Contact information
Project Manager: Tom Hagerty
(847) 904-4421
thagerty@glenview.il.us
Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us
Project description
Improvements on Spruce Street from Dewes Street to Glenview Road and the east and west alleys include:
- Improve existing storm sewer system
- Construct new asphalt roadway including the alleyways, including curb and gutter construction on Spruce Street only
- Restore the parkway
Project information and updates
Contractor: TBD
Budget: $450,000
Project number: E20-0022
Location map: Click here
Tentative schedule
- Bid award -- April 2021
- Resident preconstruction meeting -- April 2021
- Tentative construction start -- May 2021
- Tentative completion of construction -- October 2021
Schedule may be revised due to inclement weather or other unforeseen circumstances.
Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. Saturday. Work outside these hours will require Village approval.