The Village of Glenview

Park Manor improvements


2020 public improvement project

Contact information

Project Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

The project includes approximately 0.79 miles of improvements on Montgomery Lane, south of Colfax Avenue, and Parkview Road and Washington Street between Harrison Street and Colfax Avenue.

These major improvements include:

  • Installing approximately 4,200 linear feet of 8-inch Polyvinyl Chloride​ (PVC) water main and water services. The new 8-inch water mains will replace the existing deteriorating 6-inch cast iron water mains.
  • Installing approximately 4,180 feet of 12-inch to 18-inch storm sewer to improve stormwater conveyance
  • Sanitary sewer pipe repairs and service replacements, as necessary
  • Removing and replacing the asphalt pavement, sidewalks and new concrete curb and gutter on Montgomery Lane, Parkview Road and Washington Street

Project information and updates

​Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget: $2,764,508 

Location maps: Click here (Montgomery/Walnut) 

                                    Click here (Parkview/Washington)

Tentative schedule

  • Bid award -- February 18, 2020
  • Preconstruction meeting --  March 17, 2020
  • Tentative construction start -- April 6, 2020
  • Tentative completion of construction -- September 18, 2020​

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours: 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
Park Manor improvements4/11/2020Published4/3/2020 6:46 PMTim Schwister 847-904-4422On Schedule

​This past week the contractor removed the existing pavement on Parkview Road and Washington Street. The contractor also began upgrading the water main.

During the week of April 5, the contractor plans to finish upgrading the water main on Parkview and Washington Street. After the water main in installed the contractor will begin upgrading the storm sewer mainline and services.  

During this phase of construction, the contractor will be working in the street and parkway. This phase of construction is expected to last about eight weeks, weather permitting. Impact to the residents should be minimal, however; we ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM.

Thank you for your patience. ​


4/15/2019Phase 1 - Underground Utility Work
  
Park Manor improvements4/4/2020Published3/27/2020 2:56 PMTim Schwister 847-904-4422On Schedule

​This past week the contractor finished laying out the work and mobilizing equipment onsite. 

During the week of March 30, the contractor plans to begin phase I of this project. Phase I includes upgrading the storm and sanitary sewer mainlines and structures and installing new water services and b-boxes. Starting Tuesday March 31, the contractor will begin removing the existing pavement on Parkview Road and Washington Street. After the pavement has been removed then the contractor will begin installing new water main on Washington Street and then move to Parkview Road.

During this phase of construction, the contractor will be working in the street and parkway. This phase of construction is expected to last about eight weeks, weather permitting. Impact to the residents should be minimal, however; we ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM.

Thank you for your patience. ​


3/29/2020Phase 1 - Underground Utility Work
  
Park Manor improvements3/28/2020Published3/20/2020 7:11 AMTim Schwister 847-904-4422On Schedule

​Welcome to the project updates page for the Montgomery Lane, Parkview Road, and Washington Street Improvements Project. The contractor, DiMeo Brothers Inc., was awarded the project.

Project updates will typically be posted on Fridays of each week. If you have any questions please feel free to contact the Project Manager, Tim Schwister at (847) 904-4422 or at tschwister@glenview.il.us

The preconstruction meeting, which was originally scheduled for March 12, was cancelled. Although the preconstruction meeting was cancelled, the construction project will still be occurring.  

The contractor is scheduled to begin the project the week of March 23. During this week the contractor plans to be onsite mobilizing equipment and laying out the work. During the week of March 30, the contractor plans to begin phase I of the project. Throughout this phase the contractor will be upgrading the storm and sanitary sewers and installing new water services and b-boxes. This phase of construction is expected to take 8 weeks. 

3/22/2020Start of Construction

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.