2024 Road Resurfacing Projects

2024 public improvement project

road resurfacing
road resurfacing
 

The 2024 road resurfacing project includes resurfacing of 19 street sections and one alley, as well as the implementation of the annual MARS Program. The MARS program consists of asphalt resurfacing of sections of streets that are less than a complete roadway resurfacing and more than a pothole patching.

The following major improvements are included in this contract: 


  • Road resurfacing
  • Sidewalk spot repairs
  • Curb and gutter spot repairs
  • Parkway restoration


The following street sections are planned for asphalt resurfacing in 2024:





Tentative Schedule

Bid notice: February 29, 2024

Bid opening date: March 14, 2024

Approval of “Resolution for Improvement by Municipality Under the Illinois Highway Code" by the Village President: March 19, 2024

Bid award: March 19, 2024

IDOT approval of contract: To be determined.

Approximate starting date of construction: June, 2024

Approximate completion date of construction: August, 20234


Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.​

Capital Improvement Program

Road Barricades

The Village annually updates its five-year Capital Improvement Program.


2024-28 Capital Improvement Program map


2024-28 Capital Improvement Program list


2024-28 CIP Story Map

Road Resurfacing At-A-Glance

Contractor: Builders Paving LLC, of Hillside, Illinois,


Budget: $2,788,968



Eric Pugh

Project Manager

(847) 904-4235

Adriana Webb

Engineering Division Manager

(847) 904-4414