Contact information
Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us
Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us
Project description
Improvements to River Drive from Glenview Road to Dewes Street/Waukegan Road include:
- Replacing the existing water main
- Improving existing storm sewers
- Resurfacing the asphalt roadway
- Restoring the parkway
Project information and updates
Contractor: DiMeo Brothers Inc. of Elk Grove Village
Budget:$1,353,333 (bid with Glenview Road water main replacement project)
Project number: E20-0031
Location map: Click here
Tentative schedule
- Contract award -- April 8, 2021
- Resident preconstruction meeting: April 16, 2021
- Approximate start of construction -- May 3, 2021
- Approximate completion of construction -- September 30, 2021
Schedule may be revised due to inclement weather or other unforeseen circumstances.
Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. Saturday. Work outside these hours will require Village approval.