entered into an Intergovernmental Agreement  with the U.S. Army Corps of Engineers to construct storm water improvements benefiting the Glen Oak Acres neighborhood, which was originally constructed without storm sewers. 

This project consists of:​

  • installation of about 900 feet of 24-inch reinforced concrete storm sewer along the western parkway of Wagner Road from Huckleberry Lane to Del Ogier Drive, including construction of new storm sewer along Del Ogier Drive from Wagner Road to the existing outfall of the North Branch of the Chicago River.
  • construction of 300 linear feet of storm sewer pipes ranging from 12 inches to 48 inches in diameter along Woodlawn Street
  • construction of 350 linear feet of 30-inch, in-line detention pipe along Wagner Road, including pavement restoration

Along Wagner Road, some trees will be removed, parkways restored and driveways replaced, along with pavement patching. Along Woodlawn Road and Del Ogier Drive, curbs will be replaced and roadway will be resurfaced.

Project information and updates​

Please note: ​​​Contractors and construction workers will follow these guidelines to keep themselves and the public safe during the COVID-19 pandemic.

Contractor: Kovilic Construction Company of Franklin Park

Budget: $1,912,186 ($1,189,077 from the U.S. Army Corps of Engineers, $723,109 from Village of Glenview)

Project Number: E18-025​

Location map: ​

Tentative Schedule

  • Bid award and U.S. Army Corps notice to proceed -- October 2019
  • Bid award by the Village -- January 7, 2020
  • Approximate start of construction -- March 15, 2020
  • Approximate completion of construction -- October 2020

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
North Glen Oak Acres stormwater improvements11/28/2020Published11/20/2020 10:08 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor completed various outstanding items and prepared for the sidewalk installation along Wagner Road.

During the week of November 23, the contractor plans to continue project clean up and begin restoring the parkway. The contractor will not be working Thursday November 26 due to the holiday. The contractor is tentatively scheduled to finish restoring the parkway Friday November 27.

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. 



11/22/2020Phase 3 - Parkway Restoration
  
North Glen Oak Acres stormwater improvements11/21/2020Published11/13/2020 2:10 PMTom Hagerty 847-904-4421On Schedule

​This past week the contractor finished the storm sewer upgrades on Wagner Road. The contractor also completed the asphalt repair work on De L’oiger Drive, Woodlawn Road, and Wagner Road.

During the week of November 16, the contractor plans to complete various outstanding items and prepare for the sidewalk installation along Wagner Road.

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. 



11/15/2020Phase 2 - Roadway Reconstruction
  
North Glen Oak Acres stormwater improvements11/14/2020Published11/6/2020 9:55 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor continued the storm sewer upgrades on Wagner Road. 

During the week of November 9, the contractor plans to finish upgrading the storm sewer pipe and structures on Wagner Road. Additionally, the contractor is tentatively scheduled to begin the asphalt repairs on De L’ogier Drive and Woodlawn Road on Monday November 9.

NOTICE: On Saturday November 7, starting at 8:00 AM the contractor will be working onsite. During this time the contractor will be completing adjustments on the newly installed structures.  

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. 



11/8/2020Phase 1 - Underground Utility Work
1 - 3Next

​Find all project updates here.​​

 