August 2, 2024 08/02/2024
The week of July 29, Commonwealth Edison contractor completed the preliminary work for the power upgrade to the area. There is still some minor landscaping that is still to be completed once temperatures are more conducive for landscaping.
Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.
If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.
July 26, 2024 07/26/2024
The week of July 22 the contractor completed the installation of the underground storm water detention system. Furthermore, the contractor has reinstated the damaged curbs as well as completed the installation of the new asphalt on Pine Street. Pine street was opened to traffic on Friday July 26, 2024.
The week of July 29, the contractor will place pavement striping on Pine Street. Commonwealth Edison contractor will still be completing the preliminary work for the power upgrade to the area.
Please watch for further information via the project website at:
https://www.glenview.il.us/construction-projects Please watch for hand delivered notices as construction begins.
If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.
July 19, 2024 07/19/2024
The week of July 15, the contractor closed Pine Street between Glenview Road and Prairie Street. Parking is available in the 1850 Glenview Road Parking lot or along the railroad tracks along Depot Street. The contractor began excavating for the new underground storm water detention system.
The week of July 22 the contractor will complete the installation of the underground storm water detention system. Furthermore, the contractor will reinstate the damaged curbs as well as install the new asphalt on Pine Street. This work is anticipated to be completed by July 26. Commonwealth Edison will continue with the electrical upgrades for the next several weeks. Please watch for daily lane closures.
Please watch for further information via the project website at:
https://www.glenview.il.us/construction-projects Please watch for hand delivered notices as construction begins.
If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.