The Village of Glenview

Parkview Reconstruction


2022 public improvement project
Project description

The proposed Project includes approximately .25 miles of improvements on Parkview Road between Golf Road and the Cul de sac North of McArthur Drive. The following major improvements are included in the contract:

  • ​Water main improvements include the installation of approximately 1100 of 8-inch Polyvinyl Chloride (PVC) water mains and services. The new water main will replace the existing, deteriorated water main.
  • The proposed storm sewer improvements consist of upgrading of 1100 feet of storm sewer system ranging from 12 to 24-inch pipe.
  • The proposed sanitary sewer improvements consist of sanitary manhole repairs and replacement of sanitary services, if necessary.
  • The proposed pavement improvements consist of trench patching over utility installations and the entire stretch of Spruce Street from Harrison Street to Colfax Avenue will receive a full-depth resurfacing

parkview.png

Contact information

Project Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: Lenny Hoffman Excavating

Budget: $1 million

Tentative Schedule

  • Bid award -- April 5, 2022
  • Resident preconstruction meeting -- May 5, 2022, 6 p.m. at the intersection of Parkview and McArthur
  • Approximate start of construction --June 27, 2022
  • Approximate completion of construction -- Sept. 23, 2022

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​


  
  
  
  
  
  
  
Update
  
  
  
2022 Parkview Reconstruction8/12/2022Published8/5/2022 1:59 PMTom Hagerty 847-904-4421On Schedule

The week of August 1, the contractor will continue installing water main on Parkview Road beginning at Golf Road going North towards McArthur.

The week of August 8, the contractor is tentatively scheduled begin installing the new water services between Golf Road and McArthur, which connect each house to the new main line. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience.

Please remember these dates are dependent on suitable weather.

Throughout this phase of construction, the contractor will be working in the street and parkway

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


8/5/2022Phase I Underground
  
2022 Parkview Reconstruction8/4/2022Published7/29/2022 3:51 PMTim Schwister 847-904-4422On Schedule

The week of July 25, the contractor will continue installing water main on Parkview Road beginning at Golf Road going North towards McArthur.

The week of August 1, the contractor will continue installing water main on Parkview Road continuing going North towards the cul de sac north of McArthur.

Please remember these dates are dependent on suitable weather.

Throughout this phase of construction, the contractor will be working in the street and parkway

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


7/29/2022Phase 1 Underground Utility Improvements
  
2022 Parkview Reconstruction7/29/2022Published7/25/2022 7:10 AMTim Schwister 847-904-4422On Schedule

The week of July 18, the contractor will begin installing water main on Parkview Road beginning at Golf Road going North towards McArthur. While this work is being completed, residents may experience a water service interruption which could last up to two hours. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience. If you will be affected, you will be notified in advance. Again, please watch for information delivered to your home.

The week of July 25, the contractor will continue installing water main on Parkview Road continuing going North towards the Cul de sac.

Please remember these dates are dependent on suitable weather.

Throughout this phase of construction, the contractor will be working in the street and parkway

 If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


7/25/2022Phase I Underground
1 - 3Next

​Find all project updates ​​here.​​​

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.​

 





​​