Robincrest Watermain Replacement


2022 public improvement project

​Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

The proposed Project includes approximately 1 mile of improvements on Robincrest Avenue, Wissing Lane, Lincoln Street, Garden Court and Spruce Street Improvements between Harms Avenue and Shermer Road. The following major improvements are included in the contract:

  • ​Replacement of existing water main with new 8-inch diameter Polyvinyl Chloride (PVC) water main
  • Upgrade existing storm sewer system
  • Resurface the asphalt roadway, including limited curb and gutter replacement
  • Restore the parkway with sod


Project information and updates​

Contractor: Martam Construction Inc.

Budget: $4 million

Tentative Schedule

  • Bid award -- April 19, 2022
  • Resident preconstruction meeting -- May 11, 2022, 6 p.m. at the intersection of Robincrest and Spruce streets
  • Approximate start of construction --May 23, 2022
  • Approximate completion of construction -- Oct. 14, 2022

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​


  
  
  
  
  
  
  
Update
  
  
  
2022 Robincrest Watermain Replacement9/29/2022Published9/23/2022 2:45 PMTom Hagerty 847-904-4421On Schedule

During the week of September 19, the contractor completed installing the new water services and the final water connections on Robincrest. Furthermore, the contractor completed new storm sewer installation at various locations. The contractor also saw cut select curb and sidewalks for removal and replacement. Due to a shortage of cement from supply chain, the curb removal and replacement has been tentatively pushed back to the week of October 10.

The week of September 26, the contractor will begin paving of the water main trenches. The contractor will begin at Harlem and move to the west towards Shermer. If your driveway will be impacted, you will receive a notice in advance asking you to remove your vehicle for the day.

Please watch for information delivered to your home.

Throughout this phase of construction, the contractor will be working in the street and parkway.

Please watch for informational notices delivered to the front door of your home. Further information may also be found on the project website:

https://www.glenview.il.us/Pages/Robincrest%20Watermain%20Replacement.aspx  

Please remember that the work and correlating dates and times are dependent on suitable weather.

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.

Thank You for your patience​


9/23/2022Phase 2 Roadway Reconstruction
  
2022 Robincrest Watermain Replacement9/22/2022Published9/19/2022 4:33 PMTom Hagerty 847-904-4421On Schedule

During the week of September 12, the contractor completed installing the new water services and the final water connections on Robincrest. Furthermore, the contractor completed new storm sewer installation at various locations.

The week of September 19, the contractor will begin removing and replacing select curbs and sidewalks on Robincrest. If we are replacing curb in front of your driveway you will be notified in advance to remove your car from your driveway and suggestions on where to park during this time.

Please watch for information delivered to your home.

Throughout this phase of construction, the contractor will be working in the street and parkway.

Please watch for informational notices delivered to the front door of your home. Further information may also be found on the project website:

https://www.glenview.il.us/Pages/Robincrest%20Watermain%20Replacement.aspx  

Please remember that the work and correlating dates and times are dependent on suitable weather.

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.

Thank You for your patience​


9/16/2022Phase 2 Roadway Reconstruction
  
2022 Robincrest Watermain Replacement9/15/2022Published9/19/2022 7:01 PMTom Hagerty 847-904-4421On Schedule

During the week of September 6, the contractor continued installing the new water services on Robincrest continuing from Spruce Street and Shermer, which connect each house to the new main. Residents will receive notice before their new water service is scheduled to be installed. While the contractor is connecting your new service, you will experience a water service interruption that could last up to one hour. The Village understands that not having water, even for a short period of time, is an inconvenience and we greatly appreciate your patience. Please watch for information delivered to your home.

The week of September 12, the contractor will complete all watermain connections and miscellaneous storm sewer activities.

Please watch for information delivered to your home.

Throughout this phase of construction, the contractor will be working in the street and parkway.

Please watch for informational notices delivered to the front door of your home. Further information may also be found on the project website:

https://www.glenview.il.us/Pages/Robincrest%20Watermain%20Replacement.aspx  

Please remember that the work and correlating dates and times are dependent on suitable weather.

If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.

Thank You for your patience​


9/9/2022Phase 1 Underground Utility Improvements
1 - 3Next

​Find all project updates here.​​

 ​