River Drive water main replacement


2021 public improvement project

​​Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@g​lenview.il.us

Engineering Division Manager: Adriana Webb​
(847) 904-4414
awebb@glenview.il.us

Project description​

Improvements to River Drive from Glenview Road to Dewes Street/Waukegan Road include:

  • Replacing the existing water main
  • Improving existing storm sewers
  • Resurfacing the asphalt roadway
  • Restoring the parkway

Project information and updates

​Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget:$1,​353,333 (bid with Glenview Road water main replacement project)

Project number: E20-0031

Location map: Click here

Tentative schedule​

  • ​Contract award -- April 8, 2021
  • Resident preconstruction meeting: April 16, 2021
  • Approximate start of construction -- May 3​, 2021
  • Approximate completion of construction -- September 30, 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​​ 

Content Editor

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.