Spruce-Birchwood Reconstruction


2022 public improvement project

​Contact information

Project Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

The proposed Project includes approximately 0.25 miles of improvements on Spruce Street from Harrison Street to Colfax Avenue, as well as Birchwood Court from Shermer Road to Spruce Street.

The following major improvements are included in the contract:

  • Replacement of approximately 1,000 feet of existing deteriorated water main with new 8-inch diameter
  • Polyvinyl Chloride (PVC) water main. The Improvements will include installation of new 1 1/2-inch copper water service lines and new b-boxes. 
  • Upgrading of 1,000 feet of the storm sewer system, ranging from 12-inch to 24-inch diameter pipe. New gutter will also be installed
  • The proposed sanitary sewer improvements consist of sanitary manhole repairs and replacement of sanitary      services, if necessary. 
  • Reconstruction of existing asphalt pavement and curbs
  • Reconstruction of 5-foot-wide concrete sidewalk

BirchwoodPicture1.png
SprucePicture1.png
Project information and updates​

Contractor: Lenny Hoffman Excavating, Wilmette, Ill.

Budget: $1.2 million

​Preconstruction PowerPoint Presentation: Click here.

Tentative Schedule

  • Bid award -- April 5, 2022
  • Resident preconstruction meeting -- May 5, 2022
  • Approximate start of construction --May 23, 2022
  • Approximate completion of construction -- July 29, 2022

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.​