The Village of Glenview

North Glen Oak Acres stormwater improvements


2020 public improvement project

​Contact information

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

In 2019, the Village secured a $1 million grant and entered into an Intergovernmental Agreement  with the U.S. Army Corps of Engineers to construct storm water improvements benefiting the Glen Oak Acres neighborhood, which was originally constructed without storm sewers. 

This project consists of:​

  • installation of about 900 feet of 24-inch reinforced concrete storm sewer along the western parkway of Wagner Road from Huckleberry Lane to Del Ogier Drive, including construction of new storm sewer along Del Ogier Drive from Wagner Road to the existing outfall of the North Branch of the Chicago River.
  • construction of 300 linear feet of storm sewer pipes ranging from 12 inches to 48 inches in diameter along Woodlawn Street
  • construction of 350 linear feet of 30-inch, in-line detention pipe along Wagner Road, including pavement restoration

Along Wagner Road, some trees will be removed, parkways restored and driveways replaced, along with pavement patching. Along Woodlawn Road and Del Ogier Drive, curbs will be replaced and roadway will be resurfaced.

Project information and updates​

Please note: ​​​Contractors and construction workers will follow these guidelines to keep themselves and the public safe during the COVID-19 pandemic.

Contractor: Kovilic Construction Company of Franklin Park

Budget: $1,912,186 ($1,189,077 from the U.S. Army Corps of Engineers, $723,109 from Village of Glenview)

Project Number: E18-025​

Location map:  Click here

Tentative Schedule

  • Bid award and U.S. Army Corps notice to proceed -- October 2019
  • Bid award by the Village -- January 7, 2020
  • Approximate start of construction -- March 15, 2020
  • Approximate completion of construction -- October 2020

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
North Glen Oak Acres stormwater improvements7/11/2020Published7/2/2020 11:27 AMTom Hagerty 847-904-4421On Schedule

This past week the contractor began boring pipe under Wagner Road at Del Ogier Drive.

During the week of July 6, the contractor will continue boring pipe under Wagner Road at Del Ogier Drive.

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM.

Thank you for your patience. ​


7/5/2020Phase 1 - Underground Utility Work
  
North Glen Oak Acres stormwater improvements7/4/2020Published6/25/2020 11:54 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor dug the receiving pit and Wagner Road and Del Ogier Drive

During the week of June 29, the contractor will begin boring pipe under Wagner Road at Del Ogier Drive.

On Friday July 3 the contractor will not be working onsite due to the holiday.

Throughout this phase of construction, the contractor will be working in the street and parkway We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM.

Thank you for your patience. 


6/28/2020Phase 1 - Underground Utility Work
  
North Glen Oak Acres stormwater improvements6/27/2020Published6/19/2020 2:17 PMTom Hagerty 847-904-4421On Schedule

​This past week the contractor dug the boring pit at Wagner Road.  

During the week of June 22, the contractor will begin digging the receiving pit and Wagner Road and Del Ogier Drive.

Throughout this phase of construction, the contractor will be working in the street and parkway. This phase of construction is expected to last about ten weeks weather permitting. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM.

Thank you for your patience. ​


6/21/2020Phase 1 - Underground Utility Work
1 - 3Next

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.