The Village of Glenview

Pleasant Lane reconstruction


2021 public improvement project

Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us 

Engineering Division Manager:  Adriana Webb
(847) 904-4414
awebb@glenview.il.us                

Project description

Pleasant Lane from Waukegan Road to Sunset Ridge Road and the private road labeled Burr Oak Drive from Pleasant Lane to Sunset Ridge Road:

  • Replacement of existing water main
  • Improve existing storm sewer system
  • Complete various sanitary sewer repairs
  • Construct new asphalt roadway, including sidewalk and curb and gutter construction within the boulevard on Pleasant Lane
  • Restore​ the parkway

Project information and updates

Contractor: Joel Kennedy Constructing Corp. of Chicago

Budget:  $1,777,778

Project number: E18-0014

Location map:  Click here

Tentative schedule

  • Resident Design meeting -- January 7, 2021
  • Bid award-- April 8, 2021
  • Resident preconstruction meeting -- May 5, 2021
  • Tentative construction start date -- May 17, 2021
  • Tentative completion date -- September​ 10, ​2021

The schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. Saturday. Work outside these hours will require Village approval. 

  
  
  
  
  
  
  
Update
  
  
  
2021 Pleasant Lane reconstruction10/7/2021Published10/1/2021 1:54 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor completed the final layer of asphalt and re-instated all driveways. The contractor also began sod installation and should complete the sod installation early next week.

Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

If you have any questions about the project or project updates please contact the Project Manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.​


10/1/2021Project Completion
  
2021 Pleasant Lane reconstruction9/30/2021Published9/24/2021 3:19 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor completed grading the parkways and placing topsoil in advance of installation of the sod. The contractor removed the top 2 inches of pavement on the west end of the project at Waukegan Road In advance of the final layer of asphalt. Additionally, the contractor planted the trees along the center island.

During the week of September 27, the contractor will pave the final layer of asphalt on Monday or Tuesday. Subsequently, after the final layer of asphalt is installed, the contractor will complete the asphalt driveways. The contractor is tentatively scheduled to begin the installation of sod the end of next week.

Reminder
All the work for this project has taken place within the Village of Glenview right-of-way areas. If you have private property within these areas (for example, a sprinkler system, fences, special decorative rocks, or plantings), the Village does not replace or repair private items located in the public right-of-way that were damaged due to construction within the public right-of-way.

During this project, Pleasant Lane will experience intermittent lane closures to help facilitate construction. Please watch for signage and flaggers to help direct traffic through the construction site
.
Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.

If you have any questions, please contact Tom Hagerty at thagerty@glenview.il.us or by phone at (847) 904-4421.
Thank you for your patience.                   ​


9/24/2021Phase 2 Roadway Reconstruction
  
2021 Pleasant Lane reconstruction9/23/2021Published9/17/2021 2:45 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor finished the sidewalks in the center island and began grading the center island and parkways for landscaping.

During the week of September 20, the contractor will finish grading the parkways and placing topsoil in advance of installation of the sod. Also, next week the contractor will remove the top 2 inches of pavement on the west end of the project at Waukegan Road.

The final layer of asphalt is tentatively scheduled for September 27.

Reminder
All the work for this project has taken place within the Village of Glenview right-of-way areas. If you have private property within these areas (for example, a sprinkler system, fences, special decorative rocks, or plantings), the Village does not replace or repair private items located in the public right-of-way that were damaged due to construction within the public right-of-way.

During this project, Pleasant Lane will experience intermittent lane closures to help facilitate construction. Please watch for signage and flaggers to help direct traffic through the construction site


Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.

If you have any questions, please contact Tom Hagerty at thagerty@glenview.il.us or by phone at (847) 904-4421.
Thank you for your patience.                   


9/17/2021Phase 2 Roadway Reconstruction
1 - 3Next

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.