The Village of Glenview

Surrey Lane-Forestview Lane-Barton Court improvements


2021 public improvement projects

​Contact information

Project Manager: Tim Schwister
(847) 904-4422
tschwister@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements​ to Surrey Lane from Central Road to Glenview Road, about 1,430 feet; Forestview Lane from Surrey Lane to the west cul-de-sac and Barton Court include:

  • Replacing existing water main with new 8-inch diameter Polyvinyl Chloride (PVC) water main
  • Upgrading existing storm sewers
  • Repairing existing sanitary sewers
  • Installing new concrete curb and gutter on Surrey and Forestview only
  • Construction new asphalt pavement

See the PowerPoint from the December 3, 2020 Design Open House here.

Project information and updates

Contractor: Lenny Hoffman Excavating of Wilmette

Budget: $2,883,556 (bid with North Glenayre Drive project)

Location map: Click here

Tentative schedule

  • Bid award -- May 4, 2021
  • Preconstruction meeting --May 12, 2021
  • Approximate construction start -- June 1, 2021
  • Estimated completion date -- October 29, 2021​

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours: 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.