The Village of Glenview

Parkview Reconstruction


2022 public improvement project
Project description

The proposed Project includes approximately .25 miles of improvements on Parkview Road between Golf Road and the Cul de sac North of McArthur Drive. The following major improvements are included in the contract:

  • ​Water main improvements include the installation of approximately 1100 of 8-inch Polyvinyl Chloride (PVC) water mains and services. The new water main will replace the existing, deteriorated water main.
  • The proposed storm sewer improvements consist of upgrading of 1100 feet of storm sewer system ranging from 12 to 24-inch pipe.
  • The proposed sanitary sewer improvements consist of sanitary manhole repairs and replacement of sanitary services, if necessary.
  • The proposed pavement improvements consist of trench patching over utility installations and the entire stretch of Spruce Street from Harrison Street to Colfax Avenue will receive a full-depth resurfacing

parkview.png

Contact information

Project Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project information and updates​

Contractor: Lenny Hoffman Excavating

Budget: $1 million

Tentative Schedule

  • Bid award -- April 5, 2022
  • Resident preconstruction meeting -- May 5, 2022, 6 p.m. at the intersection of Parkview and McArthur
  • Approximate start of construction --June 27, 2022
  • Approximate completion of construction -- Sept. 23, 2022

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​


  
  
  
  
  
  
  
Update
  
  
  
2022 Parkview Reconstruction10/13/2022Published10/7/2022 2:48 PMTim Schwister 847-904-4422On Schedule

This past week the contractor completed the final asphalt for the driveway aprons. The contractor also began placing the final landscaping including the new sod.

The week of October 10, the contractor will complete the final landscaping including the new sod. The contractor will also prime the new roadway and place the final layer of asphalt.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.
 

Please remember these dates are dependent on suitable weather.

Throughout this phase of construction, the contractor will be working in the street and parkway

If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


10/7/2022Phase 3 Parkway Restoration
  
2022 Parkview Reconstruction9/30/2022Published9/30/2022 4:30 PMTim Schwister 847-904-4422On Schedule

This past week the contractor graded the road in preparation as well as installing the first layer of new asphalt.

The week of October 3, the contractor will adjust the structures in the road. The contractor will also perform the final standardized testing.

We appreciate your patience during this time.

Please remember these dates are dependent on suitable weather.

Throughout this phase of construction, the contractor will be working in the street and parkway

If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


9/26/2022Phase II Roadway Improvements
  
2022 Parkview Reconstruction9/29/2022Published9/23/2022 2:48 PMTim Schwister 847-904-4422On Schedule

The week of September 19, the contractor completed the new curbs and sidewalks on the west side of Parkview between Golf Road through the North side of the cul-de-sac.

The week of September 26, the contractor will grade the road in advance of the first layer asphalt. The first layer of asphalt is anticipated to installed mid-week. The contractor will adjust the structures in the road and final layer of asphalt is scheduled for September 30.

We appreciate your patience during this time.

Please remember these dates are dependent on suitable weather.

Throughout this phase of construction, the contractor will be working in the street and parkway

If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.​


9/23/2022Phase 2 Roadway Reconstruction
1 - 3Next

​Find all project updates ​​here.​​​

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.​

 





​​