The Village of Glenview

Pleasant Lane reconstruction


2021 public improvement project

Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us 

Engineering Division Manager:  Adriana Webb
(847) 904-4414
awebb@glenview.il.us                

Project description

Pleasant Lane from Waukegan Road to Sunset Ridge Road and the private road labeled Burr Oak Drive from Pleasant Lane to Sunset Ridge Road:

  • Replacement of existing water main
  • Improve existing storm sewer system
  • Complete various sanitary sewer repairs
  • Construct new asphalt roadway, including sidewalk and curb and gutter construction within the boulevard on Pleasant Lane
  • Restore​ the parkway

Project information and updates

Contractor: TBD

Budget:  $1,93 million

Project number: E18-0014

Location map:  Click here

Tentative schedule

  • Bid award-- March/April 2021
  • Resident preconstruction meeting -- April 2021
  • Tentative construction start date -- April/May 2021
  • Tentative completion date -- October 2021

The schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. Saturday. Work outside these hours will require Village approval. 

  
  
  
  
  
  
  
Update
  
  
  
Hunter Road Court reconstruction6/27/2020Published6/19/2020 2:11 PMTom Hagerty 847-904-4421Completed

​This past week the contractor began phase III, the parkway restoring phase of this project. During this week the contractor finished installing the sod and completed standardized testing on the new sanitary and storm sewer.    

On Monday June 22, the contractor is scheduled to place the final layer of asphalt, weather permitting.

Good News! The project is completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.


6/21/2020Project Completion
  
Hunter Road Court reconstruction6/20/2020Published6/12/2020 8:43 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor placed the first layer of asphalt, reinstated driveway aprons, and began backfilling behind the new curb.   

During the week of June 15, the contractor plans to begin phase III, the parkway restoration phase of this project. The contractor will be preparing the parkway for sod and completing standardized testing on the newly installed sanitary and storm sewer.

Throughout this phase of construction, the contractor will be working in the street and parkway.​

6/14/2020Phase 3 - Parkway Restoration
  
Hunter Road Court reconstruction6/13/2020Published6/5/2020 9:49 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor installed the new curb & gutter and re-established driveway aprons.  

During the week of June 8, the contractor plans to prepare the roadway for the first layer of asphalt and to place the first layer of asphalt in the middle of the week. 

Throughout this phase of construction, the contractor will be working in the street and parkway. Thank you for your patience. 

6/7/2020Phase 2 - Roadway Reconstruction
1 - 3Next

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.