The Village of Glenview

Pleasant Lane reconstruction


2021 public improvement project

Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us 

Engineering Division Manager:  Adriana Webb
(847) 904-4414
awebb@glenview.il.us                

Project description

Pleasant Lane from Waukegan Road to Sunset Ridge Road and the private road labeled Burr Oak Drive from Pleasant Lane to Sunset Ridge Road:

  • Replacement of existing water main
  • Improve existing storm sewer system
  • Complete various sanitary sewer repairs
  • Construct new asphalt roadway, including sidewalk and curb and gutter construction within the boulevard on Pleasant Lane
  • Restore​ the parkway

Project information and updates

Contractor: Joel Kennedy Constructing Corp. of Chicago

Budget:  $1,777,778

Project number: E18-0014

Location map:  Click here

Tentative schedule

  • Resident Design meeting -- January 7, 2021
  • Bid award-- April 8, 2021
  • Resident preconstruction meeting -- May 5, 2021
  • Tentative construction start date -- May 17, 2021
  • Tentative completion date -- September​ 10, ​2021

The schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. Saturday. Work outside these hours will require Village approval. 

  
  
  
  
  
  
  
Update
  
  
  
Pleasant Lane reconstruction5/22/2021Published5/14/2021 11:20 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor was not working onsite. 

During the week of May 17, the contractor will began laying out the proposed improvements, mobilizing equipment onsite, and saw cutting the existing pavement in preparation for the upcoming work.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.
Thank you for your patience. 



5/16/2021Start of Construction
  
Pleasant Lane reconstruction5/15/2021Published5/7/2021 8:29 AMTom Hagerty 847-904-4421On Schedule

​Welcome to the project updates pages for the Pleasant Lane Improvements Project. Project updates will typically be posted on Fridays of each week. The contract was awarded to Joel Kennedy Constructing Corp. If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.

During the week of May 17, the contractor will be onsite mobilizing equipment and laying out the proposed improvement work in preparation for phase I, the underground improvements portion of this project. During this phase the contractor will be installing new storm sewer, sanitary sewer, and water main, water services, and b-boxes. 

Please note that construction hours are 7AM to 7PM Monday through Friday and 9AM to 5PM on Saturday, if necessary. 

5/9/2021Start of Construction

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.