The Village of Glenview

Pleasant Lane reconstruction


2021 public improvement project

Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us 

Engineering Division Manager:  Adriana Webb
(847) 904-4414
awebb@glenview.il.us                

Project description

Pleasant Lane from Waukegan Road to Sunset Ridge Road and the private road labeled Burr Oak Drive from Pleasant Lane to Sunset Ridge Road:

  • Replacement of existing water main
  • Improve existing storm sewer system
  • Complete various sanitary sewer repairs
  • Construct new asphalt roadway, including sidewalk and curb and gutter construction within the boulevard on Pleasant Lane
  • Restore​ the parkway

Project information and updates

Contractor: Joel Kennedy Constructing Corp. of Chicago

Budget:  $1,777,778

Project number: E18-0014

Location map:  Click here

Tentative schedule

  • Resident Design meeting -- January 7, 2021
  • Bid award-- April 8, 2021
  • Resident preconstruction meeting -- May 5, 2021
  • Tentative construction start date -- May 17, 2021
  • Tentative completion date -- September​ 10, ​2021

The schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. Saturday. Work outside these hours will require Village approval. 

  
  
  
  
  
  
  
Update
  
  
  
Pleasant Lane reconstruction8/5/2021Published7/30/2021 12:20 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor completed  Phase I (the underground utility improvements), and proceed to Phase II, the road reconstruction. Phase II includes excavating the existing roadway to accommodate the new road base and asphalt. This will also include the excavation and installation of the new curb and sidewalk in the center island of the road and the first layer of new asphalt.

Phase II began this week, starting on the east end of the project working from Sunset Ridge going west and began on the north half of the road and then subsequently move to the south half of the road. This includes removing the existing asphalt and existing stone base while at the same time installing the new stone base. You will have access to your driveway throughout this time except when they are working directly in front of your driveway.  During this work, your driveway will be blocked for a short period of time but will be open by the end of the working day. You will be notified the day in advance that the contractor will be working in front of your home.

During the week of August 2 the contractor will continue working on phase II road reconstruction continuing from Sunset Ridge and moving west to Waukegan Road.

During this project, Pleasant Lane will experience intermittent lane closures to help facilitate construction. Please watch for signage and flaggers to help direct traffic through the construction site.
Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.
If you have any questions, please contact Tom Hagerty at thagerty@glenview.il.us or by phone at (847) 904-4421.
Thank you for your patience. ​


7/30/2021Phase 2 Roadway Reconstruction
  
Pleasant Lane reconstruction7/31/2021Published7/23/2021 4:15 PMTom Hagerty 847-904-4421On Schedule

This past week the Contractor completed the installation of new sanitary services. The contractor began installing storm sewer from Sunset Ridge moving West.

During the week of July 26, the contractor will continue installing storm sewer throughout the project moving from Sunset Ridge going West.

During this project, Pleasant Lane will experience intermittent lane closures to help facilitate construction. Please watch for signage and flaggers to help direct traffic through the construction site.
Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.

Thank you for your patience. ​


7/25/2021Phase 1 Underground Utility Improvements
  
Pleasant Lane reconstruction7/24/2021Published7/16/2021 4:15 PMTom Hagerty 847-904-4421On Schedule

This past week the Contractor will complete the installation of new sanitary services. This is only for the homes that are on the North side of the street due to their services crossing under the road. The contractor is continuing to work from Sunset Ridge and working toward Waukegan Road.

During the week of July 19, the contractor will begin upgrading the storm sewer throughout the project. Tentatively the contractor will start near Sunset Ridge and work towards Waukegan Rd.  

During this project Pleasant Lane will experience intermittent lane closures to help facilitate construction. Please watch for signage and flaggers to help direct traffic through the construction site.
Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.

Thank you for your patience. ​


7/18/2021Phase 1 Underground Utility Improvements
1 - 3Next

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.