Business and Development
- Master Plans and Studies
- Development Center
- Licenses & Permits
-
Construction Projects
- Development Projects
- Doing Business in Glenview
- Downtown Glenview Revitalization
- Code Enforcement & Property Maintenance
- Commercial Remodeling & Alterations
- Residential Inspections
- Commercial Inspections
- Comprehensive Plan
- Public Health Services
Wagner Road Improvements
2024 public improvement project
The proposed Project includes approximately 0.45 miles of improvements on Wagner Road from East Lake Avenue to Kenilworth Lane.
The following major improvements are included in this project:
- Installation of 2,500 feet of new 8-inch Polyvinyl Chloride (PVC) water main with new 1 ½-inch water service lines and b-boxes
- Sidewalk removal and replacement
- Pavement patching
- Parkway and driveway restoration of areas affected during construction
Tentative Schedule
- Bid award date – March 2024
- Resident pre-construction meeting – TBD
- Approximate starting date of construction – April 2024
- Approximate completion of construction – June 2024
Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are 7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.
August 16, 2024 08/19/2024
The week of August 12 the contractor worked on landscape restoration by placing sod in areas that were affected by construction.
Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.
The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.
August 9, 2024 08/09/2024
The week of August 5 the contractor completed the sidewalk and curb replacement at select locations. Once completed there will be little work until the weather is more conducive for sod placement.
Please watch for further information via the project website at: https://www.glenview.il.us/construction-projects or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.
August 2, 2024 08/02/2024
The week of July 22 the contractor completed the sidewalk and curb replacement at select locations. Once completed there will be little work until the weather is more conducive for sod placement.
Please watch for further information via the project website at: https://www.glenview.il.us/construction-projects or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.
July 26, 2024 07/26/2024
The week of July 22 the contractor will complete the sidewalk and curb replacement at select locations. Once completed there will be little work until the weather is more conducive to sod placement.
Please watch for further information via the project website at: https://www.glenview.il.us/construction-projects or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.
July 19, 2024 07/19/2024
The week of July 15 the contractor began preparing for the select curb and sidewalk replacement.
The week of July 22 the contractor will complete the sidewalk and curb replacement at select locations. Once completed there will be little work until the weather is more conducive to sod placement.
Please watch for further information via the project website at: https://www.glenview.il.us/construction-projects or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.
Landscaping 07/12/2024
During the week of July 8, the contractor continued shaping and grading the parkway where it was damaged due to construction. The contractor will not place the new sod until temperatures are more conducive for the sod to grow.
There will not be any further updates until there is additional activity on Wagner Road.
The week of July 15, there will be little work on Wagner as the contractor waits for more favorable weather to put down sod. Expect sod to be placed and sidewalk and curb repair to be completed in the next coming weeks.
Please watch for further information via the project website at: https://www.glenview.il.us/construction-projects or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.
July 5 Update 07/05/2024
The week of July 1, the contractor has finished repairing driveways and patching the pavement.
During the week of July 8, the contractor will begin shaping and grading the parkway where it was damaged due to construction. This entails removing any construction debris and excavating down four inches and placing topsoil in anticipation of sod.
Please watch for further information via the project website at: https://www.glenview.il.us/construction-projects or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.
June 26 Update 07/01/2024
The week of June 24, the contractor has begun patching the road where the new water main was installed. This is anticipated to be completed by the end of the week.
The week of July 1, the contractor will begin parkway restoration. This entails prepping and grading the parkway in order to place topsoil and then sod in these area’s once weather is more conducive for sod.
We appreciate your patience during the construction process.
Please watch for further information via the project website at: https://www.glenview.il.us/construction-projects or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235.
May 24 Update 05/24/2024
The week of May 20, 2024, the contractor continued installing new water main going north from Wagner court working north towards Kenilworth Lane.
The week of May 28, 2024, the contractor will continue installing new water main along the east side of Wagner Road, and start water main pressure and chlorination testing.
We appreciate your patience during the construction process.
Please watch for further information via the project website here or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235
May 17 Update 05/17/2024
The week of May 13, 2024, the contractor continued installing new water main going north from Wagner court working north towards Kenilworth Lane.
The week of May 20, 2024, the contractor will continue installing new water main along the east side of Wagner Road.
We appreciate your patience during the construction process.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235
Phase I Underground Work 05/03/2024
The week of April 29, the contractor will begin installing the new water main. Traffic will be one lane at times, please watch for flaggers to help direct traffic. The contractor is planning to start on the South end of the project near East Lake Avenue and work to the North. The water main work is anticipated to take approximately three weeks to complete.
The week of May 6, 2024 the contractor will continue installing new water main working from the South to the North.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235
Phase I Construction Water Main Installation 04/26/2024
The week of April 22, the contractor will continue mobilization for the project. This includes utility markings, layout and pavement saw cutting in advance of the new water main. The contractor will also stage material throughout the project including pipe and manholes.
The week of April 29, the contractor will begin installing the new water main. Traffic will be one lane at times, please watch for flaggers to help direct traffic. The contractor is planning to start on the South end of the project near East Lake Avenue and work to the North. The water main work is anticipated to take approximately three weeks to complete.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235
Phase I Underground Work 04/19/2024
The week of April 15, the contractor will continue mobilization for the project. This includes utility markings, layout and pavement saw cutting in advance of the new water main. The contractor will also stage material throughout the project including pipe and manholes.
The week of April 22, the contractor will begin preparing for the new water main installation. The contractor will install pits to install the water main with the HDD method (Horizontal Directional Drilling). Traffic will be one lane at times, please watch for flaggers to help direct traffic. The contractor is planning to start on the South end of the project near East Lake Avenue and work to the North. The water main work is anticipated to take approximately four weeks to complete.
If you have any questions about the project or project updates please contact the project manager, Eric Pugh, by email epugh@glenview.il.us or phone (847) 904-4235
YOUR EMAIL ADDRESS IS SUCCESSFULLY REMOVED FROM UPDATE ALERT LIST.
Capital Improvement Program
The Village annually updates its five-year Capital Improvement Program.
2025 Capital Improvement Program Map
2025-2029 Capital Improvement Program Map
2025-2029 Capital Improvement Program List
You can make suggestions and leave feedback about conditions of infrastructure for the next CIP by dropping a pin in this interactive map.
Wagner At-A-Glance
Contractor: PirTano Construction of Elmhurst, Illinois
Budget: $1.5 million
Wagner Project Library
Tim Schwister
Project Manager
(847) 904-4422Adriana Webb
Engineering Division Manager
(847) 904-4414What can we help you with today?
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor, sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum, dolor sit.
-
Lorem, ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.
-
Lorem ipsum dolor sit.