Shermer Road multi-use path construction


2019-2020 public improvement project

​Contact information

Project Manager: Mike DeBennette
(847) 904-4266
mdebennette@glenview.il.us                          

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Glenview and Northbrook are jointly constructing a 2-mile, 8- to 10-foot-wide multi-use path along the east side of Shermer Road between West Lake Avenue and Willow Road, including under the Union Pacific Railroad overpass. The path will accommodate both pedestrians and cyclists, and is an extension of the existing path on West Lake Avenue. It will also connect to the Techny Trail regional system; the trail system along Willow Road in Northbrook; several Metra stations; The Glen Town Center; and downtown districts.

Just under $1 million from a federal grant will cover 80 percent of the project, with Glenview and Northbrook splitting the remaining $288,000 cost.

  • November 20, 2018 -- Authorized a bid award to Baxter & Woodman Inc. of Crystal Lake for Phase III engineering services and authorized the Illinois Transportation Enhancement Program (ITEP) federal fund appropriation
  • August 20, 2019 -- Executed construction-related expenditures through the Illinois Department of Transportation and an Intergovernmental Agreement with the Village of Northbrook

Project information and updates

Contractor: M.Q. Water Sewer Contractors Inc.

Budget: $1,256,190

Project number: BGZV(391)

Tentative schedule

  • Project bid award -- June 2019
  • Pre-construction meeting -- August 29, 2019  
  • Anticipated construction start -- September 3, 2019
  • Anticipated completion -- October 30, 2019

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
2019 Shermer Road multi-use path11/10/2019Published11/1/2019 4:56 PMMike DeBennette 847-904-4266On Schedule

​This past week the contractor finished excavating continued and placing aggregate base course in preparation for the new multi-use path. The contractor also placed another section of the new multi-use path.

During the week of November 4th, the contractor plans to continue placing aggregate base course, and pouring concrete to build the new multi-use path. 
11/4/2019Concrete Removals & Excavation
  
2019 Shermer Road multi-use path10/27/2019Published10/21/2019 10:01 AMMike DeBennette 847-904-4266On Schedule

​This past week the contractor removed the existing sidewalk and began excavating for the new multi-use path. The contractor also finished protecting and pruning the remaining trees.

During the week of October 21st, the contractor plans to begin constructing the new multi-use path. The contractor also plans to complete the required fire hydrant replacements.  
10/21/2019Concrete Removals & Excavation
  
2019 Shermer Road multi-use path9/29/2019Published9/27/2019 4:05 PMMike DeBennette 847-904-4266On Schedule

​This past week the contractor began laying out the proposed bike path

During the week of September 23rd, the contractor plans to install the silt fence which will help with erosion control during construction. The contractor also plans to begin pruning and removing the existing trees along the path.
9/23/2019Phase 1 - Project Initiation
1 - 3Next

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.