The Village of Glenview

Covert Road/Briarhill Road reconstruction


2020 public improvement project

​Contact information

Project Manager: Mike DeBennette
(847) 904-4266
mdebennette@glenview.il.us

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements to Covert Road from Shermer Road to Briarhill Road and Briarhill Road from Central Road to the south cul-de-sac include: 

  • installing 8-inch Polyvinyl Chloride (PVC) water main and water services
  • installing 12-inch to 24-inch storm sewer to improve storm water conveyance
  • sanitary pipe repairs, removal and replacement of sanitary sewer manholes and service replacements, if necessary
  • pavement improvements, including removal and replacement of the existing curb and gutter and concrete pavements with installation of new asphalt pavement.

Project information and updates​

Please note​​​Contractors and construction workers will follow these guidelines to keep themselves and the public safe during the COVID-19 pandemic.

Contractor: DiMeo Brothers Inc. of Elk Grove Village

Budget: $2,187,726 (with Greenbriar Drive improvement project)

Location map: Click here

Tentative schedule

  • ​Bid award: March 3, 2020
  • Preconstruction meeting: March 17, 2020
  • Tentative construction start: April 6, 2020
  • Tentative construction completion: July 10, 2020

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are from  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval.

  
  
  
  
  
  
  
Update
  
  
  
Covert Road Briarhill Road reconstruction8/22/2020Published8/14/2020 4:53 PMTom Hagerty 847-904-4421Completed

This past week the contractor placed the final layer of asphalt.

Good News! The project is completed and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the current status of the project and upcoming work.

The Village of Glenview will provide surveys in the coming weeks for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.

8/16/2020Project Completion
  
Covert Road Briarhill Road reconstruction8/15/2020Published8/8/2020 7:11 AMTom Hagerty 847-904-4421On Schedule

This past week the contractor was not working onsite.

During the week of August 8, the contractor will prepare Covert Road and Briarhill Road for the final layer of asphalt. The final layer of asphalt is tentatively scheduled for the week of August 17.

Thank you for your patience.

8/9/2020Phase III - Parkway Restoration
  
Covert Road Briarhill Road reconstruction8/8/2020Published7/31/2020 9:24 AMTom Hagerty 847-904-4421On Schedule

This past week the contractor finished preparing the parkway for sod. Sod may not be installed until temperatures are conducive for sod placement. 

During the week of August 3, the contractor will not be working onsite. 
Thank you for your patience. 



8/2/2020Phase 3 - Parkway Restoration
1 - 3Next

​Find all project updates here.

 ​

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.