Bellwood Lane Sidewalk

2024 public improvement project

Location Map
Before
Prepping for installation
Pouring Cement
Creating Sidewalk
 

The proposed Project includes approximately 1,300 feet of improvements on Bellwood Lane from West of Longmeadow Drive to Greenwood Road.



The following major improvements are included in this project:


  • Installation of approximately 13,000 square feet of sidewalk on both the north and south sides of Bellwood Lane
  • Greenwood Road crosswalk improvements
  • Parkway restoration with sod


Tentative Schedule


  • Design open house – November 9, 2023
  • Bid award – Anticipated February 2024
  • Design pre-construction meeting – TBD
  • Approximate starting date of construction – April 2024
  • Approximate completion of construction – May 2024



Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.






Capital Improvement Program

Road Barricades

The Village annually updates its five-year Capital Improvement Program.


2024-28 Capital Improvement Program map


2024-28 Capital Improvement Program list


2024-28 CIP Story Map

Bellwood Sidewalk At-A-Glance

  • Contractor: DiMeo Brothers Inc. of Elk Grove Village, Illinois    
  • Budget: $350,000

Bellwood Lane Document Library

Pre-Construction Meeting Notice | Click here to open | Design Meeting Handout

Project Contacts

Project Manager: Eric Pugh, Project Manager

(847) 904-4235

epugh@glenview.il.us


Engineering Inspector: Dayvohn Braxton

(847) 904-4238

dbraxton@glenview.il.us


Engineering Division Manager: Adriana Webb

(847) 904-4414

awebb@glenview.il.us