July 5 Update 07/05/2024
The week of July 1st the contractor finished restoration and finished paving asphalt.
Good News! The project is substantially completed, and this will be the final blog post for the project. We hope you found the information to be helpful and insightful regarding the status of the project and upcoming work.
The Village of Glenview will provide surveys in the future for you to complete regarding the construction work and notifications provided. Please take a few moments to complete this survey. The information will allow us to know what aspects of the project we are doing well at and which areas we need to improve upon in the future.
If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421 or Dayvohn Braxton at dbraxton@glenview.il.us or 847-904-4238.
June 26 Update 07/01/2024
The week of June 24 the contractor plans on placing sod and restoring the parkway. The contractor will place topsoil and restore every area that was disturbed during construction.
Monday July 1, 2024, the road will be cleaned and primed in advance of the final layer of asphalt. The prime coat helps the final layer of asphalt bond to the existing layer. The prime coat will be dry in approximately 15 minutes. The final layer of asphalt paving is planned for Tuesday July 2. The work is dependent on favorable weather conditions and will be postponed to the next favorable day if rain is in the forecast.
If you should have any questions, please don’t hesitate to contact us. The above dates are based on acceptable weather, if we have rain days the schedule may change.
Throughout this phase of construction, the contractor will be working in the street and parkway.
Please watch for further information via the project website at: https://www.glenview.il.us/construction-projects or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421 or Dayvohn Braxton at dbraxton@glenview.il.us or 847-904-4238.
Project Initiation 05/07/2024
Welcome to the project updates page for the Linneman and Elm Street Reconstruction Project. Project updates will typically be posted on Fridays of each week. The contract was awarded to DiMeo Brothers Inc. of Elk Grove Village Illinois.
During the week of February 26, 2024, the contractor will begin mobilization for the project. This includes utility markings and layout and pavement saw cutting in advance of the new water main and storm sewer. The contractor will also stage material throughout the project including pipe and manholes.
The week of March 4, 2024, the contractor will begin installing new water main tentatively beginning at Elm Street and work towards Harlem Avenue. Installation of the new water main is anticipated to take four weeks.
Please remember these dates are dependent on suitable weather.
Please watch for further information via the project website at
or by hand delivered notices.
If you have any questions about the project or project updates please contact the project manager, Tom Hagerty, by email thagerty@glenview.il.us or phone (847) 904-4421.