Cedarwood Lane & Sumac Circle Improvements

2024 public improvement project

road construction
 

The proposed project includes approximately 600 feet of improvements on Cedarwood Lane from Linden Leaf Drive to Fir Street, and approximately 700 feet of improvements on Sumac Circle from the west cul-de-sac to the east cul-de-sac.


The following major improvements are included in this project:


  • Installation of approximately 1,200 feet of 8-inch Polyvinyl Chloride (PVC) water main with new 1.5-inch service and b-boxes on Cedarwood Lane and Sumac Circle
  • Storm sewer improvements include installation of 850 feet of 12-inch, 16-inch and 18-inch storm sewer
  • Sanitary sewer improvements, including pipe and manhole repairs and replacement of sanitary services, if necessary
  • New curb and gutter
  • Road reconstruction with asphalt pavement
  • Parkway restorations with sod
Tentative Schedule
  • Design open house – October 16, 2023​
  • Bid award - Anticipated February 2024
  • Resident pre-construction meeting – TBD
  • Approximate stating date of construction – May 2024
  • Approximate completion of construction – August 2024

Schedule may be revised due to inclement weather or other unforeseen circumstances. Work hours are  7 a.m. to 7 p.m. Monday through Friday and 9 a.m. to 5 p.m. on Saturday. Work outside these hours will require Village approval.

Capital Improvement Program

Road Barricades

The Village annually updates its five-year Capital Improvement Program.


2024-28 Capital Improvement Program map


2024-28 Capital Improvement Program list


2024-28 CIP Story Map

Cedarwood & Sumac At-A-Glance

Contractor: Dimeo Brothers, Inc. of Elk Grove Village, Illinois 


Budget: $1.58 million

Cedarwood & Sumac Project Library

Design Open House Handout | Click here to open
Design Open House Notice | Click here to open

Eric Pugh

Project Manager

(847) 904-4235

Adriana Webb

Engineering Division Manager

(847) 904-4414