Huckleberry Lane Improvements

2024 public improvement project

Road construction
Location Map
Location Map
Huckleberry Improvements
Huckleberry Improvements
 

The proposed project includes approximately 1,180 feet of improvements on Huckleberry Lane from Wagner Road to west cul-de-sac.


The following major improvements are included in this project:


  • ​Installation of 1,180 feet of new 8-inch Polyvinyl Chloride (PVC) water main with new 1 ½-inch water service lines and b-boxes
  • Installation of 1,300 feet of both PVC and RCP storm sewer, including new storm sewer service stubs to all properties through the Special Service Area.
  • Culvert removal under existing driveways
  • Sanitary service replacements
  • Curb & gutter installation through Special Service Area.
  • Road reconstruction with asphalt pavement
  • Parkway restorations with sod


Tentative Schedule
  • Design open house – November 9, 2023
  • Bid award date – Anticipated March 2024 
  • Resident pre-construction meeting – TBD
  • Approximate starting date of construction – May 2024​
  • Approximate completion of construction – August 2024


Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.​


Capital Improvement Program

Road Barricades

The Village annually updates its five-year Capital Improvement Program.


2024-28 Capital Improvement Program map


2024-28 Capital Improvement Program list


2024-28 CIP Story Map

Huckleberry Lane At-A-Glance

Contractor: Pirtano Construction of Elmhurst, Illinois


Budget: $1.68 million

Huckleberry Lane Project Library

Resolution Awarding Contract to Pirtano Construction | Resolution
Design Open House Handout | Click here to open
Design Open House Notice | Click here to open

Adriana Webb

Engineering Division Manager

(847) 904-4414