Park Manor improvements


2020 public improvement project

Contact information

Project Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

The project includes approximately 0.79 miles of improvements on Montgomery Lane, south of Colfax Avenue, and Parkview Road and Washington Street between Harrison Street and Colfax Avenue.

These major improvements include:

  • Installing approximately 4,200 linear feet of 8-inch Polyvinyl Chloride​ (PVC) water main and water services. The new 8-inch water mains will replace the existing deteriorating 6-inch cast iron water mains.
  • Installing approximately 4,180 feet of 12-inch to 18-inch storm sewer to improve stormwater conveyance
  • Sanitary sewer pipe repairs and service replacements, as necessary
  • Removing and replacing the asphalt pavement, sidewalks and new concrete curb and gutter on Montgomery Lane, Parkview Road and Washington Street

Project information and updates

Please note: ​​​Contractors and construction workers will follow these​ guidelines to keep themselves and the public safe during the COVID-19 pandemic.

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget: $2,764,508 

Location maps: Click here (Montgomery/Walnut) 

                                    Click here (Parkview/Washington)

Tentative schedule

  • Bid award -- February 18, 2020
  • Preconstruction meeting --  March 17, 2020
  • Tentative construction start -- April 6, 2020
  • Tentative completion of construction -- September 18, 2020​

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours: 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
Park Manor improvements9/26/2020Published9/18/2020 9:11 AMTim Schwister 847-904-4422On Schedule

This past week the contractor finished restoring the parkway and installing sod on Montgomery Lane, Parkview Road, and Washington Street.   

During the week of September 21, the contractor will place the final layer of asphalt. 

Good News! The project is completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

9/20/2020Project Completion
  
Park Manor improvements9/19/2020Published9/11/2020 11:15 AMTim Schwister 847-904-4422On Schedule

This past week the contractor began restoring the parkway and installing sod on Montgomery Lane, Parkview Road, and Washington Street.  The contractor also completed standardized testing on the newly installed storm and sanitary sewers. 

During the week of September 14, the contractor will continue restoring the parkway and installing sod. The final placement of asphalt surface is schedule for September 22.  

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. ​


9/13/2020Phase 3 - Parkway Restoration
  
Park Manor improvements9/12/2020Published9/4/2020 8:55 AMTim Schwister 847-904-4422On Schedule

​This past week the contractor finished re-instating the driveways on Montgomery Lane. The contractor also prepared the roadway and placed the first layer of asphalt on Montgomery Lane.  

During the week of September 8, the contractor will complete standardized testing on the newly installed storm and sanitary sewers.  

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. 

9/6/2020Phase 2 - Roadway Reconstruction
1 - 3Next

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.