Project description

In 2019, the Village secured a $1 million grant and entered into an Intergovernmental Agreement  with the U.S. Army Corps of Engineers to construct storm water improvements benefiting the Glen Oak Acres neighborhood, which was originally constructed without storm sewers. 

This project consists of:​

  • installation of about 900 feet of 24-inch reinforced concrete storm sewer along the western parkway of Wagner Road from Huckleberry Lane to Del Ogier Drive, including construction of new storm sewer along Del Ogier Drive from Wagner Road to the existing outfall of the North Branch of the Chicago River.
  • construction of 300 linear feet of storm sewer pipes ranging from 12 inches to 48 inches in diameter along Woodlawn Street
  • construction of 350 linear feet of 30-inch, in-line detention pipe along Wagner Road, including pavement restoration

Along Wagner Road, some trees will be removed, parkways restored and driveways replaced, along with pavement patching. Along Woodlawn Road and Del Ogier Drive, curbs will be replaced and roadway will be resurfaced.

Project information and updates​

Please note: ​​​Contractors and construction workers will follow these guidelines to keep themselves and the public safe during the COVID-19 pandemic.

Contractor: Kovilic Construction Company of Franklin Park

Budget: $1,912,186 ($1,189,077 from the U.S. Army Corps of Engineers, $723,109 from Village of Glenview)

Project Number: E18-025​

Location map:  Click here

Tentative Schedule

  • Bid award and U.S. Army Corps notice to proceed -- October 2019
  • Bid award by the Village -- January 7, 2020
  • Approximate start of construction -- March 15, 2020
  • Approximate completion of construction -- October 2020

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
North Glen Oak Acres stormwater improvements9/26/2020Published9/18/2020 9:16 AMTom Hagerty 847-904-4421On Schedule

This past week the contractor continued installing the new storm sewer pipe on Woodland Road. Nicor also began relocating the gas main on Wagner Road between Burton Terrace and Huckleberry Lane.

During the week of September 21, the contractor plans to finish installing the new storm sewer pipe and structures on Woodland Road. The contractor will also make the final storm sewer connection on Del Ogier Drive. Nicor will continue work to relocate the gas main on Wagner Road between Burton Terrace and Huckleberry Lane. This work should last approximately 2 more weeks. During this work, traffic will be reduced to one lane at times which may impact travel during working hours. The contractor cannot continue the utility upgrades until Nicor has finished relocating the gas main.

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM.

Thank you for your patience.

9/20/2020Phase 1 Underground Utility Improvements
  
North Glen Oak Acres stormwater improvements9/19/2020Published9/11/2020 9:53 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor continued installing the new storm sewer pipe on Woodland Road. 

During the week of September 14, the contractor will continue installing the new storm sewer pipe and structures on Woodland Road. 

Starting Monday September 14, Nicor will begin re-locating the gas main on Wagner Road between Burton Terrace and Huckleberry Lane. This work should last approximately 3 weeks. Traffic will be reduced to one lane at times. This may impact travel during working hours.
Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. 



9/13/2020Phase 1 - Underground Utility Work
  
North Glen Oak Acres stormwater improvements9/12/2020Published9/4/2020 8:56 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor continued installing the new storm sewer pipe on Woodland Road. The contractor also completed the storm sewer upgrades near 1615 Del Ogier Drive. 

During the week of September 8, the contractor will continue installing the new storm sewer pipe and structures on Woodland Road. 

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. 