Strawberry Lane improvements


2021 public improvement project

​Contact information

Project Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Approximately 950 feet on Strawberry Lane from Winnetka Road to Maple Leaf Drive

  • Replacement of existing deteriorated 6-inch cast iron water main with new 8-inch diameter Polyvinyl Chloride (PVC) water main
  • Upgrade existing storm sewer system
  • Complete sanitary sewer repairs, including manhole repairs and pipe replacement​
  • Resurface asphalt roadway, including​ spot curb and gutter repairs
  • Restore the parkway with sod

See this PowerPoint presentation

Project information and updates​

Contractor: DiMeo Brothers Inc.

Budget: $1,284,​026 (bid with Larch Avenue project)

Project Number: E20-0026

Location map: ​Click here

Tentative Schedule

  • Bid award -- February 16, 2021 (Read Staff Report)
  • Resident preconstruction meeting -- April 29, 2021
  • Approximate start of construction --May 10, 2021
  • Approximate completion of construction -- August 15,​ 2021

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
2021 Strawberry Lane improvements8/5/2021Published7/30/2021 12:19 PMTim Schwister 847-904-4422On Schedule

This past week the contractor placed the final layer of asphalt on Strawberry Lane.

Good News! The project is completed, and this will be the final blog post for the project. We hope you found the information helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.
We appreciate your patience. ​


7/30/2021Project Completion
  
2021 Strawberry Lane improvements7/31/2021Published7/23/2021 4:14 PMTim Schwister 847-904-4422On Schedule

This past week the contractor completed installing  the sod. The contractor also plans to adjust the manholes and complete the standardized testing of the newley installed underground utilities.

During the week of July 26, the contractor tentatively plans to oil and sand the road on Tuesday in anticipation of paving the final layer of asphalt on Wednesday. This work is dependent on favorable weather.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.
Thank you for your patience. ​


7/25/2021Phase 2 Roadway Reconstruction
  
2021 Strawberry Lane improvements7/24/2021Published7/16/2021 4:13 PMTim Schwister 847-904-4422On Schedule

This past week the contractor completed landscaping preparation and is scheduled to place the sod the week of July 19.  The contractor tentatively plans to mill the top two inches of  existing asphalt pavement.

During the week of July 19, the contractor tentatively plans to place the final layer of surface.

Throughout this phase of construction, the contractor will be working in the street and parkway. Construction hours are from 7 am to 7 pm Monday through Friday and 9 am to 5 pm on Saturdays, if necessary.
Thank you for your patience. ​


7/18/2021Phase 3 Parkway Restoration
1 - 3Next

​Find all project updates here.​​

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.