Project description​

The Village of Glenview is implementing a roundabout at the intersection of Patriot Boulevard and the Costco Access Roadway to improve traffic operations and to make the conditions safer for pedestrians, cyclists and motorists.

Since the development opened, customers of the area businesses experience regular traffic delays exiting and entering the Costco, Costco Gas Station and Home Depot sites due to competing turning movements and high traffic volumes, particularly during peak hours of operations. The proposed intersection modifications will improve traffic operations and allow more vehicles to proceed on their way without needing to wait, improve safety and reduce vehicle emissions at this intersection, as well as make the conditions safer for pedestrians and cyclists.

Installing roundabouts in place of traffic signals or stop signs has been found to reduce carbon monoxide emissions by 15-45 percent, nitrous oxide emissions by 21-44 percent, carbon dioxide emissions by 23-34 percent and hydrocarbon emissions by 0-40 percent. Constructing roundabouts in place of traffic signals or stop signs also reduced fuel consumption by an estimated 23-34 percent​.

In addition, the Village's traffic study showed that during peak hours of traffic, the Level of Service (LOS) at the intersection will improve from a 'C' grade to an 'A'. An 'A' grade intersection is defined as one that is highly stable with free-flow conditions and little to no congestion.​

A dedicated southbound right turn lane will also be added at this location to address existing traffic queuing during peak hours of business operations. Decorative colored concrete islands, street lighting and landscaping are also planned to enhance this business corridor within The Glen.


You can also learn more about how to navigate the roundabout with this short video​.​

Construction staging will be implemented to minimize disruptions to businesses during construction, with an anticipated start in June 2022.


Public Open House​

The Village held an Open House for resident input and questions on Jan. 25. Click here to view the presentation.


Contact in
formation

Project Manager: Tom Hagerty

(847) 904-4421
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us​



Project information a​​nd updates​

Contractor: Chicago Paving, Inc.

Budget: $1.1 million 

Project Number: E20-0026

Video: ​https://vimeo.com/616361612​​


Additional information about roundabouts can be viewed on the
Federal Highway Administration (FHA) website. ​


Tentative Schedule
  • Bid award -- December 7, 2022 
  • Approximate start of construction --June 2022
  • Approximate completion of construction -- September 2022

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday. Work outside these hours will require Village approval.​


  
  
  
  
  
  
  
Update
  
  
  
2022 Patriot/Costco Roundabout11/11/2022Published11/4/2022 2:42 PMTom Hagerty 847-904-4421On Schedule

This week the contractor placed the asphalt leveling binder early in the week.  The final layer of asphalt for the roundabout project will be place on Monday, November 7. Striping is scheduled to be completed early Tuesday morning.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.
 

Further information may also be found on the project website:

www.glenview.il.us/Pages/Patriot-Costco%20Roundabout.aspx

If you have any questions about the project or project updates, please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or by phone (847) 904-4421.

Thank You for your patience​


11/4/2022Phase III Completion
  
2022 Patriot/Costco Roundabout11/4/2022Published10/29/2022 10:21 AMTom Hagerty 847-904-4421On Schedule

This week, the contractor completed the stamped concrete in the center islands. The contractor also completed milling the pavement in advance of the final surface.

The week of October 31, final surface is tentatively scheduled to be placed on Monday October 31st. and Tuesday November 1. The contractor will also complete the new pavement striping.

Please remember that the work and correlating dates and times are dependent on suitable weather.

Further information may also be found on the project website:

www.glenview.il.us/Pages/Patriot-Costco%20Roundabout.aspx

If you have any questions about the project or project updates, please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or by phone (847) 904-4421.

Thank You for your patience​


10/28/2022Phase 2 Roadway Reconstruction
  
2022 Patriot/Costco Roundabout10/28/2022Published10/21/2022 3:51 PMTom Hagerty 847-904-4421On Schedule

This week, the contractor completed the pavement removal and installation  of the curb for the remainder of the roundabout islands. The contractor completed the installation of the new sod and landscaping.

The week of October 24, the contractor will complete the stamped concrete in the center islands. The contractor will also mill the pavement in advance of the final surface. Final surface is tentatively scheduled for the end of next week.

Please remember that the work and correlating dates and times are dependent on suitable weather.

Further information may also be found on the project website:

www.glenview.il.us/Pages/Patriot-Costco%20Roundabout.aspx

If you have any questions about the project or project updates, please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or by phone (847) 904-4421.

Thank You for your patience​


10/21/2022Phase II Roadway Improvements
1 - 3Next

​Find all project updates here.​​

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.​

 





​​