The Village of Glenview

Strawberry Lane improvements


2021 public improvement project

​Contact information

Project Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Approximately 950 feet on Strawberry Lane from Winnetka Road to Maple Leaf Drive

  • Replacement of existing deteriorated 6-inch cast iron water main with new 8-inch diameter Polyvinyl Chloride (PVC) water main
  • Upgrade existing storm sewer system
  • Complete sanitary sewer repairs, including manhole repairs and pipe replacement​
  • Resurface asphalt roadway, including​ spot curb and gutter repairs
  • Restore the parkway with sod

See this PowerPoint presentation

Project information and updates​

Contractor: DiMeo Brothers Inc.

Budget: $1,284,​026 (bid with Larch Avenue project)

Project Number: E20-0026

Location map: ​Click here

Tentative Schedule

  • Bid award -- February 16, 2021 (Read Staff Report)
  • Resident preconstruction meeting -- March 5, 2021
  • Approximate start of construction --April 2021
  • Approximate completion of construction -- August 15,​ 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
North Glen Oak Acres stormwater improvements12/5/2020Published11/25/2020 8:35 AMTom Hagerty 847-904-4421Completed

​This past week the contractor finished installing the new sidewalk on Wagner Road. The contractor also began restoring the parkway. 

During the week of November 30, the contractor plans to continue project clean up and restoring the parkway. The contractor is tentatively scheduled to finish restoring the parkway Friday November 27.

Good News! The project is completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.
Thank you for your patience. 



11/29/2020Project Completion
  
North Glen Oak Acres stormwater improvements11/28/2020Published11/20/2020 10:08 AMTom Hagerty 847-904-4421On Schedule

​This past week the contractor completed various outstanding items and prepared for the sidewalk installation along Wagner Road.

During the week of November 23, the contractor plans to continue project clean up and begin restoring the parkway. The contractor will not be working Thursday November 26 due to the holiday. The contractor is tentatively scheduled to finish restoring the parkway Friday November 27.

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. 



11/22/2020Phase 3 - Parkway Restoration
  
North Glen Oak Acres stormwater improvements11/21/2020Published11/13/2020 2:10 PMTom Hagerty 847-904-4421On Schedule

​This past week the contractor finished the storm sewer upgrades on Wagner Road. The contractor also completed the asphalt repair work on De L’oiger Drive, Woodlawn Road, and Wagner Road.

During the week of November 16, the contractor plans to complete various outstanding items and prepare for the sidewalk installation along Wagner Road.

Throughout this phase of construction, the contractor will be working in the street and parkway. We ask that you please do not park on the street during construction hours, which are from 7 AM to 7 PM. 
Thank you for your patience. 



11/15/2020Phase 2 - Roadway Reconstruction
1 - 3Next

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.