The Village of Glenview

Russet Way improvements


2021 public improvement projects

Contact information

Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements on Russet Way from Crestwood Drive to Carousel Drive include:

  • Replacement of existing water main
  • Improvements to the existing storm sewer system
  • Completing various sanitary sewer repairs
  • Construction of new asphalt roadway with curb and gutter
  • Restoration of the parkway

Project information and updates

Contractor: DiMeo Brothers

Budget: $665,900

Location map: Click here

Tentative schedule

  • Bid award: April 2020
  • Resident Pre-construction meeting: April 1,​ 2021
  • Tentative construction start: April 5 2021
  • Tentative construction completion: June 2021

​Schedule may be revised due to inclement weather or other unforeseen circumstances.

Works hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
2021 Russet Way improvements6/5/2021Published5/28/2021 12:30 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor finished removing the old asphalt and preparing the roadway for the final layer of asphalt.  

During the week of June 1, the contractor is tentatively scheduled to place the final layer of asphalt on Tuesday June 1, weather permitting.

Good News! The project is completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

 

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.​


5/30/2021Project Completion
  
2021 Russet Way improvements5/29/2021Published5/21/2021 3:10 PMTom Hagerty 847-904-4421On Schedule

This past week the contractor finished the roadway base repairs and placed the asphalt patches along Russet Way. Additionally, the contractor also finished restoring the parkway.

During the week of May 24, the contractor will begin preparing the roadway for the final layer of the asphalt surface. The contractor is tentatively scheduled to remove the old asphalt on Monday.  The final layer of asphalt is planned to be placed towards the end of the week, weather permitting.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.

Thank you for your patience. ​


5/23/2021Phase 3 - Parkway Restoration
  
2021 Russet Way improvements5/22/2021Published5/14/2021 11:18 AMTom Hagerty 847-904-4421On Schedule

This past week the contractor framed and poured the new concrete curb, sidewalk, and driveways. The contractor also began restoring the parkway. 

NOTICE: The contractor will be working Saturday May 15 from 9 am to 1 pm. During this time the contractor will continue restoring the parkway. 

During the week of May 17, the contractor will begin the roadway base repairs and will be placing asphalt patches along Russet Way. This work will begin at Carousel Drive and move towards Crestwood Drive and is expected to take three days to complete. While the contractor is completing the asphalt patching in front of your driveway the access to your driveways may be impacted for up to two hours. If you plan to have to move your vehicle multiple times during the patching work The Village asks that you please park off the project site to help optimize construction. The Village appreciates your understanding.  

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.
Thank you for your patience. 