The Village of Glenview

Lilac Avenue water improvements


2020 public improvement project

​​Contact information

Engineering Division Manager: Adriana Webb
(847) 904-4414
awebb@glenview.il.us

Project description

Improvements include installation of 8-inch Polyvinyl Chloride (PVC) water main and water services and 23-inch to 36-inch storm sewer to improve storm water conveyance; removal and replacement of curb and gutter and concrete pavement with new asphalt pavement on Lilac Avenue from Magnolia Street to Maple Street.

​Project information​

Contractor: DiMeo Brothers

Budget:$1,728,895 (includes Russet Way work in 2021)

Location map: Click here

Tentative schedule

  • Contract awarded: September 1, 2020
  • Pre-construction meeting -- September 10, 2020
  • Approximate start of construction -- September 14, 2020
  • Approximate completion of construction -- December 15, 2020

Schedule may be revised due to inclement weather or other unforeseen circumstances.

Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m.  Saturday. Work outside these hours will require Village approval. ​​


 

  
  
  
  
  
  
10/23/2020 12:47 PMKim Wenzel11/25/2020 12:00 AMOn Schedule
  
10/16/2020 9:35 AMKim Wenzel11/25/2020 12:00 AMOn Schedule
  
10/9/2020 1:31 PMKim Wenzel11/25/2020 12:00 AMOn Schedule
  
10/2/2020 11:40 AMKim Wenzel11/25/2020 12:00 AMOn Schedule
  
9/25/2020 6:00 PMKim Wenzel11/25/2020 12:00 AMOn Schedule
  
9/18/2020 9:28 AMKim Wenzel11/25/2020 12:00 AMOn Schedule

​Find all project updates here.

 

To sign up for future notifications on this project, fill out the form below. We will email updates on this project when they are available.