The Village of Glenview

Strawberry Lane improvements


2021 public improvement project

​Contact information

Project Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Approximately 950 feet on Strawberry Lane from Winnetka Road to Maple Leaf Drive

  • Replacement of existing deteriorated 6-inch cast iron water main with new 8-inch diameter Polyvinyl Chloride (PVC) water main
  • Upgrade existing storm sewer system
  • Complete sanitary sewer repairs, including manhole repairs and pipe replacement​
  • Resurface asphalt roadway, including​ spot curb and gutter repairs
  • Restore the parkway with sod

See this PowerPoint presentation

Project information and updates​

Contractor: DiMeo Brothers Inc.

Budget: $1,284,​026 (bid with Larch Avenue project)

Project Number: E20-0026

Location map: ​Click here

Tentative Schedule

  • Bid award -- February 16, 2021 (Read Staff Report)
  • Resident preconstruction meeting -- April 29, 2021
  • Approximate start of construction --May 10, 2021
  • Approximate completion of construction -- August 15,​ 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
Strawberry Lane improvements5/15/2021Published5/7/2021 7:32 AMTim Schwister 847-904-4422On Schedule

​Welcome to the project updates pages for the Strawberry Lane Improvements Project. Project updates will typically be posted on Fridays of each week. The contract was awarded to DiMeo Brothers. If you have any questions about the project or project updates please contact the project manager, Tim Schwister, by email tschwister@glenview.il.us or phone (847) 904-4422.

During the week of May 10, the contractor will begin Phase I, the underground improvements portion of this project. During this phase the contractor will be installing new storm sewer, sanitary sewer mainline and services, and water main, water services, and b-boxes. The contractor will begin this phase by installing the new water main. 

Throughout this phase of construction, the contractor will be working in the street and parkway. Please note that construction hours are 7AM to 7PM Monday through Friday and 9AM to 5PM on Saturday, if necessary. 
Thank you for your patience. 



5/9/2021Start of Construction

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.